HomeMy WebLinkAbout17- Guaranteed Maximum Price Amendment 3 - Dick Anderson Construction, Inc. - Bozeman Sports Park Mass GradingATTACHMENT B f.The general condition cost in our spreadsheet is based on a project duration of 2 months. Additional general condition costs will be added as scope from other trades are added to our contract. 3.Our proposed GMP as per exhibit A is $835,750.16. Please reference the spreadsheet exhibit A for a breakdown of the bid package cost, contingency and construction manager fee. Scope of work contained in the bid package lA can be found in the project manual under instructions to bidders. 4.The anticipated date of substantial completion is August 24th, 2017. 5.Our GMP must be accepted and approved by June 14th, 2017 for the above to become valid. If you have any questions or required additional information on the items above, please give me at (406) 360-6673. We are excited to break ground on this project. Sincerely, Louie Miller Project Manager Dick Anderson Construction CC: Zachary Lowe, PE, Dowl 3424 HIGHWAY 12 EAST, HELENA, MONTANA 59601 406-443-3225 FAX 406-443-1537 4610 TRI-HILL FRONTAGE ROAD, GREAT FALLS, MONTANA 59404 406-761-8707 FAX 406-761-3134 4498 JACKRABBIT LANE, BOZEMAN, MONTANA 59718 406-586-0889 FAX 406-388-4263 PO BOX 31511, BILLINGS, MONTANA 59107 406-248-3700 Exhibit A laJProposed GMP amdendment for Bozeman Sports Park 1A Mass Grading Bozeman Sports Park phase lA Mass Grading DAC Project#: 02-16-238 Location: Bozeman GMP #: 3 Contractor: Dick Anderson Construction Date: June 2, 2017 Address: 1500 Clark Fork Drive, Missoula, 59808 Phone: 360-6673 The Contractor is hereby: directed to make the following changes In the Contract Uf;!On receigt of an aQ[,!roved COQY: of this Amendment. ITEM NO. DESCRIPTION/ UNIT BREAKDOWN/ UNIT COSTS SEE ATTACHED BREAKDOWN 1 Phase lA Mass Grading 2 3 5 6 7 8 9 SUBTOTAL 10 GCCM fee @ 5.5% 11 Subtotal line 9, 10 12 Bond 1% 13 Insurance 1% 14 General conditions 2 months 15 Subtotal line 11, 12, 13,14 16 State Gross Receipts Tax 1% 17 Proposed Contingency 18 TOTAL COST 19 20 TOTAL CONTRACT STATUS 1.Original Contract Amount $ 2.Net Change by Previous Change Order(s)$ 3. Current Contract Amount (1 +2)$ 4. Amendment #3 Total Amount $ 5.New Contract Amount {3+4)$ 6. Total Cost of All Amendments to Date $ APPROVALS Approved by Architect0: __________________ Date: Approved by Contractor: Date: Approved by Owner: Date: COST (Indicate+ or-) $ 388,548.32 $ 388,548.32 $ 21,370.16 $ 409,918.48 $ 4,099.18 $ 4,099.18 $ 57,625.00 $ 475,741.85 $ 4,757.42 $ 20,000.00 $ 500,499.27 $ 500,499.27 303,761.07 31,489.82 335,250.89 500,499.27 835,750.16 531,989.09 EXHIBIT A EXHIBIT B 1/5 2/5 3/5 4/5 5/5