HomeMy WebLinkAbout12 - Design Report - Norton East Ranch Ph 2 - Street �i,
LAMORRISON
I iW MAIERLE, INC.
An Employee-Owned Company
STREET DESIGN REPORT
NORTON RANCH EAST SUBDIVISION
PHASE 2
BOZEMAN, MONTANA
December 2012
Prepared For:
Norton Properties, LLC
63020 NE Lower Meadow, Suite A
Bend, OR 97701 �i ijy����i
4
MES R. ,
�-p NICKELSON }I %
O 9063 P.E.
Prepared By: ,
Morrison-Maierle, Inc. r�r,,�UN�A,��;•�`
2880 Technology Boulevard West
Bozeman, Montana 59718
N:\5149\001\Design Docs\Reports\Street Report.docx
Introduction
The Norton Ranch East Subdivision, Phase 2 is a portion of a project that was previously
designed by Engineering, Inc. and approved in 2008 by the City of Bozeman under the project
name of Norton Ranch East Subdivision, Phase 1. Since the approval in 2008, Engineering,
Inc. separated a portion of the original Phase 1 into a new "Phase 1" project using the design
work accomplished during the original Phase 1. The design for Phase 2 uses the original
approved Engineering, Inc. design as a basis and therefore this design report is limited to
providing information to the specific components of Phase 2 and changes that are needed due
to the changes in the City of Bozeman Design Standards. The road section was designed by
Rimrock Engineering, Inc. in a report dated April 26, 2007.
Phase 2 Description
Phase 2 consists of 30 residential lots and a total area of 6.66 acres. It is located directly-west
of the platted Phase 1 and is bounded by May Fly Street on the south, Dragon Fly Street on the
North and a park on the west. The attached exhibit shows the location of Phase 2 relative to the
overall Phase 1 project.
Pavement Section
The approved design report includes a design section of 3 inches of Asphalt, 6 inches of
crushed base and 12 inches of pit run subbase. Based on constructability issues and our
experience in the area our recommendation is to remove the lean clay material overlaying the
poorly graded gravel and build the road section on pit run material above this material. The
boring logs completed for the project indicate that the total depth of top soil and lean clay is
approximately 2.5 to 3 feet deep.
Changes Required Due to Updated Design Standards
No changes in the design are needed to meet the updated design standards.
END
NA5149\001\Design Docs\Reports\Street Report.docx
PRELIMINARY GEOTECHNICAL INVESTIGATION
NORTON EAST RANCH SUBDIVISION
RESI DENTIAL-ttYT-S,—UTI LITI ES-AND-STREETS-
BOZEMAN, MONTANA
April 26, 2007
Project No.13-07-103-01
Prepared for:
Big Sky Land Consulting, PLLC.
5530 Burnt Road
Belgrade, Montana 59714
Prepared by:
,y Rimrock Engineering, Inc.
5440 Holiday Avenue
Y' Billings, Montana 59101
. V
Y
�
A
adjacent structures. A dewatering system should be designed by a competent
engineer with experience with dewatering systems.
• Conventional spread and continuous footings will support the structural loads for the
anticipated buildings if founded in the medium dense to dense native gravels with
sand and cobbles.
These and other conclusions and recommendations, along with restrictions and limitations on
these conclusions, are discussed in the attached report.
We appreciate this opportunity to be of service to you, and look forward to future endeavors. If
you have any questions regarding this report or need additional information or services, please
feel free to call the undersigned.
Sincerely,
RIMROCK ENGINEERING, INC.
M .:..,ai -
• fir_;. . 'E
-v 7 P
ALA
Robert W. Kukes, P.E. QZ Wade.Reynolds
Principal Staff Geologist
Enclosures: Report (3 bound copies)
B-07-103-01 Page 2 of 2 April 26, 2007
Rimrock Engineering, Inc.
PRELIMINARY GEOTECHNICAL INVESTIGATION REPORT
PROPOSED NORTON EAST RANCH SUBDIVISION
RESIDENTIAL LOTS, UTILITIES AND STREETS
BOZEMAN, MONTANA
1.0 INTRODUCTION AND SCOPE
1.1 Proiect Description
This report presents the results of our preliminary geotechnical investigation for the proposed
Norton East Ranch Subdivision which includes residential lots, interior streets, and utilities
shown on the site map, Appendix A (Plate 2). The type of buildings anticipated to be in this
subdivision were not known at the time of this report, but are anticipated to be one to two story
wood frame construction. The project will also include construction of interior subdivision
streets and associated utilities.
Structural loads were not available at the time of this report being issued and were estimated to
have continuous wall loads of 2 to 3 kips per lineal foot for long-term loading conditions for
residential construction. Loads and the type of construction for the commercial buildings (if
I applicable to this subdivision) were not available and should be designed when specific
information becomes available. Cuts and fills for building pad construction may be on the order
of 3 to 4 feet with over excavation requirements in the footing in some locations.
1.2 Purpose and Scope of Work
The purpose of this study is to evaluate the feasibility of the proposed development with respect
to the observed subsurface conditions, and to provide our preliminary geotechnical
recommendations and opinions as outlined in our proposal dated February 15, 2007,
summarized below.
• General soil and groundwater conditions at the project site, with emphasis on how
the conditions are expected to affect the proposed construction;
• Suggested specifications for earthwork construction, including site preparation
recommendations, a discussion of reuse of existing near surface soils as structural
or non-structural fill, and a discussion of remedial earthwork recommendations, if
warranted;
• Recommendations for temporary excavations and trench backfill;
t
B-07-103-01 Page 1 of 12 April 26, 2007
Rimrock Engineering, Inc.
the inclement weather and the inaccessibility of the site with a truck mounted drill rig.
Boring depth was 14.5 feet below the existing ground surface. Test pits were excavated to 8
feet below existing site grades. Locations of the boring and test pits shown on the Site Map
(Plate 2, Appendix A), were chosen by Rimrock Engineering, Inc. These locations should be
considered accurate only to the degree implied by the method used.
Soil conditions encountered are presented on the boring and test pit logs which are included as
Plates 3 through 10. A description of the Unified Soil Classification System used to identify the
site soils and a boring log legend are presented on Plates 11 and 12 (Appendix A).
Field personnel logged the soil conditions exposed in the boring and excavations and collected
bulk samples and driven penetration samples for laboratory testing. Soil samples were-obtained
by driving a 2-inch ID, Standard Penetration Sampler, into the bottom of the boring. The
number of blows required to drive the last 12 inches of an 18-inch drive with a 140-pound
hammer dropping 30 inches is recorded as the blows per foot (Blow Count) on the boring log.
When the sampler was withdrawn from the boring, samples were removed, examined by the
field engineer, labeled and sealed to preserve the natural moisture content for laboratory
testing. After the boring and excavations were completed, they were checked for groundwater
and backfilled with excavated soil using the equipment at hand.
2.2 Laboratory Testing
i
Laboratory testing is useful for evaluating both index and engineering properties of soils.
Typical index tests evaluate soil moisture content, soil particle gradation and plasticity
characteristics. We have performed/will perform laboratory testing on selected soil samples to
assess the following:
• Soil Classification (ASTM D422, D1140, D4318, D2487, and D2488)
• Unit Weight and Moisture Content (ASTM D2937 and D2216)
• California Bearing Ratio (ASTM D1835)
In addition, the following analytical tests were performed by Northern Analytical Laboratories.
• Soluble Sulfate Content
Individual laboratory test results can be found on the boring/excavation logs and on Plates 13
through 16, Appendix A, at the end of this report.
B-07-103-01 Page 3 of 12 April 26, 2007
Rimrock Engineering, Inc.
3.4 Analytical Methods
Field and laboratory data are useful when combined with engineering fundamentals to assess
specific behavior such as bearing capacity, settlement, and other design parameters. The
following approaches were used in developing the conclusions and recommendations presented
in subsequent sections of this report.
• Allowable bearing pressures were computed using Terzaghi's general bearing
capacity formula.
• Settlements were not computed at this time and will be provided when a design level
report is completed.
• Pavement sections were computed using the AASHTO Procedure for Design of
Flexible Pavement Sections.
4.0 CONCLUSIONS
The following conclusions are based on the data collected during this assessment and are
subiect to the limitations stated in this report. These conclusions may change if additional
information becomes available. Based on the results of our study, no severe soil or
groundwater constraints were observed which would preclude development. The following is a
summary of our conclusions.
The 45 acre subdivision encompassed by this report is currently covered by 0.5 to
1.0 feet of topsoil and vegetation. The underlying soils consist of a layer of lean clay
and sandy lean clay ranging in depth from 1.5 to 3.0 feet below the existing site
grades. These fine grained soils are moderately compressible, have a low potential
to swell, have a medium plasticity and were soft to medium stiff. Beneath the clay
layer we encountered gravel with sand and cobbles to the depths explored of 14.5
below existing site grades. Groundwater was encountered in our boring and test pits
at depths ranging from 3.2 to 5.5 feet below existing site grades during our
exploration in March and April 2007.
• Groundwater was encountered in the boring and testpits. Due to the shallow
groundwater elevations, dewatering for utilities and foundation construction will
be required. Our scope of services did not include designing a dewatering system
or the influence of dewatering on existing streets, utilities, or adjacent structures. A
B-07-103-01 Page 5 of 12 April 26, 2007
Rimrock Engineering, Inc.
5.2.2 Temporary Unconfined Excavations
The contractor is ultimately responsible for the safety of workers and should strictly observe
federal and local OSHA requirements for excavation shoring and safety. All temporary slopes
should comply with OSHA requirements for Type A soils near the surface and Type C below
approximately three feet. During wet weather, runoff water should be prevented from entering
excavations.
5.2.3 Temporary Trench Excavation and Backfill
It appears that excavation for footings and utility trenches can be readily made with either a
conventional backhoe or excavator in the native soil. We expect the walls of the footing
trenches in the near surface fine grained soils to stand near vertically without significant
sloughing. If trenches are extended deeper than three feet into the native gravel with sand or
are allowed to dry out, the excavations may become unstable and should be evaluated to verify
their stability prior to occupation by construction personnel. Shoring or sloping of any deep
trench walls may be necessary to protect personnel and provide temporary stability. All
excavations should comply with current OSHA safety requirements for Type A soils near the
surface and Type C below three feet. (Federal Register 29 CFR, Part 1926).
Backfills for trenches or other excavations within pavement areas should be compacted in six to
eight inch layers with mechanical tampers. Jetting and flooding should not be permitted. We
recommend all backfill be compacted to a minimum compaction of 97% of the maximum dry
density as determined by ASTM D698. The moisture content of compacted backfill soils should
be within 2% of the optimum. Poor compaction in utility trench backfill may cause excessive
settlements resulting in damage to the pavement structural section or other overlying
improvements. Compaction of trench backfill outside of improvement areas should be a
minimum of 90% relative compaction
5.3 Foundations
Shallow spread footing foundations may be founded directly on the native gravel with sand and
cobbles. Foundations on the native gravel with sand and cobbles may use an allowable bearing
capacity of 4,000 pounds per square foot. Settlements have not been computed at this time.
Foundations founded in the native gravel may require dewatering during construction. If
structures with concrete basements are anticipated, they will require a permanent dewatering
system.
Exterior foundations should be embedded a minimum of 4 feet below lowest adjacent exterior
finish grade for frost protection and confinement. Interior footings should be bottomed at least
12 inches below lowest adjacent finish grade for confinement. Wall foundation dimensions
should satisfy the requirements listed in the latest edition of the International Residential Code.
Reinforcing steel requirements for foundations should be provided by the design engineer.
B-07-103-01 Page 7 of 12 April 26, 2007
Rimrock Engineering, Inc.
In floor slab areas where moisture sensitive floor coverings are planned, an impermeable
membrane (e.g. 10-mil thick polyethylene) should be placed over the base course to reduce the
migration of moisture vapor through the concrete slabs. The impermeable membrane should be
protected by two inches of fine, moist sand placed both above and below the membrane. The
sand cover will provide protection for the membrane and will promote uniform curing of the
concrete slab. The sand cover should be moistened and tamped prior to slab placement.
5.6 Pavement Sections ��,�y.�-�_��•f" V� 5i� t /
The recommended pavement structural sections for the project presented in Table 2 were
calculated using the AASHTO pavement design procedure. Traffic loading was not available at
the time of this preliminary report and was assumed by Rimrock Engineering, Inc. based on
experience with similar projects. Final pavement sections will be calculated when traffic volume
information is available. In our analysis, we used an ADT of 1200 vehicles per day which
results in a traffic loading condition of 118,573 18-kip equivalent single axle load (18-kip ESAL)
was used for interior subdivision streets for the lifetime of the pavement. A CBR value of 5.5
was used for design of the pavement sections.
TABLE 2
PAVEMENT STRUCTURAL SECTIONS
Traffic Condition Redomme:nded Minimum Structural Section*
Interior Subdivision Streets 3 inches Asphaltic Concrete, 6-inches of 1 1/2 inch Crushed Base
Course and 12 inches of pit run subbase
Aggregate base course thickness may be reduced in each pavement structural section by approximately
20%with the use of a recommended geotextile fabric.
Placement and compaction procedures for materials and construction should conform to the
suggested specifications contained in Appendix B of this report. The sections presented in
Table 2 are based on CBR tests performed on selected samples obtained during our
investigation and should be considered preliminary in nature. We recommend verification of soil
conditions as construction progresses so that appropriate revisions can be made if necessary.
Aggregate base course thickness may be reduced in each alternate pavement structural section
by approximately 20% with the use of Amoco 4553 or 2002 geotextile fabric or comparable
geotextile fabric meeting AASHTO M 288-2000 class 1 requirements. If this alternative is
selected, we can provide addition pavement structural sections.
The asphalt pavement structural sections presented in Table 2 are designed for the assumed
traffic loadings. However, based on our experience in the area, environmental aspects such as
freeze-thaw cycles and thermal cracking will probably govern the life of AC pavements in light
traffic areas. Thermal cracking of the asphalt pavements allows more water to enter the
pavement section which promotes deterioration and increases maintenance costs.
B-07-103-01 Page 9 of 12 April 26, 2007
Rimrock Engineering, Inc.
6.2 Construction Observation/Testing and Plan Review
The recommendations made in this report are based on the assumption that an adequate
program of tests and observations will be made during construction to verify compliance with
these recommendations. These tests and observations should include, but not necessarily be
limited to, the following:
• Observations and testing during site preparation and earthwork.
• Observation of footing trench excavations.
• Observation and testing of construction materials.
• Consultation as may be required during construction.
We also recommend that project plans and specifications be reviewed by us to verify
compatibility with our conclusions and recommendations. Additional information concerning the
scope and cost of these services can be obtained from our office.
The review of plans and specifications and the field observation and testing by Rimrock
Engineering are an integral part of the conclusions and recommendations made in this report. If
we are not retained for these services, the Client agrees to assume Rimrock Engineering's
responsibility for any potential claims that may arise during construction.
7.0 LIMITATIONS
Recommendations contained in this report are based on our field explorations, laboratory tests,
and our understanding of the proposed construction. The study was performed using a mutually
agreed upon scope of work. It is our opinion that this study was a cost-effective method to
evaluate the subject site and evaluate some of the potential geotechnical concerns. More
detailed, focused, and/or thorough investigations can be conducted. Further studies will tend to
increase the level of assurance, however, such efforts will result in increased costs. If the Client
wishes to reduce the uncertainties beyond the level associated with this study, Rimrock
Engineering should be contacted for additional consultation.
The soils data used in the preparation of this report were obtained from boring/testpits made for
this investigation. It is possible that variations in soils exist between the points explored. The
nature and extent of soil variations may not be evident until construction occurs. If any soil
conditions are encountered at this site which are different from those described in this report,
our firm should be immediately notified so that we may make any necessary revisions to our
B-07-103-01 Page 11 of 12 April 26, 2007
Rimrock Engineering, Inc.
APPENDIX A
Plates
Geotechnical Investigation Report
Norton East Ranch Subdivision
EXISTING R
CITY BOUNDARY \ o
`rie.ry sr:Y rs.¢
I /
TP-3 CRTP-4
T -2 O
TP-7
O O O
TP-5 -
N;
JA V�.M
fZ.MLMPRIIt
PROPOSED _ �1Si1�D
EXTERIORLQ4Y<yC• ' Y BOUNDARY �
BOUNDARY
vFIVLC.Ec0."_�.J ,
HIGHINAY 101 ry'`
BOUNDARY
�I
SITE MAP PLATE
Rimrock Engineering, Inc. NORTON EAST RANCH SUBDIVISION Page 1 of 1
5440 Holiday Avenue Bozeman, Montana
Billings,MT 59101 Tel. (406)294-8400 Big Sky Land Consulting, PLLC 2
PROJECT NO. B-07-103-01
Date Completed: 4/20/2007 Logged By: 1Erank
Boring Location: See Site Map Plate 2
Driller: Duneman Construction Drilling Method/Size Backhoe
Elev.Top of Hole: 100 — Total Depth: 8 Groundwater Depth:I Q 4.5
F 1 4.5
u x
CL
Z O o: } o)
u1
w W>r a W DESCRIPTION NOTES
Q = J —J W U
o_ a COw a � L� 00 OU O
w 0 co 0z mU � �
c 0
�_r•'• Ve elated To soil Lean to Fat Clay,Grey,Moist,Stiff,
'g,Plasticity
Lean Cla with Sand Grey,Moist,Stiff,Low/Medium MC=30.5%
as is y, Minus#200=83.7%
Plastic Index=24.1
Poorl Graded Gravel with Sand Grey,MoisWJet,Dense,
° :'• rams ar on- as ic,
)o
0
ss— 5— °
0
�0
b
0
�0
0
End of Test Pit
90— 10
r 85— 15—
a
N
O
a
C7
0
m
0
r=
0
m
C9
O
LOG OF TEST PIT TP-2 PLATE
L03 Rimrock EngineeringNorton East Ranch Subdivision 1 of 1
s Bozeman, Montana
LO
o Drafted By: R. Kukes Project No.: B-07-103-01 Big Sky Land Consulting, PLLC 4
Date: 4/25/2007 File Number:
Rimrock Englneering
Date Completed: 4/20/2007 Logged By: .I Frank
Boring Location: See Site Map, Plate 2
Driller: Duneman Construction Drilling Method/Size: Backhoe
Elev.Top of Hole: 100 Total Depth 8 Groundwater Depth:l Q 35
FY- 2-5
d X
r } o
Q F m a
Q = w w w j J DESCRIPTION NOTES
I— d o-C°
w a 2 �2 00 OV ❑ La
w ❑ u U)Z m�
Ve etated Topsoil Lean Clay, Light Brown,Moist to Wet,
Medium i e ium Plasticity
Lean Clay Light Brown,Moist to Wet,Medium Stiff,
e ium asticity, (CL)
Poo,
ly Graded Gravel with Sand Grey,Wet, Dense,
o ranu ar on- as ic, -
�o
0 `.
95 5
0
�0
0
r ,O
End of Test Pit
go 1a
ro 8s 75
N
N
V
'a
0
m
0
0
ai
0
O
J
LOG OF TEST PIT TP-4 PLATE
o Rimrock En ineerin Norton East Ranch Subdivision 1 of 1
g 9 Bozeman, Montana
Y 6
o Drafted By: R. Kukes Project No.: B-07-103-01
� Big Sky Land Consulting, PLLC
Date: 4/25/2007 File Number:
Rimrock Engineedng
Date Completed: 4/20/2007 Logged By: J Frank
Boring Location: See Site Map, Plate 2
Driller: Duneman Construction Drilling Method/Size: Backhoe
Elev.Top of Hole: 100 Total Depth: 8 Groundwater Depth:1 Q 4.4
F 3.6
a x
m o�
m w
O $ Ld m a w � DESCRIPTION NOTES
da >a m Cw < a 0uJ o nz m CL
u
'• Ve etated To soil Lean Clay, Light Brown/Grey,Moist,
e ium as icity
Lean Clay Light Brown/Grey,Moist,Stiff,Medium
as is y, L)
AnNPoorl Graded Gravel with Silt and Sand Grey,Moist to
° e, erase, Granular on- as ic, )
0
Q Wet @3.5ft MC= 13%
° Minus 4200=5.4%
o Plastic Index=GNP
95— 5
0
°L o
O
Q
o Q
Q
End of Test Pit
90 10
0
85 15—
CV
P
a
c�
0
m
0
r
0
m
0
O
J
LOG OF TEST PIT TP-6 PLATE
o Rimrock En ineerin Norton East Ranch Subdivision 1 of 1
g g Bozeman, Montana
o Q Drafted By: R. Kukes Project No.: B-07-103-01 Big Sky Land Consulting, PLLC v
E2 Date: 4/25/2007 File Number:
Rimrock Engineering
Date Completed: 3/20/2007 Logged By: R R 1.1 F
Boring Location: See Site Map, Plate 2
Driller: Rimrock Engineering Inc. Drilling Method/Size: 3 25"1D -Hollow Stem Auger
Elev.Top of Hole: .100 Total Depth. 14.5 Groundwater Depth:l 5 2
F Z 2.5
W X
Z m W rn
W W o w DESCRIPTION NOTES
Q = J J W Y) > U
m
w o :.'i :�2 oo ° o a
W O Cn U)Z m U � (7
Vo stated To soil Lean Clay,Dark Brown/Black,Moist,
•. .:• Medium Plasticity
IFNLean Clay Brown,Moist,Medium Plasticity,(CL)
PoorI Graded Gravel with Sand Brown,Moist to Wet,
oose, rams ar on- as ic, SP)
0
�O
95 5 °Q
52 A
O
7 O
O
0
,O
°b
O
JQ
U
90— 10
B ;:.
0
,O
o Q
O
o Q
J
O
o Q
- O
ro 85 15
N
End of Boring
a
0
m
o_
r
0
m
0 _
PLATE LOG OF TEST PIT B-8
Rimrock Engineering Norton East Ranch Subdivision 1 of 1
s g g Bozeman, Montana
0 Drafted By: R. Kukes Project No.: B-07-103-01 gig Sky Land Consulting, PLLC 10
2 Date: 4/25/2007 File Number:
LOG SYMBOLS
PERCENT FINER
THANVN BULK BAG SAMPLE 4 (ASTMTHE Test Meth dIEVE C 136)
PERCENT FINER
MODIFIED CALIFORNIA SAMPLER -200 THAN THE NO.200 SIEVE
(2-1/2 inch outside diameter) (ASTM Test Method C 117)
CALIFORNIA SAMPLER LL LIQUID LIMIT
(3 inch outside diameter) (ASTM Test Method D 4318)
STANDARD PENETRATION PLASTICITY INDEX
SPLIT SPOON SAMPLER Pi. (ASTM Test Method D 4318)
(2 inch outside diameter)
El EXPANSION INDEX
GEOPROBE (UBC STANDARD 29-2)
COL COLLAPSE POTENTIAL
ROCK CORE
I
WATER LEVEL UC UNCONFINED COMPRESSION
(level where first encountered) (ASTM Test Method D 2166)
V WATER LEVEL
(level after completion)
SEEPAGE MC MOISTURE CONTENT
(ASTM Test Method D 2216)
GENERAL NOTES
1. Lines separating strata on the logs represent approximate boundaries only. Actual transitions may be gradual.
2. No warranty is provided as to the continuity of soil conditions between individual sample locations,
3.Logs represent general soil conditions observed at the point of exploration on the date indicated.
0 4. In general, Unified Soil Classification System designations presented on the logs were evaluated by visual methods only.
N Therefore,actual designations(based on laboratory tests)may vary.
a
o_
o J
4 LOG KEY PLATE
t Norton East Ranch Subdivision
' Rimrock Engineering Bozeman, Montana
12
Drafted By: R.Rexford Project No.: B-07-103-01
v Big Sky Land Consulting, PLLC
Date: 4/25/2007 File Number:
Copyrighl Rimrock Englneering,Inc 2003
60 70 80 90 10 60
GROUP UNIFIED SOIL CLASSIFICATION /
SYMBOL FINE GRAINED SOIL GROUPS /
OL Organic silts and organic silty
Z clays of low plasticity /
0 Inorganic clayey silts to very // U LINE /A-LINE
Qfine sands of slight plasticity 5 / — __ 50
Q CL Inorganic clays of low /
to moderate plasticity /
J /
OH Organic clays of moderate to high / CH
x plasticity,organic silts /
Inorganic silts and
F-1 _ 40
— clayey slits /
CH Inorganic clays of d
high plasticlty / X
LU
/ Z
3 / 30
/ C1
M r Q
/ J
2 // • a
/ CL
10 - — — 10
/
f
I_ML L r OL
I '
0
10 20 30 40 50 60 70 80 90 100
LIQUID LIMIT(LL)
LEGEND: SOURCE DEPTH LL PL PI DESCRIPTION
• TP-1 2.0 43 21 22 LEAN CLAY with SAND(CL)
m TP-2 1.5 46 22 24 LEAN CLAY with SAND(CL)
A TP-6 4.5 NP NP NP POORLY GRADED GRAVEL with
SILT and SAND(GP-GM)
0
N
V
a
c7
0
M
0
r;
4
m
r PLASTICITY CHART PLATE
W Norton East Ranch Subdivision
Rimrock Engineering Bozeman, Montana 1 of 1
Y14
o Drafted By: R.Rexford Project No.: B-07-103-01 Big Sky Land Consulting, PLLC
ml Date: 4/25/2007 File Number:
r.—Mhl Rim-1,Fnnlnanrinn Inr.2003
PHYSICAL PROPERTIES OF SOIL/AGGREGATE
Client Name: Big Sky Land Consulting,PLLC Project No: B-07-103-01
Address: 5530 Burnt Road Date of Report: 04/24/07
Belgrade,Montana 59714
Project Name: Norton East Ranch Subdivision Sample No: Composite,TP1-B8, 1-4ft.
Project Location: Bozeman, Montana Date Sampled: 04/20/07
Sampled By: Rimrock Engineering, Inc. Type of Soil/Aggregate: Existing Subgrade
Submitted By: Rimrock Engineering, Inc. Source of Sample: Composite,TP1-68, 1-4ft.
CALIFORNIA BEARING RATIO
LABORATORY BEARING RATIO(CBR)
120
I I l
I
100
l
I I
I ,
i
I i
t i !
— I I
n
- 60
0
IJ
I i
40
! 1
I
I I i_ I
20 )
i I
I 1 I I
0
0.000 0.100 0.200 0.300 0 400 0.500
Penetration,Inches
%CBR@0.1" 5.5
California Bearing Ratio-CBR Plate
Rimrock Engineering, Inc. Norton East Ranch Subdivision page 1 of 1
5440 Holiday Avenue Belgrade, Montana
Wlln.p,Montana 59101
Tel (4D6)294-6400 Project No.B-07-102-01 Big Sky Land Consulting, PLLC 16
APPENDIX B
SUGGESTED SPECIFICATIONS FOR
EARTHWORK AND PAVEMENT CONSTRUCTION
NORTON EAST RANCH SUBDIVISION
BOZEMAN, MONTANA
1.0 GENERAL
1.1 Scope - The work done under these specifications shall include clearing,
stripping, removal of unsuitable material, excavation, preparation of natural soils,
placement and compaction of on-site and imported structural fill material, and
placement and compaction of pavement materials.
1.2 _Contractor's Responsibility - A geotechnical investigation was performed for
the project by Rimrock Engineering dated April 26, 2007. The Contractor shall
attentively examine the site in such a manner that he can confirm existing
surface conditions with those presented in the geotechnical report. He shall
satisfy himself that the quality and quantity of exposed materials and subsurface
soil or rock deposits have been satisfactory represented by the Geotechnical
t Engineer's report and Civil Engineer's drawings. Any discrepancy that may be of
prior knowledge to the Contractor or that is revealed through his.investigations
shall be made available to the Owner. It is the Contractor's responsibility to
review the attached report prior to construction. The selection of equipment for
use on the project and the order of work will similarly be his responsibility such
that the requirements included in following sections have been met.
1.3 Geotechnical Engineer - The work covered by these specifications shall be
observed and tested by the Geotechnical Engineer, Rimrock Engineering, who
shall be hired by the Owner. The Geotechnical Engineer will be present during
the site preparation and grading to observe the work and to perform the tests
necessary to evaluate material quality and compaction. The Geotechnical
Engineer shall submit a report to the Owner, including a tabulation of all tests
performed. The costs of retesting of unsuitable work performed by the
Contractor shall be deducted from the payments to the Contractor.
1.4 Standard Specifications - Where referred to in these specifications, "Standard
Specifications" shall mean the current Montana Public Works Standard
Specifications dated March 2003.
t
B-07-103-01 Page 1 of 5 April 26, 2007
Rimrock Engineering, Inc.
3.3 Treatment of Exposed Surface - The ground surface exposed by excavation
shall be scarified to a depth of six inches, moisture conditioned to the proper
moisture content for compaction, and compacted as required for compacted fill.
Recompaction shall be approved by the Geotechnical Engineer prior to placing
fill.
4.0 STRUCTURAL FILL
4.1 Limits — Structural fill, if required for fill beneath foundations should be medium
dense to dense gravel with sand.
4.2 Material —We recommend the-gradation for structural fill be 100% passing-the 3-
inch sieve, 25 to 65% passing the No. 4 sieve, and no more than 20% minus No.
200 sized material. The structural fill should have a liquid limit less than 25 and a
plasticity index less than 15.
4.3 Placement - All fill materials shall be placed in layers of eight inches or less in
loose thickness and uniformly moisture conditioned. The lift should then be
compacted with approved compaction equipment to achieve at least 98% relative
compaction in areas under structure foundations. No fill material shall be placed,
spread, or rolled while it is frozen or thawing, or during unfavorable weather
i
conditions.
4.4 Benching - ! ill placed on slopes steeper than 5 horizontal to 1 vertical shall be
keyed into firm, native soils or rock by a series of benches. Benching can be
conducted simultaneously with placement of fill. However, the method and
extent of benching shall be checked by the Geotechnical Engineer.
4.5 Compaction Equipment - The Contractor shall provide and use sufficient
equipment of a type and weight suitable for the conditions encountered in the
field. The equipment shall be capable of obtaining the required compaction in all
areas, including those that are inaccessible to ordinary rolling equipment.
4.6 Recompaction - When, in the judgment of the Geotechnical Engineer, sufficient
compaction effort has not been used, or where the field density tests indicate that
the required compaction or moisture content has not been obtained, or if
"pumping" or other indications of instability are noted, the fill shall be reworked
and recompacted as needed to obtain a stable fill at the required density and
moisture content prior to placing additional fill materials.
4.6 Responsibility - The Contractor shall be responsible for the maintenance and
protection of all embankments and fills made during the contract period and shall
B-07-103-01 Page 3 of 5 April 26, 2007
Rimrock Engineering,Inc.
Base Rock. The aggregate base materials must be approved by the
Geotechnical Engineer prior to use.
After the subgrade is properly prepared, the aggregate base shall be placed in
layers, moisture conditioned as necessary, and compacted by rolling to at least
95% relative compaction. The compaction thickness of aggregate base shall be
as shown on the approved plans.
8.0 ASPHALT CONCRETE PAVEMENT
8.1 Thickness - The compacted thickness of asphalt concrete shall be shown on the
approved plans.
8.2 Materials - Aggregate materials for asphalt concrete shall conform to the
requirements listed for Type B or Type S-3 bituminous aggregates in Section
02503-2.2.3 of the "Standard Specifications." Asphalt concrete mixes shall utilize
asphalt cement meeting the requirements of Section 02510 of "Standard
Specifications". The Contractor shall submit a proposed asphalt concrete mix
design to the Owner for review and approval prior to paving. The mix design
shall be based on the Marshall Method.
8.3 Placement and Compaction - The asphalt concrete material and placement
procedures shall conform to appropriate sections of the °Standard
Specifications." The asphalt concrete material shall be compacted to a minimum
of 92% of the Theoretical Maximum Rice Specific Gravity.
B-07-103-01 Page 5 of 5 April 26, 2007
Rimrock Engineering, Inc.
APPENDIX C
Application for Authorization to Use