HomeMy WebLinkAbout02-06-17 CC Mtg - C3. Amendment 2 with Robert Peccia for 5.3 MG Water TankCommission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Rick Hixson, City Engineer
SUBJECT: 5.3 Million Gallon (MG) Water Storage Reservoir Project - Amendment
No. 2.
MEETING DATE: February 6th
, 2017
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve and authorize City Manager to sign Amendment No. 2 with
Robert Peccia and Associates.
BACKGROUND: Attached is a copy of the partially executed Amendment No. 2 with Robert
Peccia and Associates for the 5.3 Million Gallon (MG) Water Storage Reservoir Project. The
document is in the City’s standard format.
Neither the original professional services agreement nor previous amendment included the
bidding and construction phase services. The design is now complete and this amendment will
add those services. The bidding and construction phases are paid on a time and materials basis,
so only those hours needed to complete the project will be compensated.
UNRESOLVED ISSUES: None
ALTERNATIVES: As suggested by the City Commission
FISCAL EFFECTS: $457,406.00 from the Water Impact Fee Fund.
Attachments: Amendment No. 2
Report compiled on: 1/24/17