Commission Memorandum
REPORT TO: Honorable Mayor and City Commission FROM: Brian Heaston, Project Engineer
Craig Woolard, Director of Public Works
SUBJECT: Contract Award to Williams Brothers Construction for the WRF Small Works Project No. 1.
MEETING DATE: August 28, 2017
AGENDA ITEM TYPE: Action RECOMMENDATION: Authorize the City Manager to sign the Notice of Award for the WRF
Small Works Project No. 1 to Williams Brothers Construction for Bid Items No. 1, 3, 4, 5, 6 (Bid
Item No. 2 is excluded) in the amount of $838,800. RECOMMENDED MOTION: I hereby move to direct the City Manager to sign the Notice of Award for the WRF Small Works Project No. 1 to Williams Brothers Construction for Bid Items
No. 1, 3, 4, 5, and 6, in the amount of eight hundred thirty eight thousand, eight hundred dollars,
and exclude Bid Item No. 2 from the award. BACKGROUND: WRF Small Works Project No. 1 consists of the following 6 individual capital improvement items packaged together into a single construction contract.
Bid Item No. Description
1 WAS Pumps Replacement
2 Secondary Clarifier Improvements (new launder covers, replacement scum baffles and weirs)
3 Digester No. 3 Piping Modifications at the Solids Handling Building
4 Modifications to Hot Water Supply and Return Piping
5 Rehabilitation of Digesters No. 1 and No. 2 and Membrane Roof Replacement for Digesters No. 1 and No. 2 and Digester Control Bldg No. 1
6 Cleaning of Digester No. 1 Contents
Bids were opened on August 1, 2017. One bid was received, and with a total price of $1,214,000, significantly exceeded the $866,718 engineer’s estimate. It appears that the construction market in Bozeman is operating at maximum capacity and that the bid prices reflect
352
an imbalance in supply and demand. We do not hold out hope that a more favorable price would
be received if the project is re-advertised for bid as there are no signals that the overall demand for work in the Bozeman area will be shrinking anytime soon. Should the City Commission adopt Resolution 4840 (budget amendment to the wastewater fund
for the WRF Small Works Project), $850,000 of funding will be available for construction. This
funding amount will allow five of the six bid items to be awarded (Bid Items No. 1, 3, 4, 5, and 6 in the amount of $838,000). Bid Item No. 2, secondary clarifier improvements, is excluded from the award. Although improvements to the secondary clarifiers are presently needed, they are not a priority item relative to the five other bid items in the recommended award. The secondary
clarifier improvements can be bid out again at a later date and packaged together with
rehabilitation work needed on the existing primary clarifiers to create a larger project. The highest priority item in the award is the rehabilitation of primary anaerobic digesters no. 1 and no. 2 and replacement of the membrane roof system over these digesters and digester control
building no. 1. The existing digester mixers require replacement as they are old and not able to
provide effective mixing of digester contents. Poor mixing inhibits the proper operation of the anaerobic digestion process. The existing mixer gas seals at digester 1 have failed and are causing intrusion of a large volume of digester gas into the membrane roof system. Digester gas is explosive if exposed to an ignition source so the gas entrapped under the membrane roof
material is a hazardous situation in need of an immediate fix. Furthermore, the membrane roof
has failed in multiple locations and leaks water into the digester control building and old administration and lab rooms. Full replacement of the roof is necessary to bring these assets into proper repair and set upon a proactive asset management track.
Remaining items in the award include replacement of old waste activated sludge pumps and
installation of new variable frequency motor drives for the new pumps, as well as minor piping modifications at various locations about the WRF. The $850k total funding affords a modest construction contingency of $11,200 which could be
used if conditions encountered during prosecution of the work differ from those precedent in
preparation of the bid and a Change Order is approved. The Notice of Award for the referenced project is attached along with the bid tabulation.
FISCAL EFFECTS: Contract award as recommended would reduce the amended FY17
wastewater fund balance by $838,800. Award at this amount requires Commission approval of Resolution 4840 to make a total of $850,000 available for the project. ALTERNATIVES: As suggested by the Commission
ATTACHMENTS: Notice of Award Bid Tabulation
353
SECTION 00130
NOTICE OF AWARD
Dated 8/28/2017
Project: Bozeman WRF Small Works Project No. 1 Owner: City of Bozeman, Montana Owner's Contract No.:
Contract: Engineer's Project No.: 00…10059730
Bidder: Williams Brother Construction
Bidder's Address: (send Certified Mail, Return Receipt Requested)
1123 Cerise Rd, Billings, MT 59101
You are notified that your Bid dated August 1, 2017 for the above Contract has been considered. You are the
Successful Bidder and are awarded a Contract for:
Bid Items No. 1, 3, 4. 5, 6, are all included. Bid Item No. 2 is excluded.
(Indicate total Work, alternates or sections or Work awarded.) The Contract Price of your Contract is Eight hundred thirty-eight thousand, eight hundred Dollars. ($838,800.00).
(Insert appropriate data if Unit Prices are used. Change language for Cost-Plus contracts.)
5 copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award.
5 sets of the Drawings (and electronic version) will be delivered separately or otherwise made available to you immediately.
You must comply with the following conditions precedent within fifteen days of the date you receive this Notice of Award.
1. Deliver to the Owner 4 fully executed counterparts of the Contract Documents.
2. Deliver with the executed Contract Documents the Contract security Bonds as specified in Section 00100, Instructions to Bidders (Article 20), and General Conditions (Paragraph 2.01 and 5.01) and Supplementary Conditions (Paragraph SC-2.01).
Failure to comply with these conditions within the time specified will entitle Owner to consider you in default, annul this Notice of Award and declare your Bid security forfeited.
Within fifteen days after you comply with the above conditions, Owner will return to you two fully executed
counterparts of the Contract Documents.
Owner
By:
Authorized Signature
Title Copy to Engineer
354
355
356
Bid Tabulation: WRF Small Works Project No. 1 Bid Item No. Description Bid Quantity Unit Unit Price Bid Amount Engineers Estimate1 WAS Pumps Replacement 1 LS 148,800$ 148,800$ 154,141$ 2 Secondary Clarifier Improvements 1 LS 375,200$ 375,200$ 295,820$ 3 Digester No. 3 Piping Modifications at the Solids Handling Building1 LS 20,000$ 20,000$ 14,568$ 4 Modifications to the Hot Water Supply and Return Piping 1 LS 14,800$ 14,800$ 3,326$ 5Rehabilitation of Digesters No. 1 and No. 2 & Membrane Roof for Digesters No. 1 and No. 2 and Digester Control Building No. 11 LS 611,000$ 611,000$ 377,789$ 6 Unit Price for Cleaning of Digester No. 1 520 CY 85$ 44,200$ 21,074$ TOTAL 1,214,000$ 866,718$ Williams Brothers Const.357