HomeMy WebLinkAbout17- Guaranteed Maximum Price Amendment 2 - Dick Anderson Construction, Inc. - Maynard Irrigation Pipeline Relocation at Sports Park8
AIA Document A133TK - 2009
Exhibit A
Guaranteed Maximum Price Amendment
for the following PROJECT:
(,Vane and address or location)
("Construction Manager")
ARTICLE AA
§ AAA Guaranteed Maximum Price
Pursuant to Section 2.2.6 of the Agreement, the Owner and Construction Manager hereby
amend the Agreement to establish a Guaranteed Maximum Price. As agreed by the Owner
and Construction Manager, the Guaranteed Maximum Price is an amount that the Contract
Sum shall not exceed. The Contract Sum consists of the Construction Manager's Fee plus
the Cost of the Work, as that term is defined in Article 6 of this Agreement.
§ AAAA The Contract Sum is guaranteed by the Construction Manager not to exceed
three hunt/red-Oriro-jive thousand two hundred fjry dollars and 89 cents,
($335,250.89), subject to additions and deductions by Change Order as provided in the
Contract Documents.
§ A.1.I.2 Itemized Statement of the Guaranteed Maximum Price, Provided below is an
itemized statement of the Guaranteed Maximum Price organized by trade categories
allowances, contingencies, alternates, the Construction Manager's Fee, and other items
ADDITIONS AND DELETIONS:
Bozeman Sports Park
The a„thor of thin document
4600 Baxter Lane
has added inYornation
headed For if. Comole'lln,
Bozeman, MT 59718
The aether may also have
§ A.1.1.3 The Guaranteed Maximum Price is based on the following alternates, if any,
revised the text of the
THE OWNER:
original, A1.4 otandard form.
AU un�„o,enc u3� - soov e:nm:e w, u,prt ia.c vv, ±om .,,.a :cos nr one ace n xnscfc•.ce of Aantc—c.. Ait ctgnee
e
An Additien.s and De2et ions
(,Name, legal status and address)
Report also notes added
Fl 1t11e1i t ch,, xte
i. rfo cna tion as well as
110V97]6]: rnicM1 eFirxs on
revisions to the standard
The City of Bozeman Montana
form text is available from
121 N. Rouse Ave.
theaatoor and should be
revie.red.
PO Box 1230
This document has important
Bozeman, MT 59771-1230
legal conseglen,e.,
Consul to ti,n with an
(`Owner")
attorney is encoura5ad with
respect to its compkotion
or modification.
and the Construction Manager:
(iVaine, legalstalus
AfA r, ltm,=nt A2e1.1,`007,
and address)
General Conditions of the
Contract Sor Consts�rt.ion,
Dick Anderson Construction, Inc.
is adooted in this document
4498 Jackrabbit Lane
by reference. Do not uae
with other y=.neral
Bozeman, MT 59718
renditions nniess rnis
docmneRr is modifted.
("Construction Manager")
ARTICLE AA
§ AAA Guaranteed Maximum Price
Pursuant to Section 2.2.6 of the Agreement, the Owner and Construction Manager hereby
amend the Agreement to establish a Guaranteed Maximum Price. As agreed by the Owner
and Construction Manager, the Guaranteed Maximum Price is an amount that the Contract
Sum shall not exceed. The Contract Sum consists of the Construction Manager's Fee plus
the Cost of the Work, as that term is defined in Article 6 of this Agreement.
§ AAAA The Contract Sum is guaranteed by the Construction Manager not to exceed
three hunt/red-Oriro-jive thousand two hundred fjry dollars and 89 cents,
($335,250.89), subject to additions and deductions by Change Order as provided in the
Contract Documents.
§ A.1.I.2 Itemized Statement of the Guaranteed Maximum Price, Provided below is an
itemized statement of the Guaranteed Maximum Price organized by trade categories
allowances, contingencies, alternates, the Construction Manager's Fee, and other items
1_ ECa Qltic COPYING O: arty
that comprise the Guaranteed Maximum Price.
p,rtion of this AIA` nrcnlrle_,t
(Altochmenll- Letterjront General Contractor)
to ono Cher electronic fi!e is
prohibited and constitutaa a
Violation of copyright laws
§ A.1.1.3 The Guaranteed Maximum Price is based on the following alternates, if any,
as met forth in the ioeter oc
which are described in the Contract Documents and are hereby accepted by the Owner:
thl" daa,ment.
AU un�„o,enc u3� - soov e:nm:e w, u,prt ia.c vv, ±om .,,.a :cos nr one ace n xnscfc•.ce of Aantc—c.. Ait ctgnee
e
Thal Ari _ n _ C , • ae_d -
�tEeua-.
i"u
.r'.
to Ali L__ [ .1_1 vlt
Fl 1t11e1i t ch,, xte
te nftTh" draft vooticci 0: AIA software a: 14:4S:41) an ll/02/2Ott unlet Oti^t Flo,
'
110V97]6]: rnicM1 eFirxs on
12NUU/•aJ i, no, :o, txsJo,
11-- Flata'-
f IPVAl1AI F1
(State the numbers or other identification ofaccepled allernates. /f the Contract Documems permil the Owner to
accept other alternates subsequent to the Mention ofthis Amendment, attach a schedule ofsuch other alternates
showing the amount for each and the date when the amount expires)
((Change Order No.I per Attachment 1»
§ A.1.1.4 Allowances included in the Guaranteed Maximum Price, if any:
(Identify allowance and state exclusions, ifanx from the allowance price.)
Item Price ($0.00)
((N/A»
§ A.1.1.5 Assumptions, if any, on which the Guaranteed Maximum Price is based:
The work is a portion of Phase I site improvements, as per the approved Master Plan.
§ A.1.1.6 The Guaranteed Maximum Price is based upon the Supplementary and other Conditions of the Contract
included in the project specifications Attachment 2 and 2a,
§A.1.1.7 The Guaranteed Maximum Price is based upon the following Specifications: Attachments 2 and 1a:
Bozeman Sports Park Phase I - Maynard Pipeline Re -alignment (speciflcations dated Nov. 11, 2016).
§A.1.1.8 The Guaranteed Maximum Price is based upon the following Drawings: Attachments 2 and tat
Bozeman Sports Park Phase I - Maynard Pipeline Re -alignment (drawings - dated Nov. 11, 2016).
§ A.1.1.9 The Guaranteed Maximum Price is based upon the following other documents and information:
Attachment 1- Proposal fetter from DAC re: Bozeman Sports Park Irrigation Main CMP Amendment No. 2
ARTICLE A.2
§ A.2.1 The anticipated date of Substantial Completion established by this Amendment (no change):
April 17, 2016.
J�b'—LLd
OWNER (Signature)
C468—K wiGiUcv-Wil`xi
Bozeman Gkdr mr cr AL9iN6 ( jT`( Mps,&*- ,
AIA Oocumear ei3fU - 2009 Exhibit A. Copyright - 1991, 2003 and 1009 by The American Institute of Architects. A11 right. ce rved.
A'.lF:liliC 11- .1�10 u_..ent hs Aral cl-d by II :i (.epyca9lhi Lam _ht..—i ,lxon
_uJ I-nat,nnal ea... ..lh—i cetlucrion or d—ulof
tM1lc \iX .--wnc any p—Ii— of i ay m - =u3C ¢ ,rlr aad crena
........ pl1—. and —11 be p—c—I.d c L11,.um e maximextant
pcss h10 under Hha lav This draft was produced by AlAnsoEtvate cat 1J:i5:A0 an l2/02/2015 Under Order No. '1109913622 which expires on
12/01/2016, and is net for resale.
Vaer "treat (339AUA1F)
XITuV-T I
DICK ANDERSON CONSTRUCTION, INC.
March 16, 2017
Carolyn Poissant, MLA, MPA, AICP,
Manager of Trails
City of Bozeman- Department of Parks and Recreation
415 N. Bozeman Street
Bozeman, MT 59715
Re: Bozeman Sports Park- Irrigation Main -GMP Amendment #2
Dear Carolyn,
As per section 5.2 and 5.3 of our Agreement for the Bozeman Sports Park Project, we are requesting an
amendment to increase our Guaranteed Maximum Price (GMP) for the Maynard Irrigation Pipeline
Realignment portion of the project. This request is based on design changes and owner additions which are
detailed on attached exhibits. This amendment is a request for an addition $31,489.82 for a new GMP of
$335,250.89. This request Includes using $12,600 of the contingency budget established in amendment #1.
Please note that applying a portion of the available contingency is outside its intended use in this case, (see
section 2.2.4) but this portion of the project nearly complete. There remains $10,000 in contingency for
potential future items. Please reference the attached exhibit for additional clarifications and cost
breakdown for the additional Items.
The date of Substantial Completion of April 17, 2017 does not change with this amendment.
If you have any questions or required additional information on the Items above, please give me at (406)
360-6673.
Sine
Louie Miller
Dick Anderson Construction
CC: Josh deVos, Dick Anderson Construction
Zachary Lowe, PE, Dowl
3424 HIGHWAY 12 EAST, HELENA, MONTANA 59601 406-443-3225 FAX 406-443-1537
4610 TRI -HILL FRONTAGE ROAD, GREAT FALLS, MONTANA 59404 406-761-8707 FAX 406-761-3134
4498 JACKRABBIT LANE, BOZEMAN, MONTANA 59718 406-586-0889 FAX 406-388-0263
PO BOX 31511, BILLINGS, MONTANA 69107 406-248-3700
Contract Change Order
Maynard Irrigation Pipeline Realignment DAC Project #: 02-16-238
Location: Bozeman Chg.Order#: 1
Contractor: Dick Anderson Construction Date: 3/16/2017
Address: Phone: 360.6673
The Contractor Is hereby directed xo make the folbwlnz thaiues In the Contract upon receiei of an aooroved copy of tNs Chance Orde
ITEM N0.
DESCRIPTION / UNIT BREAKDOWN / UNIT COSTS
SEE ATTACHED BREAKDOWN
COST
(lndlWe+or-)
1
Modify Southern connection
2. Net Change by Previous Change Order(s)
$
9,443.73
2
Upsize 6" pipe to 12" Pipe
303,761.07
$
20,319.81
3
Added inline drain tee/valve
$
$
5,299.29
4
Added future irrigation pump connection tee/valve
$
13,361.77
5
Removed seeding from contract
$
(1,858.40)
6
Contractor donation
$
(6,000.00)
7
$
8
$
9
SUBTOTAL (Labor & Materials)
$
40,566.20
10
Overhead & Profit @ 5.5%
$
2,231.14
11
Subtotal line 9, 10
$
42,797.34
12
Bond 1%
$
427.97
13
Insurance 1%
$
427.97
14
Subtotal line 11, 12, 13
$
43,653.29
15
State Gross Receipts Tax 1%
$
436.53
16
TOTAL COST (This Change Order Only) =
$
44,089.82
17
Contingency
$
(12,600.00)
18
TOTAL
$
31,489.82
CONTRACTSTATUS
1. Original Contract Amount
$
303,761.07
2. Net Change by Previous Change Order(s)
$
3. Current Contract Amount (1+2)
$
303,761.07
4. This Change Order Total Amount
$
31,489.82
S. New Contract Amount (3+4)
$
335,250.89
6. Total Cost of All Change Orders to Date (2+4)
$
31,489.82