HomeMy WebLinkAbout12-05-16 CC Mtg - A2. Arterial and Collector District CIP
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adopt the Arterial and Collector District Capital Improvement Plan
(CIP) for Fiscal Years 2018-2022.
AGENDA ITEM TYPE: Action
MEETING DATE: December 5, 2016
RECOMMENDATION: Adopt the Arterial and Collector District Capital Improvement
Plan (CIP) for Fiscal Years 2018-2022.
SUGGESTED MOTION: I move to adopt the Arterial and Collector District Capital
Improvement Plan (CIP) for Fiscal Years 2018-2022.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th.
The Public Works department, City Manager, and other city staff met during October -
November to develop the attached Capital Plan for the capital needs of the Arterial and Collector
District (A&CD).
Items of Note:
1. Because of the role Street Impact Fees play in the expansion of our Arterial & Collector
streets, the A&CD capital plan is tied to projects on the Street Impact Fee CIP. Most
projects receive funding from both sources.
166
2. The District will be providing the “local share” of some projects in advance of
development. These projects are noted with an “*”. The city intends to create a payback
district to recover the “local share” once an adjacent project is developed. This payback
will be deposited to the Arterial & Collector Fund. At the end of this 5-year plan,
payback eligible improvements are estimated to total over $7.3 million.
o We have recorded the amount of “local share” payback improvements are funded
each year on the Financial Summary, below the Projected Year-End Cash.
o We anticipate that some of these payback amounts will come back to the Arterial &
Collector Fund as projects develop; but, for purposes of this plan we have not relied
on receiving any of that money to fund projects. This is a conservative approach to a
difficult-to-estimate cash flow.
3. Similar to the Street Impact Fee schedule, this CIP is also impacted by the development
waiver policy for certain projects that are within the first 3 years of the Capital
Improvements Plan and have all the necessary right-of-way and funding plans.
o We continue to require the 5-year plan to end with a positive year-end cash balance in
the last year of the plan.
o However, there is now added pressure to include projects within the first three years,
sometimes leading to a large negative balance. Given the fact that lead-times
(design/right of way) and construction timeframes on these projects usually span 24
months, we feel comfortable developing a CIP that could be in a negative position by
approximately “one-year’s-worth” of revenues at any given point before year five.
4. The first year of assessment was FY2016. The District’s revenues projections are based
on the amounts that were discussed when we created the district; a 3-year phase-in to an
annual total assessment of $2 Million. A 90% increase to the assessment in FY18 is
critical to this plan. Beyond FY18, we estimate a small amount of growth based on
annexation activity.
167
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission does not
wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY18.
Report compiled on: November 28, 2016
Attached: Arterial and Collector District CIP
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
Arterial & Collector Assessments
168
Arterial & Collector District Fund Capital Improvement Plan Financial Summary Current YearFY17 FY18 FY19 FY20 FY21 FY22UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,005,600$ 1,070,600$ (783,245)$ (2,151,556)$ (487,004)$ 895,839$ Plus: Assessment Revenues Dedicated to CIP 1,095,000$ 2,080,500$ 2,122,110$ 2,164,552$ 2,207,843$ 2,252,000$ ‐$ Less: Scheduled CIP Project Costs (1,030,000)$ (3,934,345)$ (3,490,421)$ (500,000)$ (825,000)$ (750,000)$ (13,464,146)$ Projected Year‐End Cash Dedicated to CIP 1,070,600$ (783,245)$ (2,151,556)$ (487,004)$ 895,839$ 2,397,840$ (13,464,146)$ Beginning Balance of Payback Improvements:‐$ ‐$ (2,544,666.00)$ (2,677,666)$ (3,997,666)$ (7,013,941)$ (7,347,941)$ SIF036 ‐ Payback District‐$ (1,278,000)$ ‐$ (1,320,000)$ (2,516,275)$ (334,000)$ SIF046 ‐ Gallatin County SID(600,000)$ SIF073 ‐ Payback District(404,000)$ SIF076 ‐ Payback District(500,000)$ SIF080 ‐ Gallatin County SID(333,333)$ SIF080 ‐ Payback District(333,333)$ SIF105 ‐ Payback District(1,240,000)$ SIF109 ‐ Gallatin County Payback/SID(133,000)$ SIF113 ‐ Payback District(2,000,000)$ SIF117 ‐ Payback District(225,000)$ Ending Balance of Payback Improvements:‐$ (2,544,666)$ (2,677,666)$ (3,997,666)$ (7,013,941)$ (7,347,941)$ (8,991,941)$ Assumptions Made for Revenue Estimates: Current YearFY17 FY18 FY19 FY20 FY21 FY22Estimated Annual Assessment Revenues 565,000$ 1,095,000$ 2,080,500$ 2,122,110$ 2,164,552$ 2,207,843$ Estimated Annual Increase 95.0% 90% 2% 2% 2% 2%Total Estimated Revenues 1,095,000$ 2,080,500$ 2,122,110$ 2,164,552$ 2,207,843$ 2,252,000$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%Total Estimated Revenues Dedicated to CIP 1,095,000$ 2,080,500$ 2,122,110$ 2,164,552$ 2,207,843$ 2,252,000$ ProjectedProjectedCURRENT14,000,0009,000,0004,000,000FY18 FY19 FY20 FY21 FY22 UnscheduledArterial & Collector Projects 169
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEUnscheduledFY21FY18FY19FY20FY22Arterial & Collector StreetsSIF036STREET IFCOTTONWOOD (BABCOCK TO DURSTON) ‐ CONSTRUCTION*$1,278,000SIF039STREET IFFERGUSON & DURSTON (INTERSECTION) ‐ CONSTRUCTION$451,244SIF046STREET IFOAK (NEW HOLLAND TO FERGUSON) ‐ CONSTRUCTION*$600,000SIF057STREET IFOAK (FLANDERS MILL TO RYUNSON WAY) ‐ CONSTRUCTION$500,000SIF058STREET IFOAK & N 27TH (INTERSECTION) ‐ CONSTRUCTION$122,146SIF061STREET IFOAK & FERGUSON (INTERSECTION) ‐ SIGNAL CONSTRUCTION$269,066SIF062STREET IFDURSTON (FOWLER TO FERGUSON) ‐ CONSTRUCTION$757,421SIF063STREET IFFOWLER & BABCOCK (INTERSECTION) ‐ CONSTRUCTION$400,000SIF073STREET IFFOWLER & DURSTON (INTERSECTION) ‐ SIGNAL CONSTRUCTION*$404,000SIF074STREET IFOAK & DAVIS (INTERSECTION) ‐ ROUNDABOUT CONSTRUCTION$352,302SIF076STREET IFFOWLER CONNECTION (HUFFINE TO OAK) ‐ DESIGN (INCLUDES 3 INTERSECTIONS)*$500,000SIF080STREET IFFERGUSON (BAXTER TO OAK) ‐ CONSTRUCTION*$666,666SIF086STREET IFBAXTER & COTTONWOOD (INTERSECTION) ‐ CONSTRUCTION$500,000SIF098STREET IFOAK & COTTONWOOD (INTERSECTION) ‐ ROUNDABOUT CONSTRUCTION$548,000SIF104STREET IFCOTTONWOOD & BABCOCK (INTERSECTION) ‐ SIGNAL CONSTRUCTION$287,067SIF105STREET IFCOTTONWOOD (DURSTON TO OAK) ‐ CONSTRUCTION*$1,240,000SIF108STREET IFS 3RD AND GRAF ‐ SIGNAL CONSTRUCTION$200,000170
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEUnscheduledFY21FY18FY19FY20FY22SIF109STREET IFOAK (ROUSE THROUGH CANNERY DISTRICT) ‐ CONSTRUCTION*$133,000SIF110STREET IFMANLEY & GRIFFIN (INTERSECTION) ‐ CONSTRUCTION$400,000SIF111STREET IFHIGHLAND (MAIN TO KAGY) ‐ CONSTRUCTION & DESIGN*$5,000,000SIF112STREET IFHIGHLAND & MAIN INTERSECTION IMPROVEMENTS$30,000SIF113STREET IFGRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION*$2,000,000SIF114STREET IFFOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION*$3,750,000SIF115STREET IFCOLLEGE (11TH TO 19TH) ‐ CONSTRUCTION$550,000SIF116STREET IFBRIDGER DR & STORY MILL RD (INTERSECTION) ‐ CONSTRUCTION$200,000SIF117STREET IFSTORY MILL (GRIFFIN TO BRIDGER) ‐ CONSTRUCTION*$225,000SIF118STREET IFBABCOCK (11TH AVE TO 19TH AVE) ‐ CONSTRUCTION*$750,000SIF121STREET IFBAXTER & DAVIS (INTERSECTION) ‐ CONSTRUCTION$500,000SIF125STREET IFCOLLEGE (11TH TO 19TH) ‐ DESIGN$100,000SIF134STREET IFOAK (COTTONWOOD TO FLANDERS MILL) ‐ CONSTRUCTION$250,000Summary for Arterial & Collector Streets (30 items)Totals by year:$825,000 $750,000$3,934,345$13,464,146FY21FY22FY18UnscheduledFY20$500,000$3,490,421FY19171
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF036
DEPARTMENT
STREET IF
PROJECT NAME
Cottonwood (Babcock to Durston) - Construction*
FY18
$1,278,000
FY19 Unscheduled
DESCRIPTION OF PROJECT
The project consists of finishinThe project consists of finishing Cottonwood Road from Babcock to Durston to a five lane urban
arterial standard.
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place. Cottonwood is also failing in this section because of heavy traffic and subbase
degradation. Failure to complete this section will likely result in large maintenance expenses.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Cottonwood serves as an important element in Bozeman's west side street system
and serves as a primary north-south corridor on the west side of the City.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Cottonwood corridor street improvements, intersection improvements at Cottonwood and
Babcock and Cottonwood and Durston.
ALTERNATIVES CONSIDERED
SID, payback district, incremental construction by adjacent developement.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Added maintenance costs
are expected if this project is not completed within the next 2-3 years.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,278,000) and the Arterial & Collector District ($1,278,000). A development payback district
may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $1,278,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
172
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF039
DEPARTMENT
STREET IF
PROJECT NAME
Ferguson & Durston (Intersection) - Construction
FY18
$451,244
FY19 Unscheduled
DESCRIPTION OF PROJECT
Installation of a roundabout at the intersection of Ferguson and Durston
Describe the criticality (i.e., importance) of this project to the operation: The level of service at this intersction has degraded to
unacceptable levels. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended.
How is capacity affected by this project: This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase it's capacity.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
Are there other affected projects: The Ferguson Road Improvement project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,804,976) and the Arterial & Collector District ($451,244).
New
Replacement
Equipment
Project
FY20 FY21 FY22
173
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF046
DEPARTMENT
STREET IF
PROJECT NAME
Oak (New Holland to Ferguson) - Construction*
FY18
$600,000
FY19 Unscheduled
DESCRIPTION OF PROJECT
Complete To 5-Lane Arterial Standard
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
Are there other affected projects: Oak Street Cottonwood to Ferguson, Intersection improvements at Oak and Ferguson and
Oak and Fowler.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project will be funded by Street Impact Fees ($1,400,000) and Arterial & Collector District financing for local improvements attributed to
Gallatin County - creation of Special Improvement District ($600,000). The Special Improvement District will re-pay the Arterial & Collector
District Fund.
New
Replacement
Equipment
Project
FY20 FY21 FY22
174
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF057
DEPARTMENT
STREET IF
PROJECT NAME
Oak (Flanders Mill to Ryunson Way) - Construction
FY18 FY19 Unscheduled
$500,000
DESCRIPTION OF PROJECT
<div>This project is the completion of the street segment of Oak St, from Flanders Mill to Ryunson Way, to a five-lane
urban principal arterial standard. Describe the criticality (i.e., importance) of this project to the operation: Future
developments in this area may not be allowed to proceed until these improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. How is capacity affected by this project: This
project increases capacity directly by constructing new segments of arterial roadway and by adding additional lanes, dedicated bike
lanes and sidewalks. How is connectivity affected by this project: Completes an important east-west link between Ferguson and
Cottonwood. What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is
attained. How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to
leverage other stakeholders. Are there other affected projects: Intersection improvements at Oak and Cottonwood, Oak and
Flanders Mill, Oak and Ferguson, Oak Street New Holland to Ferguson.</div>
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,000,000) the Arterial & Collector District ($500.000) and local participation. The Flander's Mill
development is expected to be a partner in the construction of the segments adjacent to their development.
New
Replacement
Equipment
Project
FY20 FY21 FY22
175
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF058
DEPARTMENT
STREET IF
PROJECT NAME
Oak & N 27th (Intersection) - Construction
FY18 FY19 Unscheduled
$122,146
DESCRIPTION OF PROJECT
Installation of a signal at the intersection of Oak and N 27th.
Describe the criticality (i.e., importance) of this project to the operation: The level of service at this intersction has degraded to
unacceptable levels. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended.
How is capacity affected by this project: This intersection is currently 2-way stop controlled. Replacing it with a signal will greatly
increase it's capacity.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
Are there other affected projects: Oak Street corridor projects and North 27th Street improvements project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($488,584) and the Arterial & Collector District ($122,146).
New
Replacement
Equipment
Project
FY20 FY21 FY22
176
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF061
DEPARTMENT
STREET IF
PROJECT NAME
Oak & Ferguson (Intersection) - Signal Construction
FY18
$269,066
FY19 Unscheduled
DESCRIPTION OF PROJECT
<div>Installation of a signal at the intersection of Oak and Ferguson.
&
nbsp; &n
bsp; &nb
sp; Describe the criticality (i.e., importance) of this
project to the operation: Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. How is capacity affected by this project: Development which is currently occurring as well as projects which already
have approval make it clear that this intersection will no longer meet the city's LOS standard. Installation of a signal at this
intersection will increase it's capacity and assist in improving the LOS at nearby intersections. How is connectivity affected
by this project: Facilitates the extension of Oak Street to the west of Ferguson Road where it currently does not exist, and will
eventually make the connection with Cottonwood Road. What regulations or standards are attained with this project: The Level
of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan are attained. Are there other
affected projects: Oak Street projects and Ferguson Road projects are affected.</div>
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,076,265) and Arterial & Collector District ($269,066).
New
Replacement
Equipment
Project
FY20 FY21 FY22
177
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF062
DEPARTMENT
STREET IF
PROJECT NAME
Durston (Fowler to Ferguson) - Construction
FY18 FY19
$757,421
Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Rd, from Cottonwood to Fowler, to a three-lane urban minor arterial standard
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project directly increase capacity by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements at Durston & Ferguson, Durston & Fowler, Durston & Flanders Mill.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($757,421) and the Arterial & Collector District ($757,421). A payback district may be created to
reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY20 FY21 FY22
178
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF063
DEPARTMENT
STREET IF
PROJECT NAME
Fowler & Babcock (Intersection) - Construction
FY18 FY19 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Install a traffic signal, roundabout, or other adequiate traffic control device at the intersection of Fowler and Babcock.
Describe the criticality (i.e., importance) of this project to the operation: Peak hour level of service for northbound traffic is
degrading due to lack of north-south connectivity in the network.
How is capacity affected by this project: This intersection is currently 1-way stop controlled. Replacing it with a signal or
roundabout will greatly increase it's capacity.
How is connectivity affected by this project: East-west connectivity already exists at this location. North-south connectivity is still
lacking.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Fowler corridor improvements
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,600,000) and the Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
179
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF073
DEPARTMENT
STREET IF
PROJECT NAME
Fowler & Durston (Intersection) - Signal Construction*
FY18 FY19 Unscheduled
$404,000
DESCRIPTION OF PROJECT
<div>Install a signal at the intersection of Fowler and Durston Describe the criticality (i.e., importance) of this project to
the operation: Current LOS is acceptable. How is capacity affected by this project: This intersection is currently 1-way stop
controlled. Replacing it with a signal or roundabout will greatly increase it's capacity. How is connectivity affected by this project:
East-west connectivity already exists at this location. North-south connectivity is still lacking. What regulations or standards are
attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan are
attained. Are there other affected projects: Fowler corridor street improvements.</div>
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improves an imporant connecting element in the network.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,616,000) and the Arterial & Collector District ($404,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $404,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
180
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF074
DEPARTMENT
STREET IF
PROJECT NAME
Oak & Davis (Intersection) - Roundabout Construction
FY18
$352,302
FY19 Unscheduled
DESCRIPTION OF PROJECT
<div>Install a roundabout at the intersection of Oak and Davis. Describe the criticality (i.e., importance) of this project to
the operation: Peak hour level of service for northbound traffic is degrading due to lack of north-south connectivity in the
network. Geometric deficiencies will be addressed. How is capacity affected by this project: This intersection is currently 1-way
stop controlled. Replacing it with a roundabout will greatly increase it's capacity. How is connectivity affected by this
project: East-west connectivity already exists at this location. North-south connectivity is still lacking. What regulations or
standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan are attained. Are there other affected projects: Oak Street corridor improvements and Fowler corridor
improvements.</div>
ALTERNATIVES CONSIDERED
Accept the current geometry and level of service.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,409,206) and the Arterial & Collector District ($352,302).
New
Replacement
Equipment
Project
FY20 FY21 FY22
181
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF076
DEPARTMENT
STREET IF
PROJECT NAME
Fowler Connection (Huffine to Oak) - Design (Includes 3 Intersections)*
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard, including three intersections.
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: This project directly increase capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks and making improvements to the intersections.
How is connectivity affected by this project: This project completes an important north-south connection on the west side of
town.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements at Fowler and Durston and Fowler and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will complete an important north-south connection, expand the capacity of our street network and improve safety for drivers and
pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and the Arterial & Collector District ($500,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $500,000).
New
Replacement
Equipment
Project
FY20 FY21
$500,000
FY22
182
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF080
DEPARTMENT
STREET IF
PROJECT NAME
Ferguson (Baxter to Oak) - Construction*
FY18
$666,666
FY19 Unscheduled
DESCRIPTION OF PROJECT
Complete Ferguson from Baxter to Oak to a two lane urban collector standard with bike lanes, curb and gutter, boulevards,
parking and sidewalks.
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project increases capacity directly by constructing a new roadway which includes
dedicated bike lanes and sidewalks.
How is connectivity affected by this project: Completes an important north-south link between Baxter and Oak.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection of Ferguson and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($333,333), Gallatin County ($333,333), and a developer contribution ($333,333). This budget
assumes that A&C funds will be used to cover the both the County portion and the developer contribution, both to be paid back with SID or
payback agreement.
New
Replacement
Equipment
Project
FY20 FY21 FY22
183
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF086
DEPARTMENT
STREET IF
PROJECT NAME
Baxter & Cottonwood (Intersection) - Construction
FY18 FY19 Unscheduled
$500,000
DESCRIPTION OF PROJECT
<div>Improve the intersection at Baxter and Cottonwood. Describe the criticality (i.e., importance) of this project to the
operation: Current LOS is acceptable. How is capacity affected by this project: This intersection is currently 1-way stop
controlled. Replacing it with a signal or roundabout will greatly increase it's capacity. How is connectivity affected by this project:
East-west connectivity already exists at this location. North-south connectivity is still lacking. What regulations or standards are
attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan are
attained. Are there other affected projects: Cottonwood corridor improvements and Baxter corridor improvements.</div>
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
184
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF098
DEPARTMENT
STREET IF
PROJECT NAME
Oak & Cottonwood (Intersection) - Roundabout Construction
FY18 FY19 Unscheduled
$548,000
DESCRIPTION OF PROJECT
<div>Installation of a roundabout at the intersection of Oak and Cottonwood. Describe the criticality (i.e., importance) of
this project to the operation: Functionality of the network at large is dependent on this element functioning as intended.
The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network
that are in place. How is capacity affected by this project: Capacity will be greatly incereased on the network as a whole as this
intersection is currently 3-legged, rural and stop controlled on Cottonwood (Harper Puckett). How is connectivity
affected by this project: This improvement will complete an improtant north-south connection on Cottonwood. What regulations
or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan are attained. Are there other affected projects: Cottonwood Road Improvements, Oak Street
Improvements.</div>
ALTERNATIVES CONSIDERED
Not installing the intersection improvement at the same time as the construction of the intersecting streets. Secure additional financing by
creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,192,000) and the Arterial & Collector District ($548,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
185
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF104
DEPARTMENT
STREET IF
PROJECT NAME
Cottonwood & Babcock (Intersection) - Signal Construction
FY18
$287,067
FY19 Unscheduled
DESCRIPTION OF PROJECT
<div>Installation of a traffic signal at the intersection of Cottonwood and Babcock. Describe the criticality (i.e.,
importance) of this project to the operation: Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. How is capacity affected by this project: This intersection is currently 2-way stop controlled. Replacing
it with a signal will greatly increase it's capacity. How is connectivity affected by this project: Connectivity exists at this location, it
is capacity which is being increased. What regulations or standards are attained with this project: The Level of Service (LOS)
Standard (BMC) and conformance with the Transportation Master Plan are attained. Are there other affected projects:
Cottonwood corridor improvement projects.</div>
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,148,269) and the Arterial & Collector District ($287,067).
New
Replacement
Equipment
Project
FY20 FY21 FY22
186
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF105
DEPARTMENT
STREET IF
PROJECT NAME
Cottonwood (Durston to Oak) - Construction*
FY18 FY19 Unscheduled
$1,240,000
DESCRIPTION OF PROJECT
Complete the construction of Cottonwood Road from Durston Road to Oak Street to a five-lane urban arterial standard.
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Cottonwood Rd serves as an important element in Bozeman's west side street
system and serves as a primary north-south corridor on the west side of the city.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Cottonwood corridor street improvemnts, intersection improvements at Cottonwood and
Durston and Cottonwood and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,240,000) and the Arterial & Collector District ($1,240,000). A dev105elopment payback
district may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $1,240,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
187
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF108
DEPARTMENT
STREET IF
PROJECT NAME
S 3rd and Graf - Signal Construction
FY18 FY19
$200,000
Unscheduled
DESCRIPTION OF PROJECT
<div>Signal construction at S 3rd and Graf Describe the criticality (i.e., importance) of this project to the operation: Future
developments which impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of
the network at large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity
is putting unnecessary demand on those elements of the street network that are in place. How is capacity affected by this project:
This is currently a stop controlled intersection. Installation of a roundabout will directly increase capacity. How is connectivity
affected by this project: Connectivity already exists at this location, it is capacity which is being expanded. What regulations or
standards are attained with this project: The Level of Service (LOS) Standard (BMC). Are there other affected
projects: Graf Street corridor improvements.</div>
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
188
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF109
DEPARTMENT
STREET IF
PROJECT NAME
Oak (Rouse through Cannery District) - Construction*
FY18 FY19
$133,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of improving Oak from Rouse through the Cannery District to include curb, gutter, sidewalks, and a turning
lane to provide a complete arterial street standard. The Cannery District will be responsible for the cost of curb, gutter, and
sidewalk along their property frontage as well as the turn lane to access two drive accesses that allow a left turn movement from
Oak Street into the Cannery District.
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project directly increase capacity by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.
What safety or risk measures are mitigated with this project: Left turn traffic safety will be improved upon installation of left turn
lanes. Pedestrian safety will be improved.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to leverage other
stakeholders. Cash-in-lieu of infrastructure is anticipated to be contributed from the Cannery District developer to cover the
cost of the left turn lanes needed for their drive accesses as well as the cost of curb, gutter, and sidewalk adjacent to their
property.
Are there other affected projects: Oak Street Corridor improvements
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. There will be substantial
pedestrian traffic between the Fairgrounds and the Cannery District. Additionally, the traffic impact study for the Cannery District indicated the
need for left turn lanes for their drive accesses. As the City's transportation master plan identifies the need to upgrade the Oak Street
Corridor to an arterial standard, this is an opportunity to partner with the Cannery District developer to complete a portion of the Oak Street
improvements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($133,000), the Arterial & Collector District ($133,000), and Cannery District Developer share
($133,000). A development payback district or SID may be created to reimburse the Arterial & Collector District for the County’s (project
related) costs.
New
Replacement
Equipment
Project
FY20 FY21 FY22
189
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF110
DEPARTMENT
STREET IF
PROJECT NAME
Manley & Griffin (Intersection) - Construction
FY18 FY19
$400,000
Unscheduled
DESCRIPTION OF PROJECT
Intersection control at Manley & Griffin
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: This intersection is currently 1-way stop controlled. Replacing it with a signal will greatly
increase it's capacity.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Griffin corridor improvements
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($1,600,000) and Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
190
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF111
DEPARTMENT
STREET IF
PROJECT NAME
Highland (Main to Kagy) - Construction & Design*
FY18 FY19 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Upgrade Highland, from Main to Kagy.
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project directly increase capacity by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.What
regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements at Highland and Kagy, Highland and Ellis and Highland and Main
Street
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs
FUNDING SOURCES
This project is funded by Street Impact Fees ($5,000,000) and the Arterial & Collector District ($5,000,000). A payback district may be
created to reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY20 FY21 FY22
191
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF112
DEPARTMENT
STREET IF
PROJECT NAME
Highland & Main Intersection Improvements
FY18
$30,000
FY19 Unscheduled
DESCRIPTION OF PROJECT
Improve intersection control at Highland & Main
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place
How is capacity affected by this project: Adding additional phases and improving geometry will increase capacity for deficient
movements at this intersection.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Highland Boulevard corridor improvements
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($150,000), Arterial & Collector District ($30,000)
New
Replacement
Equipment
Project
FY20 FY21 FY22
192
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF113
DEPARTMENT
STREET IF
PROJECT NAME
Griffin (7th to Rouse) - Construction*
FY18 FY19
$2,000,000
Unscheduled
DESCRIPTION OF PROJECT
Construct W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: Designed improvements will improve LOS at the key intersections and will increase
capacity in the corridor as a whole.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing).
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,000,000) and the Arterial & Collector District ($2,000,000). A development payback district or
SID may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $2,000,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
193
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF114
DEPARTMENT
STREET IF
PROJECT NAME
Fowler Connection (Huffine to Oak) - Construction*
FY18 FY19 Unscheduled
$3,750,000
DESCRIPTION OF PROJECT
Complete the section of Fowler from Huffine to Oak
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: Allows for extenion of Fowler Avenue, which will directly increase capacity.
How is connectivity affected by this project: Extends an important north-south corridor on the west side of the city.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements on Fowler at Huffine, Babcock, Durston and Oak.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Completes an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,750,000) and the Arterial & Collector District ($3,750,000). A payback district may be created
to reimburse the Arterial & Collector District for any local improvements.
New
Replacement
Equipment
Project
FY20 FY21 FY22
194
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF115
DEPARTMENT
STREET IF
PROJECT NAME
College (11th to 19th) - Construction
FY18 FY19 Unscheduled
$550,000
DESCRIPTION OF PROJECT
Complete College, from 19th to 11th, to a principal arterial standard.
Describe the criticality (i.e., importance) of this project to the operation: Functionality of the network at large is dependent on
this element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on
those elements of the street network that are in place.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks and by improving intersection LOS
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: Urban funds could be used on this section of College
Are there other affected projects: Intersections of College/11th and College/8th
ALTERNATIVES CONSIDERED
Accept the current configuration
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
50% Street Impact Fees & 50% Arterial & Collector District.
New
Replacement
Equipment
Project
FY20 FY21 FY22
195
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF116
DEPARTMENT
STREET IF
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection) - Construction
FY18 FY19 Unscheduled
$200,000
DESCRIPTION OF PROJECT
Intersection control at Bridger and Story Mill. Describe the criticality (i.e., importance) of this project to the operation: Future
developments which impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of
the network at large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity
is putting unnecessary demand on those elements of the street network that are in place. How is capacity affected by this project:
Adding additional phases and improving geometry will increase capacity for deficient movements at this intersection. How is
connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded. What
regulations or standards are attained with this project: Conformance with the Transportation Master Plan are attained.
Are there other affected projects: Story Mill, Griffin to Bridger Drive</div>
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY20 FY21 FY22
196
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF117
DEPARTMENT
STREET IF
PROJECT NAME
Story Mill (Griffin to Bridger) - Construction*
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
Improve Story Mill from Griffin to Bridger
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvments to Story Mill and Bridger Drive
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($225,000) and the Arterial & Collector District ($225,000). An Sid or payback district may be
created to recover the local share.
New
Replacement
Equipment
Project
FY20 FY21
$225,000
FY22
197
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF118
DEPARTMENT
STREET IF
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Construction*
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
Improve Babcock from 11th to 19th)
Describe the criticality (i.e., importance) of this project to the operation: Future developments which impact this intersection area
may not be allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being
expanded.What regulations or standards are attained with this project: Conformance with the Transportation Master Plan are
attained.
How is this project leveraged with other stakeholders/projects/funds: A Payback District or SID may be created to leverage other
stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($750,000) and the Arterial & Collector District ($750,000). An SID or payback district may be
created to pay for some local share improvements.
New
Replacement
Equipment
Project
FY20 FY21 FY22
$750,000
198
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF121
DEPARTMENT
STREET IF
PROJECT NAME
Baxter & Davis (Intersection) - Construction
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
Install a roundabout at Baxter & Davis
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase it's capacity.
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity that is affected.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan and Level of
Service Standard is attained.
Are there other affected projects: Baxter Lane Corridor Improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY20
$500,000
FY21 FY22
199
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF125
DEPARTMENT
STREET IF
PROJECT NAME
College (11th to 19th) - Design
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
Design College, from 19th to 11th, to a principal arterial standard. Evaluate upgrading 11th to an Arterial Collector (from a local
street). Including adding bike lanes, pedestrian crossings and removing parking.
Describe the criticality (i.e., importance) of this project to the operation: Functionality of the network at large is dependent on
this element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on
those elements of the street network that are in place.
How is capacity affected by this project: This project increases capacity directly by adding additional lanes, dedicated bike lanes and
sidewalks and by improving intersection LOS
How is connectivity affected by this project: Connectivity already exists at this location, it is capacity which is being expanded.
What regulations or standards are attained with this project: The Level of Service (LOS) Standard (BMC) and conformance with
the Transportation Master Plan are attained.
How is this project leveraged with other stakeholders/projects/funds: Urban funds could be used on this section of College
Are there other affected projects: Intersections of College/11th and College/8th.
ALTERNATIVES CONSIDERED
Accept the current configuration
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
50% Street Impact Fees & 50% Arterial & Collector District.
New
Replacement
Equipment
Project
FY20 FY21
$100,000
FY22
200
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF134
DEPARTMENT
STREET IF
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Construction
FY18 FY19 Unscheduled
$250,000
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal
arterial standard.
Describe the criticality (i.e., importance) of this project to the operation: Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place.
How is capacity affected by this project: This project increases capacity directly by constructing new segments of arterial roadway
and by adding additional lanes, dedicated bike lanes and sidewalks.
How is connectivity affected by this project: Completes an important east-west link between Ferguson and Cottonwood.
What regulations or standards are attained with this project: Conformance with the Transportation Master Plan is attained.
How is this project leveraged with other stakeholders/projects/funds: A payback District or SID may be created to leverage other
stakeholders.
Are there other affected projects: Intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson,
Oak Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,300,000), Arterial & Collector District of $250,000 for the local share ajacent to the City park,
and an additional $250,000 from School District #7.
New
Replacement
Equipment
Project
FY20 FY21 FY22
201