Loading...
HomeMy WebLinkAboutScan of Stormwater Reports DESIGN REPORT STORMWATER MANAGEMENT ROSA APARTMENTS MASTER SITE PLAN Prepared for: Rosa Construction, Inc. 125 Central Avenue, Ste. 1 A Bozeman, MT 59718 Prepared by: C&H Engineering and Surveying, Inc. 1091 Stoneridge Drive, Bozeman, MT 59718 (406) 587-1115 Project Number: 16723 November 2016 { INTRODUCTION The Rosa Apartments Master Site Plan project proposes to develop Lot 1 of Traditions Phase 3 into multiplex 3-story apartment buildings. The property is currently located in the City of Bozeman and is zoned as R-4 with an Open Space lot along the western edge of the site. Construction of Oak Street to City standards is underway and stormwater improvements have been completed including installation of a 36"by 58"RCP arch culvert that flows under the Oak Street right-of-way conveying Baxter Ditch. There is a detention pond in the northwest of the site located in the open space which will collect drainage from the site and also from the Oak Street right of way and Rosa Way public access and utility easement. This pond discharges through an existing outlet structure to Baxter Ditch to the west. A combination of site grading, curb and gutter, storm inlets and piping, on-site retention, and the existing detention pond will be used to manage stormwater runoff on the site. Supporting stormwater calculations and a breakdown of each drainage area are included in Appendix B for reference. Previous reports pertinent to the Rosa Apartments Master Site plan have also been included at the end of this section and these include: Rosa Subdivision (June 2006) and Traditions Phase 3 Oak Street Improvements (June 2015) CONTRIBUTING DRAINAGE AREAS TO EXISTING STORMWATER DETENTION POND The site was split into three drainage basins as shown on the attached Drainage Area Map included in Appendix A. All drainage from Drainage Areas 1 and 2, Oak Street, Twin Lakes Avenue, Sherwood Way and Rosa Way flow into the existing detention pond located in the open space area to the west of the site. The weir in the existing detention pond outlet structure has been sized to account for all flow from the future fully developed site and is adjustable up to 8 inches in width per the 14170 Oak Street Improvements stormwater report dated August 2015. All gutter capacities were checked along Oak Street and Twin Lakes Avenue in the original stormwater report submitted for the Oak Street Improvements project and there is a gutter flow spreadsheet included in Appendix B which assesses the gutter capacity of Rosa Way. The existing detention pond has a volume of 10,798 cubic feet at 1.5' in depth. This pond will be resized to 12,058 cubic feet during construction of Rosa Way. At full buildout Drainage Area 2 will be collected by a catch basin located in the northwest of the north parking area and Drainage Area 1 will flow into storm inlets: CB3 and CB4 located at the northwestern end of Drainage Area 1 near the parking area and Rosa Way intersection. All catch basins and inlets will convey stormwater via a 15" pipe to the existing detention pond. The 15" diameter PVC pipe has a 4.91 cubic feet per second capacity which will be adequate to convey drainage from each individual catchment. The pipe capacity spreadsheet has been included in Appendix B located at the end of this report. f APPENDIX A DRAINAGE AREA MAP C 1Pl.-.El POLE 1 .1—.—r;Yet— ` 1 µ`F.— —__ --_ _-- :.F.0 E__lll.'.�•�. . fiY --- C�ir— —_ -- --_ .. ...__-.— r= .. �-- •i_ . 1 ,' GILDER 474, EST--( AK STREET 474j z _ _ __ CREEK C�"F .s_ mr r.ji`�i .G 1L Vcrll1 J L52 LS ,x A53 SF 9, t / O I �i tr-Eabr BLDGI Aa SF BLOG2 _I — — — -- _ -- —— — — -- — 91 8 415o SF e.150 SF i to'n sr- / ].lex SF �a Yt='_nFST - 1. \.4740 111 , 11 \ I ,167• I e.150 SF ra 5aMS SF I II j I I Q BLOG4 \ II II �, M �� 1 III IIII I ${j DRAINAGE aOGIO 'III 1 \1 111 I11 o, m SF AREA 2 I II I A 1 I Il 11` 3,t5F i II I I i — _ T 1 1111 II`1 { P /G7 A3 .. 310 SF 1.17 1395F 45 _ x.329'SF ill I IIi fLnhJ C'[f?5 'e;:=i „ 4744 Al II 1— s n1 p1 t2( - 1 x II __— '�bf I DRAINAGE BumPK I I I 8.1m s' I r I I \ 5a 0 AREA 1 1 ✓ BLOG8 C. `` 1J 41 t5I.S5 `LSS BT 1 ui t 3.7ax \ i 1 � I_ .1 x 1 1.eo,s.. 5 1 ,l 1 _I p OPEN SP E t 1a� ; t 9 i ,3 I C`_I 49.05 Sq.FL p ....._ ._. I I L 1.139 I BLDG7 c rr r_1 ;; s 43eGs6F L59 LOT 5 e,15o Sc ' FL J"l': 4T4+`a I Rye SF 9.M SF li — t132.05-�- — 67t-4-20a'4rl4` M1 ---�---- — — — — •pa cp/50 —11 -- SHERWOOD WAY s11- —_ J-•�.. •s��.—mot { :c rnu +—.:;— - --- J — T Issue Date: C. — I APPENDIX B SUPPORTING CALCULATIONS c DETENTION POND (Twin Lakes, Rosa Way, Drainage Area 1, Sherwood Way, West Oak) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area(ft2) C*Area Oak Street 0.82 26588 21802 Composite ROW: C Twin Lakes Avenue 0.73 22204 16209 Coak= ((0.95*38)+(0.2*7))/45 0.83 Rosa Way 0.82 39298 32224 CT"i.= ((0.95*21.5)+(0.2*7))/30 0.73 Sherwood Way a82 15709 12881 CSherwood= ((0.95*21.5)+(0.2*7))/30 0.73 Drainage Area 2 0.72 145564 104679 Drainage Area 1 a78 138001 107310 Cosa= ((0.95*41)+(0.2*7))/60 0.67 Total 387364 295106 A=Area(acres) 8.8927 C=Weighted C Factor 0.76 3. Calculate T, (Pre-Development) Tc Overland Flow Tc=1.87(1.1-CCf)D12/Slr3 --------------------------------------------- ;Storm S=Slope of Basin(%) 1 ;Return(yrs) Cf C=Rational Method Runoff Coefficient 0.2 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 111 to 25 1.1 D=Length of Basin(ft) 886 126 to 50 1.2 51 to 100 1.25 Tc(Pre-Development)(minutes) 49 -------------------------------------------- 4. Calculate Rainfall Intensity(Duration=Pre-Development Tc) i=0.64e-"(10-yr Storm, Fig. 1-3,COB Design Standards) x=storm duration(hrs) 0.82 (Tc Pre-Development) i=rainfall intensity(in.1hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q=CiA C=Rational Method Runoff Coefficient 0.2:(open land) i=rainfall intensity(in./hr.) 0.73 (calculated above) A=Area(acres) 8.89 (calculated above) Q=Runoff Rate (Pre-Development)(cfs) 1.30 6. Calculate Required Pond Volume Total Area(acres)= 8.89 acres Weighted C= 0.76 Discharge Rate(cfs)= 1.30 cfs(Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Q.'"(cfs) Runoff Release Required (in/hr) Volume Volume Storage(W) 59 0.98 0.65 4.38 15517 4597 10920' 70 1.17 0.58 3.92 16474 5455 11020 71 1.18 0.57 3.89 16556 5533 11024 72 1.20 0.57 3.85 16637 5610 11027 73 1.22 0.56 3.82 16718 5688 11030' 74 1.23 0.56 3.78 16798 5766 11031 75 1.25 0.55 3.75 16877 5844 11033 76 1.27 0.55 3.72 16955 5922 11033 77 1.28 0.54 3.69 17033 6000 11033 78 1.30 0.54 3.66 17110 6078 11032 79 1.32 0.54 3.63 17187 6156 11031 80 1.33 0.53 3.60 17262 6234 11029 81 1.35 0.53 3.57 17338 6312 11026 82 1.37 0.52 3.64 17412 6390 11023 83 1.38 0.52 3.51 17486 6468 11019 OUTLET STRUCTURE SLOT Q=CLH 312 QExISTING POND=Discharge(cfs) 2.71 QPOND 1=Discharge(cfs) 1.30 { QTOTALAT POND 1 WEIR=Discharge(cfs) 4.01 C=Weir Coefficient 3.33 (per COB Design Standards) H=Head(ft) 1.5; L=Horizontal Length(ft) 0.66 L=Slot Width(inches) 7.9 i DRAINAGE AREA ROSA WAY Contributing Area C Area(f 2) C * Area ROW 0.82 35358 289041 Total 35358 28993.6 C=Weighted C Factor 0.81; A=Area(acres) 0.81 Required Gutter/Pipe Capacity (257yr Storm) Tc Overland Flow Tc= 1.87 (1.1-CCf)D"/S1/3 Storm S = Slope of Basin (%) 0.5 Return Cf C=Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 11 to 25 1.1 D =Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow(minutes)= 6.52 Tc Gutter Flow Tc=L/V/60 V = (1.486/n)R /3 Sv2 n=Mannings Coefficient _003' R=Hydraulic Radius A/P (ft) 0_13 (0.15'below top of curb) S = slope (ft/ft) 0.010 L=length of gutter(ft) 520 V=mean velocity(ft/s) 3.001 Tc Gutter Flow(minutes)= 2.89 Tc Total (Overland+ Gutter) = i; y 9.4-1 Q = CIA C=Weighted C Factor 1 0.82!(calculated above) I= 0.78 Tc o.64(in/hr) 2.551 A=area(acres) 0.81: Qrequired (Cfs)_ __.1.70' Provided Gutter Capacity(flowing at 0.15' below ton of curb) Q =(1.486/n)AR2i3 ' n=Mannin s Coefficient `"' -0.01311 A=area(ft2) 1.24 P =wetted perimeter ft R=Hydraulic Radius A/P (ft) 0.131 S =slope (ft/ft) 0.005 Qprovided (Cfs) _ - 2.631 GUTTER IMSADEQUATE CAPACITY i DRAINAGE AREA 1 r-, Contributing Area C Area(ft) C * Area Drainage Area 1 0.7776 138001 , 107310' Total 138001 107310 C=Weighted C Factor A=Area(acres) 3.17 Required Gutter/Pipe Capacity (257yr Storm) Tc Overland Flow Tc= 1.87 (1.1-CC)D1/2/Sii3 Storm S = Slope of Basin (%) 0.5 Return Cf C=Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 11 to 25 1.1 D =Length of Basin (ft) 159 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow(minutes) = 21.241 Tc Gutter Flow Tc=LN160 V=(1.486/n)R2' S" n=Mannings Coefficient 0.013 R=Hydraulic Radius A/P (ft) 0.13 (0.15'below top of curb) S =slope (ft/ft) 0.010 L=length of gutter(ft) 365 V=mean velocity (ft/s) 3.00. Tc Gutter Flow(minutes)= 2.03 Tc Total (Overland+Gutter)= 23.27 Q= CIA C=Weighted C Factor 0.78 (calculated above) I= 0.78 Tc o.6a(in/hr) 1.43 A=area(acres) 3.17 Qrequired (efs) = 3.52 r DRAINAGE AREA 2 Contributing Area C Area(ft) C * Area Drainage Area 1 0.71913 145564 104679! Total 145564 104679! C =Weighted C Factor 0.72 A=Area(acres) 3.34' Required Gutter/Pipe Capacity (25-yr Storm) Te Overland Flow Tc= 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 0.5 Return Cf C=Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 11 to 25 1.1 D =Length of Basin (ft) 150 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow(minutes)= 20.63 Tc Gutter Flow Tc=LN/60 V =(1.486/n)W" S" n=Mannings Coefficient 0.013 R=Hydraulic Radius A/P (ft) 0.13;(0.15'below top of curb) S = slope (ft/ft) 0.018 L=length of gutter(ft) 532 V=mean velocity(ft/s) 3.97' Tc Gutter Flow(minutes)= 2.24 Tc Total (Overland+ Gutter)= 22.87: Q = CIA C= Weighted C Factor 0.72 (calculated above) I= 0.78 Tc o.6a(in/hr) 1.45' �; A=area(acres) 3.34 Qrequired (CfS) = 3.48 MANNING'S EQUATION FOR PIPE FLOW Project: 12" Storm pipe Location: Storm Inlets By: ADM Date: 7/23/2015 Chk. By: Date: Clear Data 0 Entry Cells INPUT ________ D= 15 inches d= 14.07 inches Mannings Formula d 10 n= 0.013 mannings D 0= 57.7 degrees Q=(1.486/n)ARhv3S l iz S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter V=(1.49/n)Rh2J3S112 S=slope of channel Q=V X A n=Manning's roughness coefficient Solution to Mannings Equation Manning's n-values Wetted Hydraulic Area,ft2 Perimeter,ft Radius,ft velocity ft/s flow,cfs PVC 0.013 1.20 3.30 0.36 4.11 4.91 PE(<9"dia) 0.015 PE(>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Concl 0.013 INSPECTION AND MAINTENANCE FOR STORMWATER MANAGEMENT FACILITIES The Property Owners Association shall be responsible for the maintenance of the stormwater drainage facilities within the Rosa Apartments. Storm Water Facilities: 1. Drainage swales slope toward storm inlet structures and yard drains. 2. Existing detention pond to the west of the site located in the open space. Post Construction Inspection: 1. Observe drain time for a storm event after completion of the facility to confirm that the desired drain time has been obtained. If excessively slow infiltration rates are observed then excavate a minimum 5 ft by 5 ft drain to native gravels (or native well-draining material) and backfill with well-draining material (pit-run). 2. Observe the stormwater catch basins after installation and clear any material or obstructions in the drainage slots. Inspect the drywells after a storm event to insure proper drainage. 3. Factors responsible for clogging should be repaired immediately. Semi-Annual Inspection: 1. Check detention pond following three days of dry weather after a storm event exceeding 1/4 inch of precipitation. Failure for water to percolate or pass through out let structure within this time period indicates clogging or poor-draining soils. Replace/repair as necessary. 2. Remove grass clippings, litter, and debris from drainage swales, catch basins, and detention pond. Flush and/or vacuum drywells or stormwater pipes if excessive material is observed in the facilities. Standard Maintenance: 1. Remove sediment and oil/grease from retention ponds. 2. Inspect and remove debris from drainage swales, catch basins, and detention ponds. 3. Monitor health of vegetation and revegetate as necessary to maintain full vegetative cover. 4. Inspect for the following issues: differential accumulation of sediment, drain time, signs of petroleum hydrocarbon contamination(odors, oil sheen in pond water), standing water, trash and debris. Sediment accumulation: In most cases, sediment from a detention pond does not contain toxins at levels posing a hazardous concern. However, sediments should be tested for toxicants in compliance with current disposal requirements and if land uses in the drainage area include commercial or industrial zones, or if visual or olfactory indications of pollution are noticed. Sediments containing high levels of pollutants should be disposed of in accordance with applicable regulations and the potential sources of contamination should be investigated and contamination practices terminated. i ST ORMWAT'IER MANAGEMENT DESIGN REPORT TRADITIONS SUBDIVISION PHASE 3 OAK ST RE ET IMPROVEMENTS Prepared for: Rosa Const►•tiction, Inc. 125 Central Avenue, Bozeman, MT 59718 Pre�2ared by: C&H Engineering and Surveying, Inc. 1091 Stoneridge Drive, Bozeman, MT 59718 �'��, ' _•`.:a��-2% .. '�;' fit,' Project Number. 14170.1 �� JUNE 2015 INTRODUCTION Oak Street improvements are proposed during construction of Traditions Subdivision Phase 3 and will connect West Oak Street from Boulder Creek Subdivision to Twin Lakes Avenue at the boundary of Flanders Creek Subdivision. The 7.89-acre Lot R1, with frontage along Oak Street, is situated in the Northeast Quarter of the Southeast Quarter of Section 4, Township 2 South, Range 5 East of P.M.M., City of Bozeman, Gallatin County, Montana. Lot RI is a restricted use lot and zoned R4. This report considers the management of stormwater with Lot R1 in its current undeveloped state but also provides adequate detention to accommodate the anticipated buildout of the lot in sizing overflow structures and detention pond volume. A future subdivision or site plan will address stormwater management on the developed Lot RI in more detail and additional stormwater management will be implemented if found to be necessary. C&H Engineering developed spreadsheets were used for all calculations in this report including pipe outlet capacities, gutter flow depth and detention pond sizing. Each drainage area, composite "C" value, total acreage and storm peak runoff was calculated using a C&H Engineering developed Excel spreadsheet. Data was taken from the Flanders Creek Stormwater Report and revisions dated June 2005 to model the existing storm sewer facilities in order to interface the existing system with the proposed. All excel spreadsheet printouts and other sources can be found at the end of this report. STORMWATER MANAGEMENT Design of the stormwater facilities for this project was based on the City of Bozeman Design Standards and Specifications Policy, March 2004 including Addendums 1 through 5. The future site plan for Lot RI was incorporated into the detention pond volume as described in the detention pond section of this report. For the purposes of determining the volume for Pond 1 the Lot R1 area was assumed to have a future runoff coefficient of 0.7. In the future site plan excess runoff, which cannot be detained in Pond 1, will be retained on site or an additional detention pond will need to be designed. Pond 1 is currently shown at its maximum size on Figure D1 found at the end of this report. The inlet at the corner of Twin Lakes Avenue and Oak Street (Inlet FC-14) is proposed to be removed during Oak Street improvements. FC-14 currently is piped to a temporary retention pond located in the Oak Street right of way;this structure will be removed and r t Design Report-Page 2 of 5 the contributing drainage area will be graded to drain from the current location of FC-14 to proposed Storm Inlet 1A. There is a small section of Oak Street on the far west of the proposed street(Oak West) which accounts for 4,263 square feet of Oak Street (C=0.82). This small area will be temporarily drained to Pond 1 until completion of Boulder Creek Subdivision. A temporary swale is shown on the construction plans for management of this runoff. DRAINAGE AREA 1 Drainage Area 1 consists of a portion of Oak Street to the north of Lot Rl and a portion of Twin Lakes Avenue east of Lot Rl, as shown on Figure D1. Drainage Area 1 will contribute runoff to Pond 1 via Storm Inlet I located on the south side of Oak Street at the low point in the street profile. This inlet will be piped to a proposed 48-inch manhole (Storm Inlet 2A) via a 15-inch PVC storm sewer pipe under the curb in Oak Street. From Storm Inlet 2A a 15-inch PVC pipe will connect with a new 60-inch manhole (SDMH 1) proposed to be installed at the existing 30-inch RCP pipe draining from east to west along the south side of Oak Street in the existing 15 foot stormwater easement. The existing 30-inch RCP pipe is an outlet pipe currently used for the ii 19,000 cubic foot existing detention pond that was installed with Flanders Creek Subdivision (existing pond). A 30-inch PVC pipe will be installed downstream from SDMH 1. This pipe will be the inlet pipe for a new detention pond (Pond 1)proposed to detain runoff from Drainage Area 1. A composite "C" runoff coefficient was calculated for Drainage Area 1 along with the post-development time of concentration. The proposed 15-inch,30-inch and 36-inch storm sewer pipes discussed above all have adequate capacity as calculated on the storm sewer pipe capacity spreadsheets. Additionally all existing and proposed gutter capacities were checked to verify adequate freeboard while flowing at the COB maximum gutter flow depth of 0.15 feet below the top of curb. As can be seen in the attached spreadsheets all gutters have adequate capacity. STORMWATER DETENTION AT POND 1 Pond 1 is proposed in the designated open space area along the west side of Lot Rl. This pond will retain and release runoff from Drainage Area 1 and it has been oversized for future use following buildout of the Lot RI site. The exact drainage area contribution to this pond from Lot RI will be determined in the future site plan. Design water depth for the detention pond Design Report-Page 3 of 5 calculations was limited to 1.5 feet, which is the maximum allowed pond water depth in the COB stormwater design standards without safety fencing. Drainage area 1 has a total area of 1.14 acres and a composite "C" runoff coefficient of 0.82. The pre-developed runoff rate was calculated to be 0.17 ft%ec. (See end of the report for detailed calculations). The storage volume was computed by increasing the storm duration and computing the runoff volume minus the release volume. The release rate is equal to the pre-developed runoff rate. The maximum storage required occurs at a storm duration of 85 minutes and is equal to 1,579 cubic feet. Detention Pond #1 has a volume of 10,623 cubic feet as shown on the construction drawings. This volume accounts for the area of Lot Rl (7.89 acres) with a C coefficient of 0.7, the 1.14 acres from Drainage Area 1 plus the small contribution from Oak West. As shown on the spreadsheet entitled Detention Pond#1 (Oak Street, Twin Lakes and Lot R1 included) found at the end of this report the required volume of Pond 1 is 10,299 cubic feet. Therefore the pond as shown on Figure D 1 will be sized to have ample volume to detain the required runoff from Oak Street, Twin Lakes Avenue, and from the completed Lot Rl. OUTLET STRUCTURE AND PIPING—POND 1 AND EXISTING POND An outlet structure and piping will be installed in the north end of Detention Pond#1. The outlet structure will be sized per the City of Bozeman Design Standards and will be adjusted to a weir width of 5.6 inches. Discharge to Baxter Ditch will be limited to 2.88 ft3/sec.which includes 2.71 ft3/sec., the pre-development runoff release rate of the existing pond's 5.3-inch weir, plus the pre-development runoff release rate of 0.17 ft3/sec. from Drainage Area 1. An adjustable outlet weir will be used in the outlet structure at Pond 1 in order to increase the overflow rate in the future if additional detention volume is required during development of the future site plan design. The weir notch will have a maximum width of 8-inches which will handle the pre-development runoff from Lot Rl, Drainage Area 1 and the current release rate of the outlet weir on the existing pond. The outlet pipe for the new pond will be sized as a 36-inch PVC pipe with a 0.54% slope (maximum capacity = 52.72 ft3/sec.). The outlet pipe has been oversized to handle overflow drainage from Drainage Area 1, Lot Rl and the existing pond. The capacity of this pipe exceeds the required design flow rate of 35.41 ft3/sec., which includes the existing outlet structure's overflow rate, Q25 of 20.29 ft3/sec. (Flander's Creek Stormwater Design Report and revisions l Design Report-Page 4 of 5 dated June 2005), plus 15.12 ft3/sec. which is the total amount of overflow from Drainage Area 1 -and the anticipated maximum overflow contribution from Lot R1. The detention pond outlet pipe therefore will provide sufficient overflow capacity from the proposed detention pond to the Baxter Ditch outfall in a major storm event for the current design and the weir width can be easily adjusted to handle additional flows from Lot R1 as required. i Design Report-Page 5 of 5 �4 MARK A. ammm Na 95111ES F.L LR!E, P.; :N(E)=i::4..4 I yam(9( (YLPo�EyO / rl IY(c)-..4 %S<._4 ..•A^wT(ETTfa'ESF'1113 THIS DRUH+CE AREA I COS TRACT52 3t• t ' I WCLUDED IN B011LDETi F._ O':G('•,).4735 CT ANXRSON NSA FERN h BAXTER F.L CM:1 i CREE](STOPIMATER I r.L RI(E, 4T35,}: RANCH HO101N0 LTD -.1 R:(S 0'"n Sheet 1 OJ ! �p0� 1 �'-r_LGi:Orr 2244707 -1 A t:aT:k`'lUH STORY�T 2A 4r STA 1+67.30(23.05%) o I Y:44 ].cR FOE CARE .E,*-.t.O=W,TP.TOLE ' /^� n W tl 1; ,r tNS1Al1 NEW 3K RCP I/ OW(SYn. 4 94(1 _A Ct;POLC'` - C R F,ARm FND SECIpN f R A736. S) —,Aa Cti .:NC AK - Y �_C•rf-. v-_'•:�1=riff— v,c_ i++E r.K_ i.E ry,_ Cwi .iC r'1E _ _ � 1 �� l,E A4 O1': ,C'w�•.S_K--1'r A`�``�Ji" Y �•'y� 7��c .-7�et c so �'_E.YYtCT•�_T.^T -F.. i - _ P. .RE:.Y0. [5 n F G t , g 4 a, vrrr s;- v�--r •jai'4a-_..-�. r— i I —- c rt+s L '� 1 $1 1103 t 1 .) i I F ) -0_ µ v1:Er- IVJ:-�` LN7�6[[C0I tly` r \ FJ OJT t _ / t -- 1 ` T s_—cam—- -- �I I I _ Az2 r/j ABI�NDDH'tSJ• °�;,i,],:•ef:..,�— /' 2- W ✓ tRENI 6_• SE%EF.E<;E•.•ENT r.t,cur cn; _._... . --} ! FY PCVit•d,T E' S Mn 1 no-Irta aruErtn)srA I+u.so aar" I 1 � @ I _I tWj t..':: ttt I o X 1L+_itET.::.'.i:< \ \\\ I fi W(E}4736.7t1(SC) r._W(E!-t7:'iC EK Crime rO-ii l'' I I I I �' i B 0ETEMX)N OVM1Ei to fiV) A 6/66 007.,(. l i ..I rL Ot INE}4736.78(W) .` sN <t.00 I• ].: 1C WER SLOT \\\�R / 73gg�,,.5554(DK)rJ ` PDNo ZI a OUT(S):4736.75(31T) •..-.L tur(T. WI{IfFI 56'c / VOl-AT 1 STORY Mn 1A(4S)STA 4+31.54(26.119'L)' (OFPM.,0. WSTALL NEW 3tr RCP Po+1:4]}9.9J �'�EIEV.AT OF F1AIS➢END mD7wN FL OUT(W):4737.70(IS) 1 �: POND 47 2 FL.475632 S , ��•: ) / ' CIi:��Y1=Nit1;E EA',.'.vENT �I^p 'D,0 Ijl ! I j ('�j r�T,e'''(q �, 1 F' 1 00� r I I Fi_AtdLCPE• (:PE=V I W LK'.`:,Irt`I SUBDIVISION - t\\ V.' �I 31•TmDE Sr.—<L7:E= `•1 ( 1- r I �\ � �•' �, 1 z� I ' � I I a —.` \.`. 343.676 SF _ ON I11 lAi RI t=LANDERS Ul%faY----- -- ''� - -------------- ------ � I\ 1 ;UPI1 DID g E 2 rL 1 'I} III II t•�:� 1 .� I I I ' V1 �/1 II �Ez rAH; •,P: Ir.L O —555, O SHERWOOD r tri, N lasm Date 8I24115 Scale In Feet 50 O 50 ®1.0 15 0 Is ) DRAINAGE MAP Scale In Meterx C1,0 SGlE Y�50' #14170.1 DETENTION POND #1 (Twin Lakes and Oak Street Only) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft2) C *Area ROW 0.82 49504 40593 OS/Park 0.2 0 0 Lot R1 0.7 0 0 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 49504 40593 A =Area(acres) 1.1365 C= Weighted C Factor 0.82 3. Calculate T, (Pre-Development) Tc Overland Flow Tc= 1.87 (1.1-CCf)D"2/Sv3 Storm S = Slope of Basin (%) 1 ;Return (yrs) Cf C= Rational Method Runoff Coefficient 0.2 12 to 10 1; Cf= Frequency Adjustment Factor 1.1 111 to 25 1.1 D= Length of Basin (ft) 886 ;26 to 50 1.2; 51 to 100------------ 1.25 c(Pre-Development)(minutes) 49 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i= 0.64x 0.65 (10-yr Storm, Fig. 1-3, COB Design Standards) x=storm duration (hrs) 0.82 (Tc Pre-Development) i=rainfall intensity(in.1hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q = CiA C = Rational Method Runoff Coefficient 0.2 (open land) i= rainfall intensity(in./hr.) 0.73 (calculated above) A=Area (acres) 1.14 (calculated above) Q=Runoff Rate (Pre-Development)(cfs) 0.17 6. Calculate Required Pond Volume Total Area (acres) = 1.14 acres Weighted C= 0.82 Discharge Rate (cfs)= 0.17 cfs (Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Q.'"(cfs) Runoff Release Required (in/hr) Volume Volume Storage (ft3) 78 1.30 0.54 0.50 2354 777 1577 79 1.32 0.54 0.50 2364 787 1577 80 1.33 0.53 0.49 2375 797 1578 81 1.35 0.53 0.49 2385 807 1578 82 1.37 0.52 0.49 2395 817 1579 83 1.38 0.52 0.48 2405 827 1579 84 1.40 0.51 0.48 2415 836 1579 85 1.42 0.51 0.48 2425 846 1579 86 1.43 0.51 0.47 2435 856 1579 87 1.45 0.50 0.47 2445 866 1579 88 1.47 0.50 0.46 2455 876 1579 89 1.48 0.50 0.46 2465 886 1579 90 1.50 0.49 0.46 2474 896 1578 91 1.52 0.49 0.45 2484 906 1578 92 1.53 0.48 0.45 2494 916 1577 OUTLET STRUCTURE SLOT Q=CLH 3/2 �r QExISTING POND= Discharge (cfs) 2.71 QPOND 1 = Discharge (cfs) 0.17 QTOTALATPOND 1 WEIR= Discharge (cfs) 2.88 C=Weir Coefficient 3.33 (per COB Design Standards) H = Head (ft) 1.5 L= Horizontal Length (ft) 0.47 L =Slot Width (inches) 5.6 f DETENTION POND #1 (Oak Street, Twin Lakes and Lot R1 included) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft2) C *Area ROW 0.82 53767 44089 OS/Park 0.2 0 0 Lot R1 0.7 343838 240687 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 397605 284776 A =Area(acres) 9.1278 C= Weighted C Factor 0.72 3. Calculate T, (Pre-Development) Tc Overland Flow Tc= 1.87 (1.1-CC)D112/Sv3 Storm S= Slope of Basin (%) 1 f Return (yrs) Cf C = Rational Method Runoff Coefficient 0.2 12 to 10 1; Cf= Frequency Adjustment Factor 1.1 111 to 25 1.1 D = Length of Basin (ft) 886 ;26 to 50 1.2; f 151 to 100__--- 1.25; Tc(Pre-Development) (minutes) 49 ------- 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i = 0.64x o.s5 (10-yr Storm, Fig. 1-3, COB Design Standards) x=storm duration (hrs) 0.82 (Tc Pre-Development) I=rainfall intensity(in.1hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q= CiA C = Rational Method Runoff Coefficient 0.2 (open land) i= rainfall intensity(in./hr.) 0.73 (calculated above) A=Area (acres) 9.13 (calculated above) Q =Runoff Rate (Pre-Development)(cfs) 1.33 _ 6, Calculate Required Pond Volume Total Area (acres) = 9.13 acres Weighted C = 0.72 Discharge Rate (cfs) = 1.33 cfs (Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Q.'" (cfs) Runoff Release Required (in/hr) Volume Volume Storage (ft ) 58 0.97 0.65 4.28 14885 4639 10246 59 0.98 0.65 4.23 14974 4719 10255 60 1.00 0.64 4.18 15063 4799 10264 61 1.02 0.63 4.14 15150 4879 10271 62 1.03 0.63 4.10 15236 4959 10277 63 1.05 0.62 4.05 15322 5039 10283 64 1.07 0.61 4.01 15407 5119 10288 65 1.08 0.61 3.97 15490 5199 10292 66 1.10 0.60 3.93 15573 5279 10295 67 1.12 0.60 3.89 15656 5359 10297 68 1.13 0.59 3.86 15737 5439 10298 69 1.15 0.58 3.82 15818 5519 10299 70 1.17 0.58 3.79 15897 5599 10299 71 1.18 0.57 3.75 15977 5679 10298 72 1.20 0.57 3.72 16055 5759 10296 73 1.22 0.56 3.68 16133 5839 10294 74 1.23 0.56 3.65 16210 5919 10291 75 1.25 0.55 3.62 16286 5999 10287 76 1.27 0.55 3.59 16362 6079 10283 OUTLET STRUCTURE SLOT Q=CLH 3/2 QEXISTING POND= Discharge (cfs) 2.71 QPOND 1 = Discharge (cfs) 1.33 QTOTAL AT POND 1 WEIR= Discharge(cfs) 4.04 C =Weir Coefficient 3.33 (per COB Design Standards) H = Head (ft) 1.5 L= Horizontal Length (ft) 0.66 L =Slot Width (inches) 7.9 DETENTION POND #1 (Temp. Drainage from Oak West) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft2) C*Area ROW 0.82 4263 3496 OS/Park 0.2 0 0 Lot R1 0.7 0 0 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 4263 3496 A =Area (acres) 0.0979 C=Weighted C Factor 0.82 3. Calculate T, (Pre-Development) Tc Overland Flow Tc= 1.87 (1.1-CCf)D1/2/Sii3 Storm S= Slope of Basin (%) 1 !Return (yrs) Cf C = Rational Method Runoff Coefficient 0.2 12 to 10 1; Cf= Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 886 ;26 to 50 1.21 51 to 100------------ 1.25 Tc(Pre-Development) (minutes) 49 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i= 0.64x o.65 (10-yr Storm, Fig. 1-3, COB Design Standards) x=storm duration (hrs) 0.82 (Tc Pre-Development) i=rainfall intensity(in.1hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q = CiA C = Rational Method Runoff Coefficient 0.2 (open land) i= rainfall intensity(in./hr.) 0.73 (calculated above) A=Area (acres) 0.10 (calculated above) Q =Runoff Rate (Pre-Development) (cfs) 0.01 6. Calculate Required Pond Volume Total Area (acres) = 0.10 acres Weighted C = 0.82 Discharge Rate (cfs)= 0.01 cfs (Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Q.'" (cfs) Runoff Release Required (in/hr) Volume Volume Storage (ft3) 70 1.17 0.58 0.05 195 60 135 71 1.18 0.57 0.05 196 61 135 72 1.20 0.57 0.05 197 62 135 73 1.22 0.56 0.05 198 63 135 74 1.23 0.56 0.04 199 63 136 75 1.25 0.55 0.04 200 64 136 76 1.27 0.55 0.04 201 65 136 77 1.28 0.54 0.04 202 66 136 78 1.30 0.54 0.04 203 67 136 79 1.32 0.54 0.04 204 68 136 80 1.33 0.53 0.04 204 69 136 81 1.35 0.53 0.04 205 69 136 82 1.37 0.52 0.04 206 70 136 83 1.38 0.52 0.04 207 71 136 84 1.40 0.51 0.04 208 72 136 85 1.42 0.51 0.04 209 73 136 86 1.43 0.51 0.04 210 74 136 87 1.45 0.50 0.04 211 75 136 88 1.47 0.50 0.04 211 75 136 89 1.48 0.50 0.04 212 76 136 90 1.50 0.49 0.04 213 77 136 91 1.52 0.49 0.04 214 78 136 92 1.53 0.48 0.04 215 79 136 93 1.55 0.48 0.04 216 80 136 94 1.57 0.48 0.04 216 81 136 95 1.58 0.47 0.04 217 81 136 96 1.60 0.47 0.04 218 82 136 97 1.62 0.47 0.04 219 83 136 98 1.63 0.47 0.04 220 84 135 DRAINAGE AREA LOT k 1 Contributing Area C Area(ft) C * Area Composite ROW ROW 0.81957 0 0 ((0.95 43)+(0.2 17))/60 OS/Park 0.2 0 0 0.8195652 Lot RI 0.7 346141 242299 Total 346141 242299 C=Weighted C Factor 0.70 A=Area(acres) 7.95 Required Gutter/Pipe Capacity (25-yr Storm) Tc Overland Flow Tc= 1.87 (1.1-CCf)D1i2/S1i3 Storm S = Slope of Basin(%) 0.5 Return C f C =Rational Method Runoff Coefficient 0.35 2 to 10 1 C f=Frequency Adjustment Factor 1.1 11 to 25 1.1 D=Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow(minutes)= 6.52 Tc Gutter Flow Tc=LN160 V= (1.486/n)R" S" n=Mannings Coefficient 0.013 R=Hydraulic Radius A/P (ft) 0.13 (0.15'below top of curb) S = slope (ft/ft) 0.010 L=length of gutter(ft) 670 V=mean velocity(ft/s) 3.00 Tc Gutter Flow(minutes)= 3.72 Tc Total (Overland+ Gutter)= 10.25 Q =CIA ( C=Weighted C Factor 0.70 (calculated above) I=0.78 Tc 0.64(in/hr) 2.42 Drainage Area#LOT R1 A= area(acres) 7.95 Qrequired (cfs) = 13.44 Provided Gutter Capacity (flowing at 0 15' below ton of curb) Q= (1.486/n)Ale'S" n=Mannings Coefficient 0.013 A=area(f 2) 1.24 P =wetted perimeter(ft) 9.23 R=Hydraulic Radius A/P (ft) 0.13 S =slope (ft/ft) 0.01 Qprovided (efS)= 3.72 CAPACITY PROBLEM Drainage Area#LOT R1 DRAINAGE AREA 1 (TWIN LAKES WEST AND OAK STREET) Contributing Area C Area(ft 2) C * Area Composite ROW ROW 0.81957 45504 37293 ((0.95*43)+(0.2*l7))/60 OS/Park 0.2 0 0 0.8195652 Lot Rl 0.7 0 0 Total 45504 37293.5 C =Weighted C Factor 0.82 A=Area(acres) 1.04 Required Gutter/Pipe Capacity (257yr Storm) Tc Overland Flow Tc= 1.87 (1.1-CCf)Dli2/S1/3 Storm S = Slope of Basin (%) 0.5 Return Cf C=Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 11 to 25 1.1 D =Length of Basin(ft) 15 26 to 50 1.2 Tc Overland Flow(minutes)= 6.52 51 to 100 1.25 Tc Gutter Flow Tc=L/V/60 V= (1.486/n)R2i3 Sv2 n=Mannings Coefficient 0.013 R=Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (ft/ft) 0.005 L= length of gutter(ft) 968 V=mean velocity(ft/s) 2.12 Tc Gutter Flow(minutes) = 7.61 Tc Total (Overland+ Gutter)= 14.13 Q=CIA ( C= Weighted C Factor 0.82 (calculated above) I=0.78 Tc 0.64(in/hr) 1.97 A=area(acres) 1.04 Qrequired (efS) = 1.68 Provided Gutter Capacity (flowing at 0 15' below ton of curb) Q = (1.486/n)AR"'S" n=Mannings Coefficient 0.013 A=area(f 2) 1.24 P =wetted perimeter (ft) 9.23 R=Hydraulic Radius A/P (ft) 0.13 S = slope (ft/ft) 0.01 Qprovided (CfS) = 3.72 GUTTER IMSADEQUATE CAPACITY i DRAINAGE AREA OAK WEST Contributing Area C Area(ft) C * Area Composite ROW ROW 0.81957 4263 3494 ((0.95*43)+(0.2*17))/60 OS/Park 0.2 0 0 0.8195652 Lots 0.35 0 0 Total 4263 3493.81 C =Weighted C Factor 0.82 A=Area(acres) 0.10 Required Gutter/Pipe Capacity (25-yr Storm) Tc Overland Flow Tc= 1.87 (1.1-CCf)D1i2/S1/3 Storm S = Slope of Basin (%) 0.5 Return C f C=Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf=Frequency Adjustment Factor 1.1 11 to 25 1.1 D =Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow(minutes)= 6.52 Tc Gutter Flow Tc=LN/60 V=(1.486/n)R2i3 S" n=Mannings Coefficient 0.013 R=Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S =slope(ft/ft) 0.005 L=length of gutter(ft) 88 V=mean velocity(ft/s) 2.12 Tc Gutter Flow(minutes)= 0.69 Tc Total (Overland+ Gutter)= 7.22 Q =CIA C= Weighted C Factor 0.82,(calculated above) I= 0.78 Tc o.64(in/hr) 3.03 Drainage Area#OAK WEST A=area(acres) 0.10 Qrequired (Cfs) = 0.24 Provided Gutter Capacity (flowing at 0.15' below ton of curb) Q= (1.486/n)AIe'S" n=Mannings Coefficient 0.013 A= area(f z) 1.24 P =wetted perimeter(ft) 9.23 R=Hydraulic Radius A/P (ft) 0.13 S = slope (ft/ft) 0.005 Qprovided (efS) = 2.63 GUTTER IMASADEQUATE CAPACITY Drainage Area#OAK WEST DESIGN REPORT STORM WATER MANAGEMENT ROSA SUBDIVISION Prepared for: JOHN ROSA Prepared by: C & H Engineering and Surveying, Inc. 205 Edelweiss Bozeman, MT 59718 (406) 587-1115 Project Number: 05230 June, 2005 STORM WATER MANAGEMENT Summary STORM WATER run-off from Rosa Subdivision will be directed to several storm water detention areas located throughout the site. Sheet D1, enclosed in the Appendix,highlights the individual drainage areas that drain to each storm water pond. The subdivision was divided into four separate watersheds, that will be directed to their own detention pond. Drainage area#1 will drain to a point at the southern boundary of the central park, near the intersection of Parkview Avenue and Glenwood Drive. Drainage area#2 will drain to a pond on the norther boundary of the central park,near the intersection of Annie Street and Rosa Way. Drainage area 43 will drain to two detention ponds located at the north portion of the parks#6 &7,by the intersection of Sherwood Way and Rosa Way. Drainage area#4 will drain to a detention pond located near the intersection of Rosa Way and Oak Street. All proposed ponds will have an outlet pipe to Baxter Ditch to ensure that the ponds drain after storm water events. Inlets will be placed to intercept the storm water runoff at intervals to ensure that the curb capacity is not exceeded, and to rout the storm water to the desired storm water detention area. The storm water runoff rate was calculated with the rational formula as shown. A runoff coefficient(C) of 0.35 was used for the lots Zoned R3, and 0.60 was used for the larger R4 and R-O lots as recommended by the City of Bozeman Design Standards, and a composite C value was used for the right of way due to the higher percentage of impervious area. COMPOSITE RUNOFF COEFFICIENT The runoff coefficient for the R/W Area at 60 ft. wide: C,i,,,= [(0.90x43 ft)+(0.20xl7 ft)]/60 ft = 0.70 r DRAINAGE AREA#1 Drainage Area#1 consists of a total of 266,080 ft2, with 86,910 ft2 of that being right of way,and 179,170 ft2 of medium density lots. Drainage area#1 will be divided into three subareas,one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to each catch basin. The time of concentration for sub-area#1-1 is calculated below: Time of Concentration Overland flow(115 ft @ 1.0%, C=0.35) = 14.3 min. Gutter flow(400 ft @ 0.95% avg. slope on Rosa Way) V=(1.486/n)W"Sv2 (n=0.013, A=1.24 ft, P=9.23, R"'=0.2623, S"2=0.0982) V=2.95 ft/s T=400 ft/2.95 ft/s/60s/min =2.3 min Total Time of Concentration = 16.6 minutes(0.28 hours) For a 25-year storm event Its= 0.78X-•64= 0.78(0.28)--64= 1.76 in/hr Q25 Lots= CIA=0.35(1.76 in/hr)(0.9361 acres) = 0.58 cfs Q25 r/w= CIA=0.70(1.76 in/hr)(0.3586 acres)= 0.44 cfs Q25 Total=(0.58+0.44) = 1.02 cfs=Total flow rate entering catch basin#1 The time of concentration for sub-area#1-2 is calculated below: Time of Concentration Overland flow(155 ft @ 1.0%, C=0.35) = 16.7 min. Gutter flow(470 ft @ 0.50% avg. slope on Brookside Lane) V= (1.486/n)W"Sv2 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, S"2=0.0707) V=2.12 ft/s T=470 ft/2.12 ft/s/60s/min =3.7 min Gutter flow(470 ft @ 0.95% avg. slope on Rosa Way) V= (1.486/n)R213SI12 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, Si2=0.0982) V=2.95 ft/s T=240 ft/2.95 ft/s/60s/min = 1.4 min Gutter flow(280 ft @ 0.60% avg. slope on Glenwood Drive) V=(1.486/n)R213Si12 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, Sv2=0.0775) V=2.32 ft/s T=280 ft/2.32 ft/s/60s/min =2.0 min Total Time of Concentration =23.8 minutes (0.40 hours) For a 25-year storm event Its= 0.78X--64= 0.78(0.40)-.64= 1.40 in/hr Q25 Lots = CIA=0.35(1.40 in/hr)(3.1770 acres)= 1.56 cfs Q25 r/w= CIA= 0.70(1.40 in/hr)(1.2709 acres) = 1.25 cfs Q25 Total=(1.56+1.25) =2.81 cfs=Total flow rate entering catch basin#2 The time of concentration for sub-area#1-3 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) =3.2 min. Gutter flow(300 ft @ 0.60% avg. slope on Glenwood Drive) ( V= (1.486/n)R2i3Sli2 (n=0.013,A=1.24 ft, P=9.23, W"=0.2623, Sv2=0.07746) V=2.32 ft/s T= 300 ft/2.32 ft/s/60s/min =2.2 min Total Time of Concentration =5.4 minutes (0.09 hours) For a 25-year storm event 125= 0.78X-•64= 0.78(0.09)--64= 3.64 in/hr Q25 r/w=CIA= 0.70(3.64 in/hr)(0.3656 acres) = 0.93 cfs Q25 Total= 0.93 cfs=Total flow rate entering catch basin#3 Q25 Total for Storm Sewer#1 = (1.02+2.81+0.93) =4.76 cfs The capacity of the curb and gutter, at a 0.60% slope, with a depth of water 0.15' below top of curb is calculated as follows: Q=(1.486/n)AR2"Sv2 n= 0.013 for Concrete A= 1.24 ft2 P = 9.23 ft V� ' R=A/P= 1.24/9.23 =0.1343 ft R"' =0.2623 ft S =0.0060 ft/ft S v2= 0.0775 ft/ft Q = (1.486/0.013)(1.24)(0.2623)(0.0775)=2.88 cfs. 2.81 cfs < 2.86 cfs — Gutter capacity is adequate DRAINAGE AREA#2 Drainage Area#2 consists of a total of 490,865 ft2, with 79,295 ft2 of that being right of way, 263,990 ft2 of park land, and 147,580 ft2 of medium density lots. Drainage area#2 will be divided into four subareas, three for each area that contributes to a catch basin that will be utilized,plus the portion of the park that will drain into the detention pond. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#2-1 is calculated below: Time of Concentration Overland flow(115 ft @ 1.00%, C=0.35) = 14.3 min. Gutter flow(830 ft @ 1.00% avg. slope on Rosa Way) V=(1.486/n)R2i3Sli2 (n=0.013,A=1.24 ft, P=9.23, W"=0.2623, S"2=0.1000) V=3.00ft/s T= 830 ft/3.00 ft/s/60s/min =4.6 min Total Time of Concentration = 18.9 minutes (0.32 hours) For a 25-year storm event Its= 0.78X-•64=0.78(0.32)-"64= 1.62 in/hr Q25 Lots= CIA= 0.35(1.62 in/hr)(1.7553 acres)= 1.00 cfs Q25 r/w= CIA=0.70(1.62 in/hr)(0.6123 acres) = 0.69 cfs Q25 Total= (1.00+0.69) = 1.69 efs=Total flow rate entering catch basin#4 The time of concentration for sub-area#2-2 is calculated below: Time of Concentration Overland flow(110 ft @ 1.00%, C=0.35) = 14.0 min. �" Gutter flow(830 ft @ 1.0% avg. slope on Rosa Way) V=(1.486/n)R2/3S'/2 (n=0.013, A=1.24 ft, P=9.23, R2/3=0.2623, S'/2=0.1000) t V= 3.00 ft/s T= 830 ft/3.00 ft/s/60s/min =4.6 min Total Time of Concentration = 18.6 minutes(0.31 hours) For a 25-year storm event Its=0.78X--64= 0.78(0.31)-•64 = 1.65 in/hr Q25 Lots= CIA= 0.35(1.65 in/hr)(1.656 acres)=0.96 cfs Q25 r/w=CIA= 0.70(1.65 in/hr)(0.9431 acres)= 1.09 cfs Q25 Total= (0.96+1.09) =2.05 cfs=Total flow rate entering catch basin#5 The time of concentration for sub-area#2-3 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) =3.2 min. Gutter flow(150 ft @ 0.60% avg. slope on Annie Street) V= (1.486/n)R2/3S'/2 (n=0.013, A=1.24 ft, P=9.23, R2/3=0.2623, S'/2=0.07746) V=2.32 ft/s T= 150 ft/2.32 ft/s/60s/min = 1.1 min Total Time of Concentration =4.3 minutes (0.09 hours) For a 25-year storm event Its = 0.78X--64= 0.78(0.07)--64=4.21 in/hr Q25 r/w= CIA=0.70(4.21 in/hr)(0.2649 acres)=0.78 cfs Q25 Total= 0.78 cfs=Total flow rate entering catch basin#6 Q25 Total for Storm Sewer#2= (1.69+2.05+0.78) =4.52 cfs DRAINAGE AREA#3 Drainage Area#3 consists of a total of 421,020 ft2,with 85,620 ft2 of that being right of way, 151,785 ft2 of park land, and 183,615 ft2 of medium density lots. Drainage area#3 will be divided into three subareas, one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#3-1 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) =3.2 min. Gutter flow(115 ft @ 0.60% avg. slope on Sherwood Way) V= (1.486/n)W/3S112 (n=0.013, A=1.24 ft, P=9.23, W"=0.2623, S"2=0.07746) V=2.32 ft/s T= 115 ft/2.32 ft/s/60s/min = 0.8 min Total Time of Concentration =4.0 minutes(0.07 hours) For a 25-year storm event Its = 0.78X-.64=0.78(0.07)-•64=4.30 in/hr Q25 r/w= CIA= 0.70(4.30 in/hr)(0.1625 acres) =0.49 cfs Q25 Total= 0.49 cfs=Total flow rate entering catch basin#7 & 8 Q25 Total for Storm Sewer#3 = 0.49 cfs The time of concentration for sub-area#3-2 is calculated below: Time of Concentration Overland flow(115 ft @ 1.0%, C=0.35) = 14.3 min. Gutter flow(320 ft @ 1.10% avg. slope on Rosa Way) V=(1.486/n)R2'3S'/2 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, S"2=0.1049) V=3.14 ft/s T=320 ft/3.14 ft/s/60s/min = 1.7 min Gutter flow(200 ft @ 0.60% avg. slope on Sherwood Way) V=(1.486/n)R213S'/2 (n=0.013, A=1.24 ft,P=9.23, R2"=0.2623, S"2=0.0775) V=2.32 ft/s T=200 ft/2.32 ft/s/60s/min = 1.4 min Total Time of Concentration = 17.4 minutes (0.29 hours) For a 25-year storm event I25 =0.7M.14= 0.78(0.29)-•64= 1.72 in/hr Q25 Lots= CIA= 0.35(1.72 in/hr)(0.7118 acres)= 0.43 cfs Q25 r/w= CIA=0.70(1.72 in/hr)(0.7375 acres)=0.89 cfs Q25 Total =(0.43+0.89)= 1.32 cfs=Total flow rate entering catch basin#9 The time of concentration for sub-area#3-3 is calculated below: Time of Concentration Overland flow(145 ft @ 1.0%, C=0.35) = 16.1 min. Gutter flow(620 ft @ 0.80% avg. slope on Parkview Avenue) V= (1.486/n)R213S112 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, S"2=0.0894) V=2.68 ft/s T= 620 ft/2.68 ft/s/60s/min =3.9 min Gutter flow(270 ft @ 0.60% avg. slope on Parkview Avenue) V= (1.486/n)R213S112 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, Sv2=0.0775) V=2.32 ft/s T=270 ft/2.32 ft/s/60s/min = 1.9 min Total Time of Concentration =21.9 minutes (0.37 hours) For a 25-year storm event I25 =0.78X-.64=0.78(0.37)".64= 1.47 in/hr Q25 Lots= CIA= 0.35(1.47 in/hr)(3.5035 acres) = 1.80 cfs Q25 r/w= CIA= 0.70(1.47 in/hr)(1.0655 acres)= 1.10 cfs Q25 Total= (1.80+1.10) =2.90 cfs=Total flow rate entering catch basin#10 Q25 Total for Storm Sewer#3 = (1.32+2.90)=4.22 cfs DRAINAGE AREA 94 Drainage Area#4 consists of a total of 474,050 ft2, with 143,825 ft2 of that being right of way, 40,660 ft2 of park land, and 289,565 ft2 of high density lots. Drainage area#4 will be divided into three subareas, one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#4-1 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) =3.2 min. Gutter flow(625 ft @ 1.20% avg. slope on Rosa Way) r-. V= (1.486/n)R2"S"2 (n=0.013, A=1.24 ft, P=9.23, R2i3=0.2623, S"2=0.1095) V=3.28 ft/s T= 625 ft/3.28 ft/s/60s/min =3.2 min Total Time of Concentration =6.4 minutes(0.11 hours) For a 25-year storm event Its= 0.78X--64=0.78(0.1 ly.14=3.20 in/hr Q25 r/w= CIA=0.70(3.20 in/hr)(0.5342 acres) = 1.20 cfs Q25 Total = 1.20 cfs=Total flow rate entering catch basin#11 The time of concentration for sub-area#4-2 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.8 min. Gutter flow(262.5 ft @ 0.60% avg. slope on A Street) V= (1.486/n)W"Sv2 (n=0.013, A=1.24 ft, P=9.23, R2i3=0.2623, S"2=0.0775) V=2.32 ft/s T=262.5 ft/2.32 ft/s/60s/min = 1.89 min Total Time of Concentration = 15.7 minutes (0.26 hours) For a 25-year storm event Its =0.78X--64 =0.78(0.26)-.64= 1.85 in/hr Q25 Lots= CIA= 0.60(1.85 in/hr)(1.4415 acres)= 1.60 cfs Q25 r/w= CIA= 0.70(1.85 in/hr)(0.47 acres) =0.61 cfs Q25 Total =(1.60+ 0.61)=2.21 cfs=Total flow rate entering catch basin#15 Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.8 min. Gutter flow(262.5 ft @ 0.60% avg. slope on A Street) V=(1.486/n)R2i3SIi2 (n=0.013,A=1.24 ft, P=9.23,R2i3=0.2623, Sv2=0.0775) V=2.32 ft/s T=262.5 ft/2.32 ft/s/60s/min = 1.89 min Total Time of Concentration = 15.7 minutes (0.26 hours) For a 25-year storm event Its =0.78X--64 =0.78(0.26)-'64= 1.85 in/hr Q25 Lots= CIA= 0.60(1.85 in/hr)(1.2609 acres) = 1.40 cfs Q25 r/w= CIA= 0.70(1.85 in/hr)(0.47 acres) = 0.61 cfs Q25 Total = (1.40+ 0.61) =2.01 cfs=Total flow rate entering catch basin#12 Q25 Total for Storm Manhole#2= (2.21 +2.01)=4.22 cfs The time of concentration for sub-area#4-3 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.9 min. Gutter flow(300 ft @ 1.20% avg. slope on Rosa Way) V=(1.486/n)R2i3Sli2 (n=0.013,A=1.24 ft, P=9.23, R2"=0.2623, Sv2=0.1095) V= 3.28 ft/s T= 300 ft/3.28 ft/s/60s/min = 1.5 min Total Time of Concentration = 15.4 minutes (0.26 hours) For a 25-year storm event I25=0.78X-.64= 0.78(0.26)--64 = 1.85 in/hr r. Q25 Lots= CIA= 0.60(1.85 in/hr)(1.9050 acres)=2.11 cfs Q25 r/w= CIA= 0.70(1.85 in/hr)(0.6319 acres) =0.82 cfs Q25 Total = (2.11+0.82)=2.93 cfs=Total flow rate entering catch basin#13 The time of concentration for sub-area#44 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.9 min. Gutter flow(300 ft @ 1.60% avg. slope on Rosa Way) V= (1.486/n)W"Sv2 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, Sv2=0.1265) V=3.79 ft/s T=300 ft/3.79 ft/s/60s/min = 1.3 min Total Time of Concentration = 15.2 minutes (0.25 hours) For a 25-year storm event I25 = 0.78X-.64= 0.78(0.25)--64= 1.89 in/hr Q25 Lots= CIA=0.60(1.89 in/hr)(1.7423 acres)= 1.98 cfs Q25 r/w= CIA= 0.70(1.89 in/hr)(0.8160 acres)= 1.08 cfs Q25 Total = (1.98+1.08) =3.06 cfs=Total flow rate entering catch basin#14 Q25 Total for Storm Sewer#4 =(1.20+4.42+2.93+3.06)= 11.61 cfs Drainage Area#1 15" PVC from Catch Basin 91 to Catch Basin#2 This pipe carries the storm water from drainage sub-area#1-1. As previously calculated we should anticipate a flowrate of 1.02 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.40 feet with a velocity of 3.00 ft/sec. 15" PVC from Catch Basin#2 to Catch Basin 93 This pipe carries the storm water from drainage sub-areas 1 A & 1-2. As previously calculated we should anticipate a flowrate of(1.02 +2.81) = 3.83 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.88 feet with a velocity of 4.17 ft/sec. 15" PVC from Catch Basin#3 to Pond #1 This pipe carries the storm water from drainage sub-areas 1-1, 1-2 & 1-3. As previously calculated we should anticipate a flowrate of(1.02 +2.81+0.93)=4.76 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.08 feet with a velocity of 4.22 ft/sec. Detention Pond#1 The total area served by Detention Pond#1 is 6.11 acres with a weighted C-factor of 0.464 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release,rate) is 1.07 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.07 cfs. The required storage for Detention Pond#1 is 3,215 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#1 will be 2.09 inches in width. These calculations are included with the calculations for sizing the pond. Drainage Area#2 15" PVC from Catch Basin#4 to Catch Basin #5 This pipe carries the storm water from drainage sub-area 2-1. As previously calculated we should anticipate a flowrate of 1.69 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.53 feet with a velocity of 3.44 ft/sec. 15" PVC from Catch Basin#6 to Catch Basin #5 This pipe carries the storm water from drainage sub-area 2-3. As previously calculated we should anticipate a flowrate of 0.78 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.75% slope. The 15-inch pipe will flow at a depth of 0.32 feet with a velocity of 3.21 ft/sec. 15" PVC from Catch Basin 45 to Storm MH#1 to Detention Pond#2 This pipe carries the storm water from drainage sub-area 2-1, 2-2, &2-3. As previously calculated we should anticipate a flowrate of(1.69+0.78+2.05) =4.52 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.01 feet with a velocity of 4.24 ft/sec. Detention Pond#2 The total area served by Detention Pond#2 is 11.270 acres with a weighted C-factor of 0.326 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release rate) is 1.801 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.801 cfs. The required storage for Detention Pond#2 is 3,610 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#2 will be 3.53 inches in width. These calculations are included with the calculations for sizing the pond. l Drainage Area #3 15" PVC from Catch Basin 97-8 to Pond 93 This pipe carries the storm water from drainage sub-area 3-1. As previously calculated we should anticipate a flowrate of 0.49 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 1.00% slope. The 15-inch pipe will flow at a depth of 0.23 feet with a velocity of 3.10 ft/sec. Detention Pond #3 The total area served by Detention Pond#3 is 2.23 acres with a weighted C-factor of 0.367 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release rate) is 0.367 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 0.367 cfs. The required storage for Detention Pond#3 is 525 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#3 will be .72 inches in width. These calculations are included with the calculations for sizing the pond. 15" PVC from Catch Basin#10 to Catch Basin #9 This pipe carries the storm water from drainage sub-area 3-3. As previously calculated we should anticipate a flowrate of 2.90 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.72 feet with a velocity of 3.94 ft/sec. 15" PVC from Catch Basin #9 to Pond #4 This pipe carries the storm water from drainage sub-area 3-2 & 3-3. As previously calculated we should anticipate a flowrate of(2.90+1.32) =4.22 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.95 feet with a velocity of 4.22 ft/sec. Detention Pond#4 The total area served by Detention Pond#4 is 7.440 acres with a weighted C-factor of 0.3.96 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release rate) is 1.11 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.11 cfs. The required storage for Detention Pond#4 is 3,340 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#4 will be 2.18 inches in width. These calculations are included with the calculations for sizing the pond. Drainage Area 94 15" PVC from Catch Basin#14 to Catch Basin #13 This pipe carries the storm water from drainage sub-area 4-4. As previously calculated we should anticipate a flowrate of 3.06 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.75 feet with a velocity of 3.99 ft/sec. 15" PVC from Catch Basin#12 to Storm MH#2 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 2.21 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.61 feet with a velocity of 3.69 ft/sec. 15" PVC from Catch Basin#15 to Storm MH#2 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 2.01 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.58 feet with a velocity of 3.60 ft/sec. 15" PVC from Storm MH#2 to Catch Basin#13 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 4.22 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.39 feet with a velocity of 4.23 ft/sec. 18" PVC from Catch Basin 913 to Catch Basin #11 This pipe carries the storm water from drainage sub-area 4-2, 4-3, &4-4. As previously calculated we should anticipate a flowrate of(4.22+2.93+3.06) = 10.21 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 18" PVC pipe at 1.00% slope. The 18-inch pipe will flow at a depth of 1.20 feet with a velocity of 6.77 ft/sec. 18" PVC from Catch Basin#11 to Detention Pond#5 This pipe carries the storm water from drainage sub-area 4-1, 4-2, 4-3, &4-4. As previously calculated we should anticipate a flowrate of(1.20+4.22+2.93+3.06) = 11.41 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 18" PVC pipe at 1.50% slope. The 18-inch pipe will flow at a depth of 1.10 feet with a velocity of 8.22 ft/sec. Detention Pond #5 The total area served by Detention Pond#5 is 10.88 acres with a weighted C-factor of 0.596 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release rate) is 1.61 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.61 cfs. The required storage for Detention Pond#5 is 9,200 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#5 will be 3.16 inches in width. These calculations are included with the calculations for sizing the pond. Rosa Subdivision: Stormwater Addendum DRAINAGE AREA#1 (Now includes Durston Road) Drainage Area#1 consists of a total of 297,279 ft2, with 118,109 ft2 of that being right of way and 179,170 ft2 of high density lots. Drainage area#1 will be divided into three subareas, one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to each catch basin. The time of concentration for sub-area#1-1 is calculated below: Time of Concentration Overland flow(115 ft @ 1.0%, C=0.60) = 14.3 min. Gutter flow(400 ft @ 1.30% avg. slope on Rosa Way) V= (1.486/n)W"Sv2 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, 5112=0.114) V=2.51 ft/s T=400 ft/2.51 ft/s/60s/min =2.66 min Total Time of Concentration = 16.96 minutes(0.28 hours) For a 25-year storm event Its= 0.78X-.64=0.78(0.28)-.64= 1.76 in/hr Q25 Lots= CIA= 0.35(1.76 in/hr)(0.9361 acres) = 0.58 cfs Q25 r/w= CIA=0.70(1.76 in/hr)(0.5084 acres)=0.63 cfs (includes Durston Road) Q25 Total =(0.58+0.63) = 1.21 cfs=Total flow rate entering catch basin#1 Capacity of curb and gutter at 0.9%Average slope (Rosa Way&Durston Road) Q= (1.486/n)AR2/3S112 n= 0.013 for Concrete A= 1.24 ft2 P= 9.23 ft R=A/P = 1.24/9.23 = 0.1343 ft R " = 0.2623 ft S = 0.009 ft/ft SU2= 0.09487 ft/ft Q =(1.486/0.013)(1.24)(0.2623)(0.09487)=3.53 cfs. Total flow in gutter along Rosa Way and Durston Road Q = 1.21 cfs 1.21 cfs s 3.07 cfs - Gutter capacity is adequate The time of concentration for sub-area#1-2 is calculated below: Time of Concentration Overland flow(155 ft @ 1.0%, C=0.35)= 16.7 min. Gutter flow(470 ft @ 0.5% avg. slope on Brookside Lane) V= (1.486/n)R2i3S112 (n=0.013, A=1.24 ft,P=9.23, W"=0.2623, Sv2=0.0707) V=2.12 ft/s T=470 ft/2.12 ft/s/60s/min =3.7 min Gutter flow(470 ft @ 1.30% avg. slope on Rosa Way V= (1.486/n)RIIISIi2 (n=0.013, A=1.24 ft, P=9.23, R"'=0.2623, Sv2=0.1140) V=3.42 ft/s T=470 ft/3.42 ft/s/60s/min =2.3 min Gutter flow(470 ft @ 0.601/o avg. slope on Glenwood Drive V= (1.486/n)R2i3S"2 (n=0.013, A=1.24 ft, P=9.23, W"=0.2623, S"2=0.0982) V=2.32 ft/s T=280 ft/2.32 ft/s/60s/min =2.0 min Gutter flow(470 ft @ 0.50% avg. slope on Durston Road V= (1.486/n)R2i3SIi2 (n=0.013,A=1.24 ft, P=9.23, R2i3=0.2623, S"2=0.0707) V=2.12 ft/s T=470 ft/2.12 ft/s/60s/min =3.69 min Total Time of Concentration=28.4 minutes (0.47 hours) For a 25-year storm event I25=0.78X--64= 0.78(0.47)-•64= 1.26 in/hr Q25 Lots=CIA= 0.35(1.26 in/hr)(3.1770 acres) = 1.40 cfs Q25 r/w= CIA= 0.70(1.26 in/hr)(1.8373 acres) = 1.62 cfs (includes Durston Road) Q25 Total= (1.40+1.62)=3.02 cfs=Total flow rate entering catch basin#2 The time of concentration for sub-area#1-3 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) =3.2 min. Gutter flow(300 ft @ 0.60% avg. slope on Glenwood Drive) V= (1.486/n)R2i3Sv2 (n=0.013, A=1.24 ft, P=9.23, R2"=0.2623, Sv2=0.0982) V=-2.32 ft/s T=300 ft/2.32 ft/s/60s/min =2.2 min Total Time of Concentration=5.4 minutes (0.09 hours) For a 25-year storm event Its=0.78X-•64=0.78(0.09),64 =3.64 in/hr Q25 r/w=CIA=0.70(3.64 in/hr)(0.3656 acres)=0.93 cfs Q25 Total= 0.93 cfs=Total flow rate entering catch basin#3 Q25 Total for Storm Sewer#1 = (1.21 +3.02+0.93) = 5.16 cfs Drainage Area#1 15" PVC from Catch Basin#1 to Catch Basin#2 This pipe carries the storm water from drainage sub-area#1-1. As previously calculated we should anticipate a flowrate of 1.21 cfs from a 25-year storm event. Calculations are enclosed for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.44 feet with a velocity of 3.14 ft/sec. 15" PVC from Catch Basin #2 to Catch Basin 93 This pipe carries the storm water from drainage sub-areas 1-1 & 1-2. As previously calculated we should anticipate a flowrate of(1.21 +3.02)=4.23 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.95 feet with a velocity of 4.23 ft/sec. 18" PVC from Catch Basin#3 to Pond#1 This pipe carries the storm water from drainage sub-areas 1-1, 1-2 and 1-3. As previously calculated we should anticipate a flowrate of(1.21 +3.02+ 0.93) = 5.16 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 18" PVC pipe at 0.30% slope. The 15-inch pipe will flow at a depth of 1.11 feet with a velocity of 3.68 ft/sec. Detention Pond #1 The total area served by Detention Pond#1 is 6.82 acres with a weighted C-factor of 0.489 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow(acceptable release rate) is 1.192 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.192 cfs. The required storage for Detention Pond 41 is 3,900 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#1 will be 2.34 inches in width. These calculations are included with the calculations for sizing the pond. r' i Shoat I of 1 CO.LOQ XOAON U bSM V1 101 L MIC> U U I L f 661 —Lf' s SL 101 j 'i bs 0A 01101 1�§ i- 9101 -- - i 11 1 3t 101 !� V7,,1Q1 ol 01 6 101\ 'z lu b 3zfb 101 Lo v vt 3Z 101 Coco Co 0 101'. f z ez I DD0'9 4. 101 —w U bS 79jr V1 iol £l 101 G�101 coitj M E jr \\0Z 101 MJB-AREik z 161- Wdr dD --- - ---- ---- 09 U) (o �Vofiz 0 LjO.Loo azz L,L 0.t ON] z 35(-11-88000M d, L2 B V 0 ffi st OT 12 < IIII ji. 0 >: F, W -0 6 C) DRAINAGE PLAN SCALE I-20V Scale In Feet 200 0 200 I Dmv(W Date G127105 60 0 60 Scale In Meters D 1 #047701