HomeMy WebLinkAbout12-12-16 CC Mtg - C7. Wastewater Fund CIP Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Anna Rosenberry, Administrative Services Director SUBJECT: Adopt the Wastewater Fund Capital Improvement Plan (CIP) for Fiscal Years 2018-2022. AGENDA ITEM TYPE: Consent MEETING DATE: December 12, 2016 RECOMMENDATION: Adopt the Wastewater Fund Capital Improvement Plan (CIP) for Fiscal Years 2018-2022. BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital Improvements Plan and submit it to the Commission by December 15th. Similar to recent years past, we are bringing the various parts of the plan forward as items on the Consent agenda. We will be prepared to address questions, if they arise, at the public meeting. The Public Works, City Manager, and other city staff met in October and November to develop the attached Capital Plan for the equipment and capital needs of the Wastewater Fund. The Wastewater Fund CIP tracks the capital equipment replacements and construction projects for Wastewater Operations (collection system) and the Water Reclamation Facility (WRF). Item of Note: • PW04 PROPERTY ON CORNER OF ASPEN & ROUSE – Property in close proximity has been located for purchase to potentially expand the shops and offices. This cost would be shared with Street Maintenance Fund and Water Fund. 169 • WW71 WRF FACILITY MASTER PLAN UPDATE has been added at $250,000. • WW49 ROLL-OFF STORAGE BUILDING CONSTRUCTION & POSSIBLE 2ND SCREW PRESS ENCLOSURE – This project would be a covered addition of the roll- off loading area and would capture and redirect exhaust to keep the roll-offs from freezing in the winter and would act as storage for roll-offs and totes. • Several other recurring items, such as WW08-18 WASTEWATER PIPE REPLACEMENT, have been scheduled, adjusted or added based on current needs. UNRESOLVED ISSUES: None. ALTERNATIVES: As suggested by the City Commission. If the Commission does not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda. FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for FY18. Report compiled on: November 30, 2016 Attached: Wastewater Fund CIP 170 Wastewater Fund Capital Improvement PlanFinancial Summary Current YearFY17 FY18 FY19 FY20 FY21 FY22UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,354,455$     1,625,992$         1,099,406$      1,670,727$     2,701,654$     3,896,834$     ‐$                     Plus:  Wastewater Revenues Dedicated to CIP 2,112,538$     2,175,914$         2,241,191$      2,308,427$     2,377,680$     2,449,010$     ‐$                     Less:  Scheduled CIP Project Costs (1,841,001)$    (2,702,500)$       (1,669,870)$    (1,277,500)$   (1,182,500)$    (1,602,500)$   (16,034,333)$   Projected Year‐End Cash Dedicated to CIP 1,625,992$     1,099,406$         1,670,727$      2,701,654$     3,896,834$     4,743,344$     (16,034,333)$   Assumptions Made for Revenue Estimates: Current YearFY17 FY18 FY19 FY20 FY21 FY22Estimated Annual Wastewater Revenues 8,450,151$       8,450,151$           8,703,656$       8,964,765$       9,233,708$       9,510,719$         Estimated Annual Increase 0.0% 3% 3% 3% 3% 3%Total Estimated Revenues 8,450,151$       8,703,656$           8,964,765$       9,233,708$       9,510,719$       9,796,041$       Current Revenues Dedicated to CIP % 25.0% 25.0% 25.0% 25.0% 25.0% 25.0%  Plus:  Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%  Total % Dedicated to CIP 25.0% 25.0% 25.0% 25.0% 25.0% 25.0%Total Estimated Revenues Dedicated to CIP 2,112,538$       2,175,914$           2,241,191$       2,308,427$       2,377,680$       2,449,010$       ProjectedProjectedCURRENT18,000,00016,000,00014,000,00012,000,00010,000,0008,000,0006,000,0004,000,0002,000,0000Wastewater Fund Projects & Equipment 171 CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEUnscheduledFY21FY18FY19FY20FY22Wastewater FundPW04ENGINEERINGPROPERTY ON CORNER OF ASPEN & ROUSE$0$100,000$0WW07ENGINEERINGANNUAL WASTEWATER PIPE REPLACEMENT PROGRAM ‐ DESIGN$22,500$22,500$22,500$22,500$22,500WW08‐18ENGINEERINGWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2018$1,000,000WW08‐19ENGINEERINGWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2019$1,000,000WW08‐20ENGINEERINGWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2020$1,000,000WW08‐21ENGINEERINGWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2021$1,000,000WW08‐22ENGINEERINGWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2022$1,000,000WW27ENGINEERINGANNUAL WATERSHED STUDY & STREAM MODELING$60,000$60,000$60,000$60,000$60,000GF227FINANCEERP REPLACEMENT "SUNGARD REPLACEMENT/UPGRADE"$333,333PW03PUBWORKS ADMINVEHICLE MAINTENANCE DESIGN & STORAGE CONSTRUCTION$50,000STR67STREETS OPCOVERED STORAGE AT SHOPS COMPLEX$50,000WW54Wastewater OpREPLACE #1783 ‐ 1995 FORD DUMP TRUCK$95,000WW65Wastewater OpDIGITAL UNIVERSAL CAMERA ‐ DUC$70,000WW86Wastewater OpWHEELED EXCAVATOR$151,000WW39WRFSANDBLAST & PAINT CLARIFIER DRIVES AND BEACHES$90,000$90,000WW42WRFPRIMARY CLARIFIER COVER$1,500,000WW45WRFFINAL & SECONDARY CLARIFIER LAUNDER COVERS$200,000WW49WRFROLL‐OFF STORAGE BUILDING CONSTRUCTION & POSSIBLE 2ND SCREW PRESS ENCLOSURE$600,000WW50WRFREFRIGERATED AUTOMATIC SAMPLER$10,000172 CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEUnscheduledFY21FY18FY19FY20FY22WW53WRFPOSITIVE DISPLACEMENT LOBE PUMPS$50,000WW58WRFCHIP SEAL AND TOPCOAT WRF ASPHALT$47,370WW66WRFODOR CONTROL FOR OLD PRETREATMENT BUILDING$40,000WW69WRFWRF FACILITY R&R$50,000$50,000$50,000$50,000$50,000WW70WRFWRF FACILITY ENGINEERING & OPTIMIZATION$50,000$50,000$50,000$50,000$50,000WW71WRFWRF FACILITY MASTER PLAN UPDATE$250,000WW76WRFTHIRD PRETREATMENT SCREEN$300,000WW78WRFSERVER REPLACEMENT AT WRF (WRFCTRLBAK)$10,000WW79WRFWRF IMPROVEMENTS FOR ENERGY SUSTAINABILITY$4,000,000WW80WRFLAGOON VALVE REPLACEMENT IN LIFT #3, CLEAN OUT REPLACEMENT ON SLUDGE LINE TO LAGOON; PUMP, VALVES AND PIPING TO PUMP SLUDGE BACK FROM THE SMALL LAGOON$50,000WW81WRFMEMBRANE ROOF REPLACEMENT ON OLD DIGESTER BUILDING (DIG 1 & 2)$60,000WW83WRFUFAT GRAVITY THICKENER DRIVE AND ARMS REPLACEMENT$400,000WW84WRFSERVER REPLACEMENT AT WRF (WRFCTRLPRI)$10,000WW85WRFWRF PROCESS UPGRADES TO IMPROVE NUTRIENT RECOVERY$10,000,000Summary for  Wastewater Fund (33 items)Totals by year:$1,182,500 $1,602,500$2,702,500$16,034,333FY21FY22FY18UnscheduledFY20$1,277,500$1,669,870FY19173 CIP Project Fund Wastewater Fund PROJECT NUMBER GF227 DEPARTMENT FINANCE PROJECT NAME ERP Replacement "SunGard Replacement/Upgrade" FY18 FY19 Unscheduled $333,333 DESCRIPTION OF PROJECT ERP Replacement "SunGard Replacement/Upgrade" ALTERNATIVES CONSIDERED Continue running current SunGard package. Use SunGard.net (Naviline EDGE) as an improvement to the current system, but not a full replacement. ADVANTAGES OF APPROVAL Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compilation of Commission reports and packets for Community Development. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Unknown. Dependent on the option chosen. FUNDING SOURCES General Fund 33%; Water Fund 33%; Wastewater Fund 33% New Replacement Equipment Project FY20 FY21 FY22 174 CIP Project Fund Wastewater Fund PROJECT NUMBER PW03 DEPARTMENT PUBWORKS ADMIN PROJECT NAME Vehicle Maintenance Design & Storage Construction FY18 FY19 $50,000 Unscheduled DESCRIPTION OF PROJECT Design and construct vehicle storage Describe the criticality (i.e., importance) of this project to the operation: Having equipment, especially winter equipment, inside and ready to go extends the life, produces less emissions by not having to warm up and shortens response time. Which infrastructure assets are maintained by this equipment: All of our rolling stock and equipment. How is efficiency improved with this equipment: The difference in getting in a motor grader that is parked inside vs. one that is parked outside in -20 degree weather is enormous. Equipment stays in better shape. Much less wear and tear on drivetrain and hydraulics. Easily adds an hour of productivity to every shift. How is this project leveraged with other stakeholders/projects/funds: By being located next to existing city property, we could aggregate the lots giving even more useful space. ALTERNATIVES CONSIDERED Not build and only use for outdoor storage. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Equipment continues to degrade from the sun and exposure. Large inside storage for several departments. Equipment would be located next to current Vehicle Maintenance Shop. Good access onto Rouse and Griffin. Early morning shift equipment could be stored here so as not to disturb the neighbors in this mostly zoned Industrial area. With this building, Streets could switch to producing our own brine solution for pre wet of the sand. We wouldn't have to use mag chloride which is about 4-5 times more expensive than salt brine. Gallatin County has expressed interest in buying brine from us. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Normal building maintenance. Possibly heat with waste oil from the Shops. Possibly heat with wood chips from Forestry. FUNDING SOURCES This project totals $200,000. It will be split evenly 4 ways: Water Fund ($50,000), Wastewater Fund ($50,000), Street Maintenance ($50,000), and Parks ($50,000). New Replacement Equipment Project FY20 FY21 FY22 175 CIP Project Fund Wastewater Fund PROJECT NUMBER PW04 DEPARTMENT ENGINEERING PROJECT NAME Property on Corner of Aspen & Rouse FY18 $100,000 FY19 Unscheduled DESCRIPTION OF PROJECT Property Purchase to expand shops area and potentially offices. This is an opportunity to make more land available for project PW01-SH - Shops Expansion. ALTERNATIVES CONSIDERED Do not purchase the property. Wait to purchase at a later date. ADVANTAGES OF APPROVAL Larger contiguous land area for City Shops. The Shops Expansion project has been a scheduled CIP for a number of years. This item could bring an important piece of land into that project area, making a better-functioning property at Rouse and Tamarack. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Building Maintenance would be needed to keep the existing structure useful. FUNDING SOURCES Split 33/33/33 between Water, Wastewater and Street Maintenance Funds. New Replacement Equipment Project FY20 FY21 $0 FY22 $0 176 CIP Project Fund Wastewater Fund PROJECT NUMBER STR67 DEPARTMENT STREETS OP PROJECT NAME Covered Storage At Shops Complex FY18 FY19 Unscheduled $50,000 DESCRIPTION OF PROJECT Covered Storage at Shops Complex Describe the criticality (i.e., importance) of this project to the operation: Getting equipment parked inside greatly extends the life of the equipment. Which infrastructure assets are maintained by this equipment: All of our rolling stock and equipment. How is efficiency improved with this equipment: The difference in getting in a motor grader that is parked inside vs. one that is parked outside in -20 degree weather is enormous. Equipment stays in better shape. Much less wear and tear on drivetrain and hydraulics. Easily adds an hour of productivity to every shift. What is the impact (i.e., scope-of-use) for this equipment: Equipment and vehicle storage. What are the implications of deferring the purchase of this equipment: Equipment continues to degrade from the sun and exposure. How is this project leveraged with other stakeholders/projects/funds: At the proper site we could build one big enough to house other department’s equipment. Project is split 50% Street Maintenance Fund, 20% Water Fund, & 25% Wastewater Fund. Are there other affected projects: Depends where this building is located. ALTERNATIVES CONSIDERED Keep parking millions of dollars’ worth of equipment outside. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Equipment continues to degrade from the sun and exposure. Better equipment management. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Normal building maintenance. FUNDING SOURCES 50% Street Maintenance Fund, 25% Water Fund, 25% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 177 CIP Project Fund Wastewater Fund PROJECT NUMBER WW07 DEPARTMENT ENGINEERING PROJECT NAME Annual Wastewater Pipe Replacement Program - Design FY18 $22,500 FY19 $22,500 Unscheduled DESCRIPTION OF PROJECT This item provides for design work to be completed every-other year, in anticipation of the Annual System Upgrades. Describe the criticality (i.e., importance) of this project to the operation: Annual wastewater pipe replacement projects minimize service interruptions or main breaks attributable to aging infrastructure. Are there other affected projects: Annual Wastewater Pipe Replacement Program project would be delayed if not done. ALTERNATIVES CONSIDERED ADVANTAGES OF APPROVAL Provides survey work needed for design of necessary sewer system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED NA FUNDING SOURCES 100% Wastewater Utility Fund New Replacement Equipment Project FY20 $22,500 FY21 $22,500 FY22 $22,500 178 CIP Project Fund Wastewater Fund PROJECT NUMBER WW08-18 DEPARTMENT ENGINEERING PROJECT NAME Wastewater Pipe Replacement Program - Construction in 2018 FY18 $1,000,000 FY19 Unscheduled DESCRIPTION OF PROJECT This project would complete design, bid and begin construction in the Spring/Summer of 2018. Priority will be places on the sewer segment on S Grand from Olive to Hayes to coincide with the S Grand street reconstructions scheduled for FY18. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL Provides for the construction of necessary wastewater system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 179 CIP Project Fund Wastewater Fund PROJECT NUMBER WW08-19 DEPARTMENT ENGINEERING PROJECT NAME Wastewater Pipe Replacement Program - Construction in 2019 FY18 FY19 $1,000,000 Unscheduled DESCRIPTION OF PROJECT This project would complete design, bid and begin construction in the Spring/Summer of 2019. Priority will be places on the sewer segment on S Tracy from College to Babcock to coincide with the S Tracy street reconstructions scheduled for FY19. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL Provides for the construction of necessary wastewater system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 180 CIP Project Fund Wastewater Fund PROJECT NUMBER WW08-20 DEPARTMENT ENGINEERING PROJECT NAME Wastewater Pipe Replacement Program - Construction in 2020 FY18 FY19 Unscheduled DESCRIPTION OF PROJECT This project would complete design, bid and begin construction in the Spring/Summer of 2020. Priority will be places on the sewer segment on S Black from College to the Cul-De-Sac to coincide with the S Black street reconstructions scheduled for FY20. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL Provides for the construction of necessary wastewater system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 $1,000,000 FY21 FY22 181 CIP Project Fund Wastewater Fund PROJECT NUMBER WW08-21 DEPARTMENT ENGINEERING PROJECT NAME Wastewater Pipe Replacement Program - Construction in 2021 FY18 FY19 Unscheduled DESCRIPTION OF PROJECT This project would complete design, bid and begin construction in the Spring/Summer of 2021. Priority will be places on the sewer segment on N Tracy from Villard to Peach to coincide with the N Tracy street reconstructions scheduled for FY21. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL Provides for the construction of necessary wastewater system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 FY21 $1,000,000 FY22 182 CIP Project Fund Wastewater Fund PROJECT NUMBER WW08-22 DEPARTMENT ENGINEERING PROJECT NAME Wastewater Pipe Replacement Program - Construction in 2022 FY18 FY19 Unscheduled DESCRIPTION OF PROJECT This project would complete design, bid and begin construction in the Spring/Summer of 2022. Priority will be places on the sewer segment on N 17th from Durston to the end to coincide with the N 17th street reconstructions scheduled for FY22. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL Provides for the construction of necessary wastewater system maintenance work. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 $1,000,000 183 CIP Project Fund Wastewater Fund PROJECT NUMBER WW27 DEPARTMENT ENGINEERING PROJECT NAME Annual Watershed Study & Stream Modeling FY18 $60,000 FY19 $60,000 Unscheduled DESCRIPTION OF PROJECT Develop a comprehensive, multi-year watershed study and computer model for the East Gallatin River, which would enable the City and DEQ to better determine stream load allocations and develop a more scientifically valid TMDL for the river segment we discharge to. This will require annual field sample collection, laboratory analytical work, and detailed computer modeling using calibrated and validated datasets. Describe the criticality (i.e., importance) of this project to the operation: Crucial tool to inform MPDES discharge permit negotiations and compliance with MT numeric nutrient regulations What regulations or standards are attained with this project: Future MPDES discharge permit compliance. How is this project leveraged with other stakeholders/projects/funds: Leverages cooperative relationship with Gallatin Local Water Quality District in the performance of field sampling activities. Are there other affected projects: Project has significant potential to affect scope of future upgrades to WRF to meet numeric nutrient limitations imposed by DEQ Circular 12A and implemented through future MPDES discharge permits. Stream modeling may reduce or eliminate the need for future upgrades dependent upon the results of ongoing data collection and model calibrations. Modeling could identify that assimilative capacity is available in the East Gallatin River or that the EGR is nutrient limited. Model also essential to identify nutrient trade opportunities which could be a significant MPDES compliance tool. ALTERNATIVES CONSIDERED Not undertake this work and risk having to accept the TMDL and waste load allocations the DEQ has proposed in their original draft documents. This decision could greatly limit our ability to appeal future nutrient limitations and could result in non-compliance. ADVANTAGES OF APPROVAL This watershed study will greatly enhance the City’s understand of our impact on the East Gallatin River and enable us to more successfully negotiate future permit limits with the DEQ. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED None, unless additional stream sampling is desired in subsequent years. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 $60,000 FY21 $60,000 FY22 $60,000 184 CIP Project Fund Wastewater Fund PROJECT NUMBER WW39 DEPARTMENT WRF PROJECT NAME Sandblast & Paint Clarifier Drives and Beaches FY18 $90,000 FY19 $90,000 Unscheduled DESCRIPTION OF PROJECT Sandblast and paint old clarifier drives, beaches, baffles and weirs. Describe the criticality (i.e., importance) of this project to the operation: The old final clarifiers were installed in the late 1980's and need to be painted to extend their useful life. Which infrastructure assets are maintained by this equipment: Final Clarifiers. What is the impact (i.e., scope-of-use) for this equipment: Painting the clarifier drives will preserve the infrastructure and delay the purchase of new stainless drives. ALTERNATIVES CONSIDERED Do nothing ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Not painting the clarifier drives will speed their deterioration which may result in failure of the drives before plans can be made to replace them. Replace lost & chipping paint on old clarifiers to prevent further deterioration of existing infrastructure. These clarifiers have not been painted since they were installed in 1985. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No new operating costs. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 185 CIP Project Fund Wastewater Fund PROJECT NUMBER WW42 DEPARTMENT WRF PROJECT NAME Primary Clarifier Cover FY18 FY19 Unscheduled $1,500,000 DESCRIPTION OF PROJECT Install a geodesic dome cover with 8 foot side walls on the 3 primary clarifiers. The installation would include a door, two skylights and a vent tube. The clarifier drive motor and controls would have to be explosion proof. Describe the criticality (i.e., importance) of this project to the operation: Not having to use all the primary clarifiers during the winter would allow larger particulate carbon to be flushed into the Bio-Trains postponing the purchase of supplemental carbon to reduce the total nitrogen in the facility effluent. Covering the primary clarifiers would allow the capturing of odors from the raw sewage they contain and direct these odors to treatment equipment. These odors are now reaching the residences near the facility and Springhill Road. Which infrastructure assets are maintained by this equipment: The three Primary Clarifiers. How is efficiency improved with this equipment: Not having to use all the primary clarifiers during the winter would allow larger particulate carbon to be flushed into the Bio-Trains postponing the purchase of supplemental carbon to reduce the total nitrogen in the facility effluent. What is the impact (i.e., scope-of-use) for this equipment: This equipment is used to reduce odors and improve the efficiency of the BNR process reducing nutrient discharges to the river. ALTERNATIVES CONSIDERED Do nothing ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Odors from raw sewage are not contained within the facilities boundaries and drift to near by neighbors and traffic on Springhill Road. Enclosing the primary clarifiers will trap these odors so they can be eliminated on the property. The Bozeman WRF is limited in the amount of carbon needed to remove nitrates with the BNR process. Covering the primary clarifiers will allow more carbon to be utilized by the process improving nutrient removal year round. Covering the primary clarifiers will allow odor control & eliminate cleaning & painting. Cleaning & painting of all railings and catwalks is an on-going maintenance issue to remove grease & droppings deposited by birds. Covers on primary clarifiers would allow some clarifiers not to be used during the winter ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Only maintenance of odor control would be additional. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 186 CIP Project Fund Wastewater Fund PROJECT NUMBER WW45 DEPARTMENT WRF PROJECT NAME Final & Secondary Clarifier Launder Covers FY18 $200,000 FY19 Unscheduled DESCRIPTION OF PROJECT Cover effluent launder of one final clarifier to eliminate algal growth in the launder. Describe the criticality (i.e., importance) of this project to the operation: Secondary Launder Covers will reduce the algae in the clarifier launders to a level that they will need only to be cleaned only once or twice a year. Currently there is a brush system installed on the skimmer arm that needs to be maintained constantly to insure proper operation. Some brushes can fall into the clarifier and could damage the clarifier drive or get stuck in the waste sludge piping. Which infrastructure assets are maintained by this equipment: Final Clarifiers. How is efficiency improved with this equipment: It will eliminate the man hours needed to maintain the brush system now in place and prevent clarifier damage. What is the impact (i.e., scope-of-use) for this equipment: It will eliminate the man hours needed to maintain the brush system now in place and prevent clarifier damage. ALTERNATIVES CONSIDERED Continue using a brush system to reduce the amount of algal growth. This method requires continual maintenance and there is a risk of brushes breaking off and falling into the clarifier. This could block the wasting hopper in the clarifier. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: The man hours used to maintain the brush system can be put to better use and possible infrastructure damage could be eliminated. Elimination of the brush system with its maintenance and dangers. Maintenance on the launder would be cut to twice a year for a quick manual cleaning allowing operators to spend time on other duties. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED None. Would actually cut operating costs (time and materials) FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 187 CIP Project Fund Wastewater Fund PROJECT NUMBER WW49 DEPARTMENT WRF PROJECT NAME Roll-Off Storage Building Construction & Possible 2nd Screw Press Enclosure FY18 $600,000 FY19 Unscheduled DESCRIPTION OF PROJECT Construction of a roll-off building and possible 2nd screw press enclosure. Describe the criticality (i.e., importance) of this project to the operation: Currently, an enclosed area consisting of concrete blankets suspend by cables and heated with torpedo heaters keeps the roll-offs from freezing in the truck storage building, where they are stored over night during the winter. The addition would return the needed space in the truck storage building and would reduce heating costs by using the exhaust air from the solids handling building. How is efficiency improved with this equipment: Less energy would be used if an extension to the roll-off loading area was built that could use exhaust air from the solids dewatering building to heat it. What is the impact (i.e., scope-of-use) for this equipment: Storing roll-offs, polymer totes and possibly housing a screw press. ALTERNATIVES CONSIDERED Construction of a roll-off loading bay extension for roll-off storage and possibly a screw press enclosure. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Higher energy costs associated with heating a make shift storage area in the truck storage building. Increased safety risks associated with using and fueling torpedo heaters inside a building. This addition to the existing roll-off loading area would serve as storage for the sludge roll-offs to keep them from freezing and reduce odors. This addition will also be available to house a second screw press and polymer tote storage. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED This addition could be heated with exhaust air from the Solids Handling Building, reducing costs. If a screw press was also housed in this addition, electrical costs for pumping and press operation would be additional. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 188 CIP Project Fund Wastewater Fund PROJECT NUMBER WW50 DEPARTMENT WRF PROJECT NAME Refrigerated Automatic Sampler FY18 $10,000 FY19 Unscheduled DESCRIPTION OF PROJECT Purchase a new refrigerated sampler for the influent, primary, and effluent. Describe the criticality (i.e., importance) of this project to the operation: If the refrigerated sampler fails, samples have to be taken manually every two hours and flow proportioned. This sample is not representative of the time period from 12:30 am until 7:00 am because the plant is unmanned during that time and no samples are taken. The manual samples are taken during the highest loading on the facility and could result in an effluent limit violation. How is efficiency improved with this equipment: Manual sampling could induce errors that would make the composite sample more or less concentrated that could result in a violation. An operator's time that would be spent doing other testing or inspecting the facility is now collecting and measuring samples manually. What is the impact (i.e., scope-of-use) for this equipment: Two of the three refrigerated samplers at the facility sample the in and out going flows that are required to be tested for the facilities Discharge Monitoring Report. ALTERNATIVES CONSIDERED Keep repairing old samplers until they fail. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: The refrigerated samplers have been repaired several times by replacing worn out parts but if the computer control components fail the repair costs will be much higher. The samplers we are using have been in service since 2000 and we have been replacing worn out parts. We need to start replacing them before the circuit boards fail. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED None FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 189 CIP Project Fund Wastewater Fund PROJECT NUMBER WW53 DEPARTMENT WRF PROJECT NAME Positive Displacement Lobe Pumps FY18 $50,000 FY19 Unscheduled DESCRIPTION OF PROJECT The positive displacement lobe pumps will replace the older wasting pumps that cannot provide the necessary wasting rates. Describe the criticality (i.e., importance) of this project to the operation: Being able to remove the required amount of microorganisms (WAS) from the Bio-Trains is a key factor in maintaining the facility's effluent quality. If the sludge in the wasting hoppers in final clarifiers one thru three cannot be remove at a rate fast enough to keep the sludge from going anaerobic then secondary phosphorus release will occur. Which infrastructure assets are maintained by this equipment: The wasting system from Final Clarifiers numbers one, two, and three would be serviced by these pumps. How is efficiency improved with this equipment: Positive displacement lobe pumps have a wider range of pumping speeds then the current pumps in service on this system. Maintenance costs less and they are also easier to maintain then the older pumps. What is the impact (i.e., scope-of-use) for this equipment: Pump WAS to the RST's at a rate that would maintain the proper F/M ratio and prevent secondary phosphorus. ALTERNATIVES CONSIDERED Do nothing. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: A decrease in facility effluent quality and an increase in pump maintenance and cost. Controlling mixed liquor inventory is critical to producing high quality effluent. If solids in the mixed liquor cannot be removed fast enough, total suspended solids will increase in the effluent which will also increase the total phosphorus to the river. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No new operating costs. Replacement of the lobe pump may actually increase efficiency. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 190 CIP Project Fund Wastewater Fund PROJECT NUMBER WW54 DEPARTMENT Wastewater Operations PROJECT NAME Replace #1783 - 1995 Ford Dump Truck FY18 FY19 Unscheduled DESCRIPTION OF PROJECT This project will replace a 1995 Ford Dump Truck that has 25,396 miles on it. Which infrastructure assets are maintained by this equipment: This dump truck would be used to haul material for the water, storm and sanitary sewer departments. And can be loaned to the street department for their operations. How is efficiency improved with this equipment: Efficiency is improved due to a more reliable dump truck that can cut down on the amount of trips we make by having multiple truck on site. ALTERNATIVES CONSIDERED Continue to use older vehicle which is becoming unreliable and costly to maintain. ADVANTAGES OF APPROVAL Will be a more fuel efficient and lower emissions vehicle. The new vehicle will improve safety of the crews, there would be lower repair costs and it would help maintain current operations levels. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Using an older piece of equipment that becomes more unreliable. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 $95,000 FY21 FY22 191 CIP Project Fund Wastewater Fund PROJECT NUMBER WW58 DEPARTMENT WRF PROJECT NAME Chip Seal and Topcoat WRF Asphalt FY18 FY19 $47,370 Unscheduled DESCRIPTION OF PROJECT Chip Seal and topcoat WRF Asphalt to keep it from deteriorating. Describe the criticality (i.e., importance) of this project to the operation: Without chip sealing and topcoat the asphalt will deteriorate sooner requiring replacement. Which infrastructure assets are maintained by this equipment: The 4.894 acres of asphalt at the WRF facility needs to be protected to extend its useful life. Chip seal 0.402 acres and topcoat 4.492 acres. What is the impact (i.e., scope-of-use) for this equipment: Protect the existing asphalt to extend its useful life. ALTERNATIVES CONSIDERED Do nothing. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Deferring the chip seal and topcoat will allow the asphalt to deteriorate sooner requiring its replacement sooner at a much higher cost to the City. Chip seal and topcoat will protect the existing City infrastructure. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED None FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 192 CIP Project Fund Wastewater Fund PROJECT NUMBER WW65 DEPARTMENT Wastewater Operations PROJECT NAME Digital Universal Camera - DUC FY18 $70,000 FY19 Unscheduled DESCRIPTION OF PROJECT Digital Universal Camera Describe the criticality (i.e., importance) of this project to the operation: This camera is critical to accessing the condition of the sewer main along with the Pipeline Assessment program we use. Our goal is to inspect the entire collection system once every 5 years. Which infrastructure assets are maintained by this equipment: The Digital Universal Camera (DUC) is a semi-autonomous, high resolution digital CCTV side scanning camera designed for rapid and detailed condition assessment of our wastewater system. How is efficiency improved with this equipment: This camera allows us to TV the main non-stop will allows us to increase the amount of pipe we TV in a day up to 5 to 10 times more than the traditional stop and go method that we now use. ALTERNATIVES CONSIDERED Continue to use the stop and go method (SAG) and take longer to TV the mains. We have a goal to TV the entire system every 5 years, this is getting harder to do with the increasing growth of our collection system. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: As we gain more miles of main every year we will have to adjust our goal of every main being televised once every five years to six or seven with the current stop and go technology we use. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Placing electronic equipment in raw sewage is hard to predict costs I believe there will be little or no more costs than our present camera. FUNDING SOURCES 100% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 193 CIP Project Fund Wastewater Fund PROJECT NUMBER WW66 DEPARTMENT WRF PROJECT NAME Odor Control For Old Pretreatment Building FY18 $40,000 FY19 Unscheduled DESCRIPTION OF PROJECT Odor Control For Old Pretreatment Building Describe the criticality (i.e., importance) of this project to the operation: Old Pretreatment Building odor (raw sewage) is vented out the roof of the building next to Springhill Road which generates odor complaints. The open channel containing the raw sewage emits corrosive gases into the building. What is the impact (i.e., scope-of-use) for this equipment: Protect equipment in the building and reduced odor complaints. ALTERNATIVES CONSIDERED Do nothing and run the risk of more odor complaints. Lack of enclosed and heated storage in the facility requires equipment to be parked in the old pretreatment building. Equipment stored there is exposed to the corrosive atmosphere. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Continuation of odor complaints and the corrosion of unprotected metal in the Old Pretreatment Building. Foul air from the sewer system coming into the old pretreatment building needs to be collected and treated. This treatment will eliminate the odor complaints and corrosive atmosphere. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No additional operating costs if another inline fan is not needed. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 194 CIP Project Fund Wastewater Fund PROJECT NUMBER WW69 DEPARTMENT WRF PROJECT NAME WRF Facility R&R FY18 $50,000 FY19 $50,000 Unscheduled DESCRIPTION OF PROJECT WRF Facility R&R Describe the criticality (i.e., importance) of this project to the operation: Repair and replacement of equipment is an ongoing job at the Bozeman WRF. These funds would be used to repair or replace equipment that fails unexpectedly in an emergency situation. Which infrastructure assets are maintained by this equipment: Any unscheduled repair or replacement of equipment within the facility that would keep the facility running properly. How is efficiency improved with this equipment: An unforeseen mechanical failure needs to be remedied quickly to protect the quality of facility effluent discharged into the East Gallatin. What is the impact (i.e., scope-of-use) for this equipment: To repair or replace any equipment that fails and could compromise facility performance. ALTERNATIVES CONSIDERED Not having this fund would defer other needed maintenance. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Without these funds available repair or replacement of failed equipment would depend on budgeted funds that may be allocated already. Most processes run 24/7 and have backup systems but when the first system fails there is no backup system and repairs need to be made immediately. Not all repairs or equipment failures can be predicted and budgeted as a capital improvement project. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED None FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 $50,000 FY21 $50,000 FY22 $50,000 195 CIP Project Fund Wastewater Fund PROJECT NUMBER WW70 DEPARTMENT WRF PROJECT NAME WRF Facility Engineering & Optimization FY18 $50,000 FY19 $50,000 Unscheduled DESCRIPTION OF PROJECT WRF Facility Engineering & Optimization Describe the criticality (i.e., importance) of this project to the operation: This will allow engineering to be completed on needed projects and to study plant optimization options before spending money on equipment that might not be needed or the proper type. Which infrastructure assets are maintained by this equipment: The entire facility How is efficiency improved with this equipment: Additionally, this will allow studies to be conducted to make sure the proposed plant optimizations will actually improve the effluent quality at a reasonable expense. What is the impact (i.e., scope-of-use) for this equipment: This will allow engineering to be completed on needed projects and to study plant optimization options before spending money on equipment that might not be needed or the proper type. ALTERNATIVES CONSIDERED Order replacement or upgrades to equipment that may not be sized correctly or made of the proper materials. Proceed with optimization projects without knowing if the project will actually improve plant performance. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Not having this will impede engineering needed for emergency projects that will come up unexpectedly. It will allow for engineering studies of operational problems to find the most efficient way to correct the problem. The advantage of having funds available to do engineering studies before any project is started will make sure that the right equipment is purchased and that it will perform properly. Optimization studies will predict actual cost/benefit over time to make sure the city is spending its money efficiently. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Currently unknown FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 $50,000 FY21 $50,000 FY22 $50,000 196 CIP Project Fund Wastewater Fund PROJECT NUMBER WW71 DEPARTMENT WRF PROJECT NAME WRF Facility Master Plan Update FY18 $250,000 FY19 Unscheduled DESCRIPTION OF PROJECT Facility Master Plan Update Describe the criticality (i.e., importance) of this project to the operation: The Master Plan Update will compare past predictions of the loadings on the City's Water Reclamation Facility with current loadings. How is efficiency improved with this equipment: New projections will be made using these data trends to determine the best course of action and sequencing of projects to meet the needs of the facility. What is the impact (i.e., scope-of-use) for this equipment: The entire facility will be effected by this plan because it will plan for facility expansion, side stream treatment and odor control among other things. ALTERNATIVES CONSIDERED Not being proactive in predicting the best way to accommodate future loading at the Bozeman WRF will not fulfill the city’s needs to meet future discharge limits. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: If the update plan is not conducted future needs of the facility may not be scheduled in an logical manner or even recognized. Financial expenditures and bond obligations could be incurred without sound justification. Bozeman’s rapid population growth dictates a review of the WRF’s treatment processes to make sure they will meet requirements now and in the future. Establishing a clear incremental improvement process will prevent mistakes and eliminate inefficient spending of funds. New permit and water quality regulations require an update of the master plan to ensure compliance over the next 15 years. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No additional costs FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 197 CIP Project Fund Wastewater Fund PROJECT NUMBER WW76 DEPARTMENT WRF PROJECT NAME Third Pretreatment Screen FY18 FY19 $300,000 Unscheduled DESCRIPTION OF PROJECT Purchase a third pretreatment screen and the engineering to properly install it. Describe the criticality (i.e., importance) of this project to the operation: The two installed pretreatment screens are running 24/7 so there is no redundancy to the system. How is capacity affected by this project: Adding a third screen will increase the capacity of pretreatment to handle increased flows without bypassing the screens. What regulations or standards are attained with this project: Preventing the clogging of pipes and pumps will preserve the effluent quality of the facility. Which infrastructure assets are maintained by this equipment: All equipment downstream of the screens will be better protected. How is efficiency improved with this equipment: Pipes and pumps that are not plugged run more efficiently and require less energy to run. What is the impact (i.e., scope-of-use) for this equipment: To protect the facility infrastructure. ALTERNATIVES CONSIDERED Do nothing and run the risk of having to bypass the existing screens because they cannot handle the load coming into the plant. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Do nothing and run the risk of having to bypass the existing screens because they cannot handle the load coming into the plant. Protecting downstream infrastructure by not having to bypass the screens. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Additional cost of electricity for the motors on the screen. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 198 CIP Project Fund Wastewater Fund PROJECT NUMBER WW78 DEPARTMENT WRF PROJECT NAME Server Replacement at WRF (WRFCTRLBAK) FY18 FY19 Unscheduled DESCRIPTION OF PROJECT Replace the WRF server WRFCTRLBAK ALTERNATIVES CONSIDERED ADVANTAGES OF APPROVAL ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 $10,000 199 CIP Project Fund Wastewater Fund PROJECT NUMBER WW79 DEPARTMENT WRF PROJECT NAME WRF Improvements for Energy Sustainability FY18 FY19 Unscheduled $4,000,000 DESCRIPTION OF PROJECT Energy Recovery (Methane Cogeneration) Project Design and Construction Describe the criticality (i.e., importance) of this project to the operation: To generate electricity for excess methane gas, reduce the carbon footprint of the facility and to add captured exhaust heat to the facility's heat loop. How is connectivity affected by this project: This project supports the sustainability and green goals of the city. What regulations or standards are attained with this project: The carbon foot print of the Water Reclamation Facility will be reduced. How is efficiency improved with this equipment: To generate electricity for excess methane gas and reduce the carbon footprint of the facility. What is the impact (i.e., scope-of-use) for this equipment: To generate electricity for excess methane gas, reduce the carbon footprint of the facility and to add captured exhaust heat to the facility's heat loop. How is this project leveraged with other stakeholders/projects/funds: The initial study for the project could identify other stakeholders such as Northwestern Energy. Are there other affected projects: The facility could reduce its carbon footprint by using methane as an onsite fuel to generate electricity. This would support the sustainability goals of the city. ALTERNATIVES CONSIDERED Continue to flare our excess digester methane. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: To continue to flare excess methane and not benefit from the generated electricity, reduced carbon footprint or additional captured heat. Current plant excess methane gas will be captured and utilized to reduce plant operating costs. It supports the City's Municipal Climate Action Plan goals. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Once construction is funded, this project will reduce energy costs of the facility. FUNDING SOURCES Wastewater Fund, other grants or community partners. New Replacement Equipment Project FY20 FY21 FY22 200 CIP Project Fund Wastewater Fund PROJECT NUMBER WW80 DEPARTMENT WRF PROJECT NAME Lagoon Valve Replacement in Lift #3, Clean Out Replacement on Sludge Line to Lagoon; Pump, valves FY18 $50,000 FY19 Unscheduled DESCRIPTION OF PROJECT Replace valves that cannot be opened or closed because of struvite deposits (replace 4 valves, blind flange 6 others). Replace cleanouts in the sludge lagoon line so their orientation allows a complete cleaning of the sludge line. Put in pump valves and piping so that sludge from the little lagoon can be pumped back through the pipe going out to the small lagoon. Describe the criticality (i.e., importance) of this project to the operation: If the screw press fails or if a digester needs to be emptied quickly Digester #3 has only a limited amount of storage so the sludge will need to be stored in the small lagoon. The system serving the small lagoon needs to be fully functional. Which infrastructure assets are maintained by this equipment: The small lagoon, the sludge line to the lagoon, Digester #3 and the screw press. How is efficiency improved with this equipment: The small lagoon can be filled and mixed properly. The sludge line to the lagoon can be cleaned in less time. Sludge in the small lagoon can be pumped back to Digester #3 and the screw press for dewatering without having to be trucked back. What is the impact (i.e., scope-of-use) for this equipment: This CIP supports the small lagoon sludge storage and the piping that gets the sludge to and from the lagoon. ALTERNATIVES CONSIDERED Do nothing and not be able to control flow to the small lagoon or even mix it. Sludge line to the small lagoon will not be cleaned properly. Sludge pumped to the small lagoon will have to be trucked back to Digester #3. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Not being able to control flow to the small lagoon or even mix it. Sludge line to the small lagoon will not be cleaned properly. Sludge pumped to the small lagoon will have to be trucked back to Digester #3. The small lagoon can be used to store sludge when needed. The sludge line to the lagoon can be cleaned in less time. Sludge in the small lagoon can be pumped back to Digester #3 and the screw press for dewatering without having to be trucked back. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No additional costs unless positive displacement is used to pump sludge back to Digester #3. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 201 CIP Project Fund Wastewater Fund PROJECT NUMBER WW81 DEPARTMENT WRF PROJECT NAME Membrane Roof Replacement on Old Digester Building (Dig 1 & 2) FY18 $60,000 FY19 Unscheduled DESCRIPTION OF PROJECT Repair or replacement of membrane roof covering on old digester building. Describe the criticality (i.e., importance) of this project to the operation: The extent of damage to the roof is not known. Just outside the door to the roof you step on the roof membrane and it is like walking on a thin water bed. An inspection and a repair or replacement to the roof membrane needs to be conducted in the near future prevent damage to the buildings roof. Which infrastructure assets are maintained by this equipment: The old digester building roof and infrastructure below. What is the impact (i.e., scope-of-use) for this equipment: Protect the old digester building roof and equipment in the room below. ALTERNATIVES CONSIDERED Do nothing and see if more ceiling leaks occur. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Possible more damage to the old digester building roof. There has been water under the roof membrane for several years (since 2004) and the extent of damage to the roof is unknown. Repair or replacement of the roof membrane would stop the leaks that pour water into the room below during rain events. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No additional costs. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 202 CIP Project Fund Wastewater Fund PROJECT NUMBER WW83 DEPARTMENT WRF PROJECT NAME UFAT Gravity Thickener Drive and Arms Replacement FY18 FY19 Unscheduled DESCRIPTION OF PROJECT Replacement of the gravity thickener deteriorating mechanism. Describe the criticality (i.e., importance) of this project to the operation: The gravity Thickener thickens elutriated fermented sludge before it is sent to the digester thus increasing detention time in the digesters. Which infrastructure assets are maintained by this equipment: The Gravity Thickener is second stage of the UFAT system that generates Volatile Fatty Acids that are an energy source for the Phosphorus Accumulating Organisms. These POA's are what remove the phosphorus from the wastewater. How is efficiency improved with this equipment: The gravity Thickener thickens elutriated fermented sludge before it is sent to the digester thus increasing detention time in the digesters. What is the impact (i.e., scope-of-use) for this equipment: To thicken sludge before is pumped to the digester which increases the digester efficiency. ALTERNATIVES CONSIDERED None ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: The failure of the gravity thickener and UFAT system. Installation planning and purchase of the drive and arms will allow a scheduled shutdown rather than a quick fix when the drive fails. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED No additional costs. FUNDING SOURCES Not known at this time. New Replacement Equipment Project FY20 FY21 FY22 $400,000 203 CIP Project Fund Wastewater Fund PROJECT NUMBER WW84 DEPARTMENT WRF PROJECT NAME Server Replacement at WRF (WRFCTRLPRI) FY18 FY19 Unscheduled DESCRIPTION OF PROJECT Replace the WRF server WRFCTRLPRI ALTERNATIVES CONSIDERED ADVANTAGES OF APPROVAL ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 $10,000 204 CIP Project Fund Wastewater Fund PROJECT NUMBER WW85 DEPARTMENT WRF PROJECT NAME WRF Process Upgrades to Improve Nutrient Recovery FY18 FY19 Unscheduled $10,000,000 DESCRIPTION OF PROJECT The study and construction of nutrient recovery processes to capture nitrogen and phosphorus from anaerobically digested sludge. Describe the criticality (i.e., importance) of this project to the operation: Recovery of the limiting element phosphorus, in the form of struvite, is critical to the production of food. The present market value of recovered phosphorus (struvite) is approximately $200 to $300 dollars a ton but its value will increase as the easily minable phosphorus rock deposits are depleted. How is capacity affected by this project: Nutrient recovery will reduce the nutrient load on the facility from the screw press supernatant that has to be returned to the head of the facility for treatment therefore increasing its capacity. How is connectivity affected by this project: This project supports the sustainability and green goals of the city. What regulations or standards are attained with this project: Nutrient recovery will reduce the nutrient load on the facility from the screw press supernatant that has to be returned to the head of the facility for treatment. Reducing the load will increase the facility efficiency so that the effluent quality will be maintained. How is efficiency improved with this equipment: Nutrient recovery will reduce the nutrient load on the facility from the screw press supernatant that has to be returned to the head of the facility for treatment therefore increasing its capacity. What is the impact (i.e., scope-of-use) for this equipment: The recovery and reuse of nutrients from the waste stream would complete the phosphorus nutrient cycle and support the sustainability goals of the city. The use of this nutrient recovered fertilizer would reduce the possibility of groundwater contamination. How is this project leveraged with other stakeholders/projects/funds: The initial study for the project could identify other stakeholders. ALTERNATIVES CONSIDERED Do nothing and loose a commodity that is a bi-product of anaerobic digestion ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Not proceeding with nutrient recovery falls short of the sustainability goals of the City. The production of magnesium ammonium phosphate to be sold as a slow release fertilizer will recycle limited nutrients back into the ecosystem. This process will reduce the nitrogen and phosphorus in our side stream returning to the head of the plant which will in turn reduce the loading on the process. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED Maintenance and operating costs that will be off set by income from the sale of the slow release fertilizer. FUNDING SOURCES 100% Wastewater Funds New Replacement Equipment Project FY20 FY21 FY22 205 CIP Project Fund Wastewater Fund PROJECT NUMBER WW86 DEPARTMENT Wastewater Operations PROJECT NAME Wheeled Excavator FY18 FY19 Unscheduled $151,000 DESCRIPTION OF PROJECT This would be a trac hoe excavator with wheels instead tracks. Describe the criticality (i.e., importance) of this project to the operation: It is a critical piece of machinery in our department. Which infrastructure assets are maintained by this equipment: Water, sewer, and stormwater How is efficiency improved with this equipment: Because it can move more dirt quicker. How is this project leveraged with other stakeholders/projects/funds: Can be split with water. ALTERNATIVES CONSIDERED Continue to use smaller equipment. ADVANTAGES OF APPROVAL What are the implications of deferring the purchase of this equipment: Continue using smaller equipment that task longer to do the work due to it's size. Increased productivity with larger excavator. ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED N/A FUNDING SOURCES 50% Water Fund, 50% Wastewater Fund New Replacement Equipment Project FY20 FY21 FY22 206