HomeMy WebLinkAboutNEURD Resolution 4734 presentation 12-19-16Economic Development
Northeast Urban
Renewal District
Resolution 4734
December 19, 2016
Economic Development
Resolution 4732
Summary of Proposed Projects with cost estimates
Economic Development
1)Reconstruction of East Tamarack
Street -$582,500;
2)Reconstruction of East Peach Street -
$743,800;
3)Reconstruction of North Ida Avenue -
$290,500;
4)Reconstruction of Front Street -
$193,700; and
5)Reconstruction of East Aspen Street
and construction of a pedestrian
bridge to cross Bozeman Creek and
connect to the existing trail -
$166,200.
Summary of Terms and Conditions
Economic Development
Summary of Terms and Conditions (Cont.)
Economic Development
Proposed Bidding and Construction Schedule
Economic Development
Proposed Schedule
December 19, 2016 –adopt resolution
4734;
February 20, 2017 –release solicitation
documents;
March 27, 2017 –proposal deadline;
March 28 –April 14, 2017 -negotiations
with respondent(s);
April 17, 2017 –bond purchase
agreement;
April 25, 2017 –bid opening;
April 28, 2017 –notice to successful
respondent;
May 8, 2017 –bond resolution;
May 10, 2017 –contract award;
May 18, 2017 –bond sale closing.