Loading...
HomeMy WebLinkAboutMarch 2017Parking Director's Report1                 BOZEMAN PARKING COMMISSION  Parking Program Manager’s Report     Date: March 3, 2017        To: Bozeman Parking Commission   From: Ed Meece, Parking Program Manager  An update of major developments, in February, includes:   Participating in discussions, with the Economic Development Department, regarding a potential new  development and parking related issues.   Hosted a remote‐web demo of the Citation and Revenue Control equipment available from T2 systems, and  toured the parking garage/campus operations at MSU Parking Department. Both of these activities are part of  the research process for development of our Request for Proposal packet.   Phase I (gates only) of the new surveillance camera project at the Bridger Park Downtown began on 2/28/17.  Staff continues to work the IT Department to assemble final bids and planning for Phase II.   The steps and stairwells at Bridger Park Downtown were power washed/cleaned on 2/27/17.   The Bozeman City Commission approved a contract with Western Transportation Institute to conduct a parking  inventory/capacity study on 2/13/17.   PPM assisted in preparation for the City Commission’s consideration of a proposed ‘Mobile Vending’ ordinance.   Replaced PSD vehicle #2979 with a transferred vehicle from Bozeman Police Department ( 2001 Chevrolet  Impala, 119,000 miles). [Note: on 3/1/17, a PSD vehicle sustained significant damage in an accident at Bozeman  High School’s parking lot. The civilian driver was at fault, and repair/claim procedures are underway.]   PPM is drafting Professional Service Agreements/Scope of Work for consulting services with Rick Williams.   The PSD participated in initial FY 18 budget preparation and discussions with the Finance Department.   At the request of Big Sky Western Bank, the PPM is developing a pilot project that would make available some of  BSWB’s private parking spaces for public use.   The PSD began to experience a higher level of complaints from businesses and citizens, related to construction  parking near 5 West and Masonic Lodge. We have responded with additional enforcement activity, and are  exploring methods for enhancing our ‘construction parking permit’ system. This issue will likely be before the  Parking Commission, for discussion, in April.    Financial Update  I am continuing to work with the Finance Department to extract information from the finance database that will more  thoroughly demonstrate the overall fiscal health of the Parking Services Fund (enterprise). For that reason, this section of  my report will continue to evolve, over the next several months. Still to come – 18 month “Rolling Average” for all revenue  sources, ‘Actual’ data (revenue and expenditure) for the previous fiscal year, and Beginning Fund Balance/Ending Fund  Balance (monthly). For February 2017, the report was modified to reflect revenue and expenditure levels both with, and  without, the Tax Increment Finance District (TIFD) funds intended for major purchases at the Bridger Park Downtown.   A quick review of February 2017, shows the PSD’s revenues well in excess of budgeted amounts (110%), and on track with  a normal rate of budgeted expenditures (62%). Both the Administration/Personnel (PPM), and Garage/Personnel (Parking  2    Clerk), appear to be trending much higher than I would expect at this time. I am investigating this issue. In addition, staff  issues early in the fiscal year and overtime required to repair the garage gates have affected Enforcement/Personnel costs  as well.   On the Horizon..  At the suggestion of Parking Commissioner Bennett, future PPM reports will include a summary of information related to  new development plans under review, or approved, by the Community Development Department. In doing so, I hope to  provide the Parking Commission an enhanced perspective of parking related issues related to such activity.   As discussed earlier, I am working with Rick Williams to develop performance metrics for the Parking Services Division. A  lot of additional data collection, and extraction, in order for these indicators to be timely and meaningful in their  application.        3    FEBRUARY 2017 FINANCIAL SUMMARY (3/3/2017)         % FY 17 FY 17 EARNED REVENUE BUDGET ACTUAL YTD Parking Lot Permits 23,229.00$     25,948.00$    112% Garage Permits 200,000.00$  284,955.00$  142% Garage‐ Transient Revenue 75,500.00$     49,345.00$    65% Garage Validation Coupons 3,000.00$       3,941.00$      131% Residential Nghbd.Permits 12,905.00$     13,555.00$    105% Employee Ngbhd. Permits 1,855.00$       1,955.00$      105% Visitor Ngbhd.  Permits 10,210.00$     10,320.00$    101% Admin/Late Fees 42,000.00$     42,623.00$    101% Boot Fees 1,500.00$       1,950.00$      130% Citation Revenue 240,000.00$  210,742.00$  88% Misc. Revenue ‐$                 26,393.00$    N/A Rents/Royalties/Other 2,000.00$       617.60$          31% Interest Income ‐$                 348.58$          N/A Loan Interest ‐$                 622.05$          N/A Refunds & Reimbursements ‐$                 2,391.50$      N/A Transfer Other Funds (TIFD) 165,000.00$   ‐$                 N/A TOTAL (w/TIFD Transfer) 777,199.00$  675,706.73$  87% TOTAL  (w/out TIFD Transfer) 612,199.00$  675,706.73$  110% % FY 17 FY 17 SPENT EXPENDITURE BUDGET ACTUAL YTD Admin ‐ Personnel 80,381.00$     65,713.00$    82% Admin ‐‐ Operating 134,956.00$  107,580.00$  80% Admin ‐‐ Capital 165,000.00$   ‐$                 0% Enforcement ‐‐ Personnel 197,953.00$  130,449.00$  66% Enforcement ‐‐ Operating 52,841.00$     21,176.00$    40% Enforcement ‐‐ Capital 10,000.00$      ‐$                 N/A Garage ‐‐ Personnel 38,617.00$     23,054.00$    60% Garage ‐‐ Operating 171,300.00$  76,210.00$    44% Garage ‐‐ Capital ‐$                  ‐$                 N/A TOTAL (w/Admin Capital ‐ TIFD) 851,048.00$  424,182.00$  50% TOTAL (w/out Admin Capital‐TIFD) 686,048.00$  424,182.00$  62% 4    FEBRUARY 2017 STRATEGIC PLAN TRACKING    STRATEGY DESCRIPTION  PROJECTED  COMPLETION  ACTUAL  COMPLETION COMMENTS  1  Formalize the guiding  principles as policies  within the parking and  transporation system  plan.  Aug‐16  Adopted by the BPC  in 8/2016.  2  Adopt the 85% rule as the  standard for measuring  performance of the  parking supply and  triggering specific  management strategies.  Aug‐16  Adopted by the BPC  in 8/2016.  3  Strengthen the role of the  Parking Manager and the  Parking Services Division ‐  to better integrate with  the Community  Development and  Economic Development  planning. On‐Going On‐Going  PPM attending DRC  meetings; PPM  meeting with staff  from both CD and ED  on a regular basis;  PPM reviewing  pending projects for  opportunity to  provide meaningful  input.  4  Establish a policy for  adjusting rates (on and  off‐street)  Oct‐16  Adopted by the BPC  in 3/2017  5  Establish a Capital  Maintenance Reserve  Fund Jul‐16 On‐going  As part of FY 18  budget process, the  PPM will be working  with Finance  Department to create  this fund.  6  Re‐evaluate and  restructure current cash‐ in‐lieu program.  TBD (more  precise date in  near future?) On‐going  PPM is working with  the COB's internal  'parking team' to  develop the best  poicy response and  timing on this matter.  7  Re‐evaluate code‐based  parking minimum  requirements. TBD On‐going  PPM is working with  the COB's internal  'parking team' to  develop the best  poicy response and  timing on this matter.  8  Re‐evaluate and clarify  the purpose and intent of  the current code section  regarding Special  Improvement District #  565.  TBD (more  precise date in  near future?)  PPM is working with  the COB's internal  'parking team' to  develop the best  poicy response and  timing on this matter.  5    10  Develop a reasonable  schedule of data  collection to assess  performance, including an  accurate on and off street  inventory (public and  private) and an  occupancy/utilization  analysis.   6/1/17 &  10/1/17 On‐going  First data collection  efforts, following the  Strategic Parking  Management Plan,  are scheuled for  Spring and Fall 2017;  CC approved contract  with WTI in Feb.  2017  15  Upgrade the  access/revenue control  system at the Bridger  Garage. 6/30/2017 On‐going  RFP is in research  process, with a  DRAFT expected for  stakeholder revision  in late February;  Vendor demo (T2)  and visit to MSU  Parking Dep. In Feb.  2017  16  Install a vehicle counter  system at Bridger Garage  and at the Surface lots. 6/30/2017 On‐Going  RFP is in research  process, with a  DRAFT expected for  stakeholder revision  in late February.