HomeMy WebLinkAbout02-06-17 CC Mtg - C4. Resolution 4757, Allocation of Additional TOPS FundingResolution 4757 – Additional TOP Funding for Path to the M
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Carolyn Poissant – Manager of Trails, Open Space and Parks
Design and Development
Mitch Overton – Director of Parks, Recreation and Cemetery
SUBJECT: Resolution 4757 – Allocation of Additional 2012 Trails, Open Space and
Parks Bond funding for the Bicycle and Pedestrian Pathway to the “M”
and Drinking Horse Mountain Project
MEETING DATE: February 6, 2017
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve Resolution 4757 for the allocation of up to an additional
$75,000 from the 2012 Trails, Open Space and Parks Bond fund for the Bicycle and Pedestrian
Pathway to the “M” and Drinking Horse Mountain project.
BACKGROUND: On October 28,
2013, Bozeman City Commission (Commission)
approved Resolution 4484, which authorized the allocation of $600,000 from Trails, Open Space
and Park Bond Funds for: “the Construction of a Pathway to the M and Drinking Horse
Mountain and authorized the City Manager to enter into a Grant Match Agreement with the U.S.
Department of Transportation’s Federal Land Access Program.” The required federal National
Environmental Policy Act public input process and associated surveys and investigations were
completed in order to develop a preferred trail alignment concept. The preferred trail alignment
necessitated negotiations with five property owners along the trail corridor to obtain potential
easements or right-of-way.
Commission approved a contract with DOWL, LLC, a consultant certified in state right-of-way
acquisition to proceed with the negotiations. Three of the five property owners have agreed to
public trail access easements and two agreements have been executed thus far. The sections
where easements cannot be obtained are indicated in dashed lines on the illustration below.
These properties are located along Bridger Canyon Road, west of Creekwood Subdivision and
comprise approximately 36% of the total trail length. Due to the inability to secure these two
easements, a revised trail alignment must be pursued. The Federal Highways Federal Lands
Access Program (FHWA-FLAP) consultant has provided four alternatives, each of which could
be constructed within Montana Department of Transportation right-of-way along Bridger
Canyon Road (Attachment A).
64
Resolution 4757 – Additional TOP Funding for Path to the M
The reduced cost of the easements is offset by the revised estimated costs of utility relocation
work within state right-of-way, as follows:
The project partners, including Gallatin Valley Land Trust, Federal Highways FLAP project
team, Montana Department of Transportation (MDT), and staff recommend pursuing the design
of Alternative 2, which has an added cost of approximately $670,000 ($1,020,000 minus
$350,000, the cost of the original alignment). Additional design fees and contingency are
included in the revised project budget provided by the FHWA-FLAP project manager
(Attachment B), which also credits the City’s cost expended for the DOWL contract (right-of-
way work). The additional match amount estimated to be required is $68,717.43.
As such, the amount requested is $75,000. The Trails, Open Space and Parks Committee
unanimously recommended that Commission approve the allocation of an additional $75,000 in
TOP funding at their meeting of December 22, 2016 (with all five members present) with the
following motion:
“Having considered all public input, staff recommendation, and other information
received to date, I hereby recommend that City Commission allocate up to an
additional $75,000 for re-alignment of the Path as needed to utilize available
Land Owner
Parcel
Number
Anticipated
ROW costs
Estimated
utility costs
Actual
closing
costs
Revised
utility cost
estimate
Lyman Creek LLC 023a, 23b $26,500 $8000 $27,000
Cameron Holt 024a $8,650 $8000 $9,236 $8,000
FPR Properties 025a, 025b $24,100 $8000 $31,850 $8,000
James and Janet Simmons 027a $29,400 $8000 $29,986 $8,000
Robert and Cynthia
Crayton 028a $8,950
$8000
$15,000
Contingency $10,000 $10,000
Subtotal $107,600 $40,000 $71,072 $76,000
Combined
Total $147,600
$147,072
65
Resolution 4757 – Additional TOP Funding for Path to the M
rights-of-way for the Path to the M and Drinking Horse Mountain project.”
(Motion by Starner, second by Gray.)
UNRESOLVED ISSUES: An Encroachment Permit will need to be obtained from the state of
Montana Department of Transportation in association with final design and engineering.
ALTERNATIVES: Per Commission.
FISCAL EFFECTS: The allocation of $75,000 from the TOP Bond will reduce the remaining
unallocated balance to $1,054,534.
ATTACHMENTS: Resolution 4757
Attachment A – Path Design Alternatives
Attachment B – FLAP budget
Report compiled on: January 31, 2017
66
COMMISSION RESOLUTION NO. 4757
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, TO AUTHORIZE ADDITIONAL FUNDING FROM THE 2012 TRAILS,
OPEN SPACE AND PARKS BOND FUND FOR THE BICYCLE AND PATHWAY TO
THE “M” AND DRINKING HORSE MOUNTAIN PROJECT.
WHEREAS, Resolution 4484 approved and authorized funding in the amount of
$600,000 for the Bicycle and Pedestrian Pathway to the “M” and Drinking Horse Mountain
project; and
WHEREAS, Commission authorized the City Manager to enter into a Grant Match
Agreement with the U.S. Department of Transportation’s Federal Land Access Program; and
WHEREAS, the required federal National Environmental Policy Act public input
process and associated surveys and investigations were completed in order to develop a preferred
pathway alignment concept, which necessitated negotiations with five property owners along the
pathway corridor to obtain easements or rights-of-way; and
WHEREAS, due to the inability to secure all of the necessary easements, a revised
pathway alignment must be pursued; and
WHEREAS, the project partners and staff recommend pursuing a design alternative
which has an added cost of approximately $75,000.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana:
67
Section 1
Funding / Authority. The Commission hereby authorizes additional funding in the amount of up
to $75,000 from the balance of the 2012 Trails, Open Space and Parks Bond fund to cover the
additional costs for design and construction of the project as recommended by staff.
Section 2
Amendment to Resolution 4484. This resolution serves to amend Resolution 4484 as delineated
in Section 1 above.
PASSED AND APPROVED by the City Commission of the City of Bozeman,
Montana, at a regular session thereof held on the 6th
day of February, 2017.
___________________________________
CARSON TAYLOR
Mayor
ATTEST:
___________________________________
ROBIN CROUGH
City Clerk
APPROVED AS TO FORM:
___________________________________
GREG SULLIVAN
City Attorney
68
ATTACHMENT A
TRAIL TO THE M AND DRINKING HORSE MOUNTAIN – ALTERNATIVE ALIGNMENTS
Trails, Open Space and Parks Committee Meeting – Dec. 22, 2016
City Commission Meeting – Feb. 6, 2017
69
70
ATTACHMENT B - Revised Phase I Budget Summary
Program Budget Current expenditures Remaining Notes
PE $570,000 $138,301 $25,000 Internal remaining costs (158600.06 in BI)
T.O. RPA $473,800 For 0-95% Construction Estimate
T.O. RPA $13,000 For redesign along MDT At 95% (5/16) $2,648,756.15
Est to complete $25,000 Update based on new design Cost Alt 1 $1,020,000.00
RA to City $149,000 (may be reduced) Current design -$350,000.00
CE $280,000 $280,000 Estimated based on CN reduced ROW $147,600.00
CN $2,800,000
CN Adjusted $3,318,756 Estimate with Alt 1
Contingency $280,000 $280,000 Estimated based on CN Updated Estimate $3,318,756.15
Sub Total $774,101 $3,928,756
Total $3,930,000
Match required $527,406
(13.42%)
Cash Match Paid $527,406.00
Match through contract with DOWL $35,000.00 estimate
Total $562,406.00
Remaining match(est) $68,717.43
$631,123
$4,702,857
71