Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Rick Hixson, City Engineer
SUBJECT: 2014 Wastewater Collection System Facility Plan Update - Amendment
No. 8 for additional Construction Administration Service for the construction phase of the South
University District Sewer Main Project and additional ongoing Pretreatment Program Assistance.
MEETING DATE: May 8th, 2017
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve and authorize City Manager to sign Amendment No 8 to the
Professional Services Agreement.
BACKGROUND: Attached is a copy of the partially executed Amendment No. 8 with
Morrsion Maierle for the 2014 Wastewater Collection System Facility Plan Update. A
previously approved amendment added the construction phase services for the South University
District sewer main. Delays associated with an unknown AT&T fiber optic line caused the
project to extend beyond the anticipated completion date. This in turn caused the need for
additional construction inspection and administration in the amount of $25,325. The amendment
also includes $10,000 for ongoing assistance with the wastewater pretreatment program. This
effort will primarily focus on EPA issues associated with permitting discharges from the landfill
to the wastewater system.
The document is in the City’s standard format.
UNRESOLVED ISSUES: None
ALTERNATIVES: As suggested by the City Commission
FISCAL EFFECTS: $35,325 to be paid from the Wastewater fund and Wastewater Impact Fee
fund.
Attachments: Amendment No. 8
Report compiled on: 4/27/17