HomeMy WebLinkAboutDraft - Wastewater IF CIPWastewater Impact Fee Capital Improvement PlanFinancial Summary Current YearFY17 FY18 FY19 FY20 FY21 FY22UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,479,000$ (135,912)$ (354,762)$ 127,446$ 673,763$ 1,287,397$ ‐$ Plus: Impact Fee Revenues Dedicated to CIP 1,103,500$ 1,221,150$ 1,282,208$ 1,346,318$ 1,413,634$ 1,484,315$ ‐$ Plus: Loans for WWIF11, WWIF202,185,000$ 5,290,000$ Plus: Developer Contribution From WWIF26 631,837$ Less: Scheduled CIP Project Costs (3,350,249)$ (1,440,000)$ (2,985,000)$ (6,090,000)$ (800,000)$ (800,000)$ (6,018,035)$ Projected Year‐End Cash Dedicated to CIP (135,912)$ (354,762)$ 127,446$ 673,763$ 1,287,397$ 1,971,713$ Assumptions Made for Revenue Estimates: Current YearFY17 FY18 FY19 FY20 FY21 FY22Estimated Annual Wastewater Impact Fee Revenues 1,103,500$ 1,163,000$ 1,221,150$ 1,282,208$ 1,346,318$ 1,413,634$ Estimated Annual Increase 0.0% 5% 5% 5% 5% 5%Total Estimated Revenues 1,103,500$ 1,221,150$ 1,282,208$ 1,346,318$ 1,413,634$ 1,484,315$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Wastewater Capacity Expansion CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%Total Estimated Revenues Dedicated to CIP 1,103,500$ 1,221,150$ 1,282,208$ 1,346,318$ 1,413,634$ 1,484,315$ ProjectedProjectedCURRENT7,000,0006,000,0005,000,0004,000,0003,000,0002,000,0001,000,0000Wastewater Impact Fee Projects
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEUnscheduledFY21FY18FY19FY20FY22Impact Fees WastewaterWWIF11WW IMPACT FEFRONT STREET INTERCEPTOR$2,185,000WWIF20WW IMPACT FEN FRONTAGE RD INTERCEPTOR$5,290,000WWIF22WW IMPACT FEESDAVIS‐FOWLER INTERCEPTOR (DURSTON RD TO W OAK ST)$778,035WWIF24WW IMPACT FEDAVIS LANE (LIFT STATION)$1,200,000WWIF27WW IMPACT FEESSOUTH UNIVERSITY DISTRICT/CATTAIL CREEK BASIN ‐ S 15TH AVE TO WILLOW WAY TO W LINCOLN ST$795,000WWIF31WW IMPACT FEESDAVIS LN LIFT STATION, INTERCEPTOR, AND FORCE MAIN$645,000WWIF32WW IMPACT FEHIDDEN VALLEY (LIFT STATION)$3,240,000WWIF33WW IMPACT FEDAVIS LN LIFT STATION DEBIT SERVICE$800,000$800,000$800,000$800,000$800,000Summary for Impact Fees Wastewater (8 items)Totals by year:$800,000 $800,000$1,440,000$6,018,035FY21FY22FY18UnscheduledFY20$6,090,000$2,985,000FY19
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF11
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Front Street Interceptor
FY18 FY19
$2,185,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of construction of ~8,500 LF 18", 21", 24" sewer pipe from manhole E0304 to C0524.
Describe the criticality (i.e., importance) of this project to the operation: Without this wastewater interceptor development in
the vicinity of Bozeman Deaconess Health Services as well as the remainder of The Village Downtown property will not be able
to occur.
How is capacity affected by this project: The downstream portion of the existing sewer is already at capacity. Additional capacity is
needed to serve future development in the vicinity of Bozeman Deaconess Hospital and lands to the south.
How is connectivity affected by this project: This interceptor provides sewer for Upper Bozeman Creek Basin.
What safety or risk measures are mitigated with this project: There are no risk or safety issues mitigated by this project.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Master Plan.
How is this project leveraged with other stakeholders/projects/funds: It is estimated that 70% of this project costs will be due to
capacity expansion and will be eligible for Wastewater Impact Fees. The remaining 30% of the project costs will need to be
provided by a "local share" contribution or other source.
Are there other affected projects: This project will provide sewer capacity in the area of Bozeman Deaconess Health Services.
ALTERNATIVES CONSIDERED
Limit development to only that capacity of the existing sewer.
ADVANTAGES OF APPROVAL
This project will significantly increase the service area and capacity of the trunk sewer.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $1,529,864 30% Wastewater Impact Fees for Local Share = $655,656, recovered via payback district(s).
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF20
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
N Frontage Rd Interceptor
FY18 FY19 Unscheduled
DESCRIPTION OF PROJECT
This project will replace or parallel 11,500' of the North Frontage Road interceptor between Springhill Rd and Bridger Dr.
Describe the criticality (i.e., importance) of this project to the operation: Portions of the interceptor are at or very near capacity
and unless improvements are made it will be at or over capacity when the tributary obligated areas are developed.
How is capacity affected by this project: Directly increases collection capacity in the southeast and east parts of the city.
Development in the southeast part of town within the Community Plan Boundary as well as the east part of town will be
tributary to this North Frontage Road Interceptor.
How is connectivity affected by this project: This project will provide capacity to new development within the existing city limits.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Master Plan.
How is this project leveraged with other stakeholders/projects/funds: It is estimated that 70% of this project costs will be due to
capacity expansion and will be eligible for Wastewater Impact Fees. The remaining 30% of the project costs will need to be
provided by a "local share" contribution or other source.
Are there other affected projects: There are potentially a great number of private development projects which will not be able to
proceed due to the lack of wastewater collection capacity.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for future growth tributary to
this main.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district(s)
New
Replacement
Equipment
Project
FY20
$5,290,000
FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF22
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Davis-Fowler Interceptor (Durston Rd to W Oak St)
FY18 FY19 Unscheduled
$778,035
DESCRIPTION OF PROJECT
This project will replace or parallel 2700' of the Davis-Fowler Interceptor between Durston and Oak.
Describe the criticality (i.e., importance) of this project to the operation: The interceptor between Durston Rd and W Oak will
eventually exceed capacity as the Baxter Creek drainage basin develops.
How is capacity affected by this project: In order to convey the ultimate build-out flow, the interceptor will need to be increased
from an 18-inch diameter to a 24-inch diameter pipe.
How is connectivity affected by this project: This interceptor provides sewer for Baxter Creek and Cattail Creek Basins.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating the long-term
future growth in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF24
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Davis Lane (Lift Station)
FY18 FY19 Unscheduled
$1,200,000
DESCRIPTION OF PROJECT
Complete the buildout of Davis Ln Lift Station
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating the long-term
future growth in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF27
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
South University District/Cattail Creek Basin - S 15th Ave to Willow Way to W Lincoln St
FY18
$795,000
FY19 Unscheduled
DESCRIPTION OF PROJECT
This project consists of extending the sewer main to service the South University District area with a 10-inch sewer pipe.
Describe the criticality (i.e., importance) of this project to the operation: As described in the 2015 Wastewater Facility Plan, there
is little potential to accommodate additional flow from this area through existing pipe network, therefore, if capacity is not added
no further development in this area can be supported. Since this area is especially suited to housing for University students and
since the University continues to grow in population the community needs are best accommodated if collection capacity is
increased.
How is capacity affected by this project: This interceptor will support an average day flow value of 1,456 gallons per acre.
How is connectivity affected by this project: This sewer pipe will serve the area generally between Lincoln and University Way,
and South 19th and the vacant land to the west of Spectators.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Master Plan.
How is this project leveraged with other stakeholders/projects/funds: It is estimated that 50% of this project costs will be due to
capacity expansion and will be eligible for Wastewater Impact Fees. The remaining 50% of the project costs will need to be
provided by a "local share" contribution or other source.
Are there other affected projects: There are potentially a great number of private development projects which will not be able to
proceed due to the lack of wastewater collection capacity.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating the long-term
future growth in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF31
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Davis Ln Lift Station, Interceptor, and Force Main
FY18
$645,000
FY19 Unscheduled
DESCRIPTION OF PROJECT
This project will provide initial funding for oversizing the Davis Ln Lift Station not included in the funding package for the Billings
Clinic. This will include oversizing the wet well capacity and sanitary sewer freeway crossing to accommodate peak hour flows up
to 6.2 MGD.
Describe the criticality (i.e., importance) of this project to the operation: This will be the City's portion of the initial Davis Ln Lift
Station upsizing construction that is not included in the Billings Clinic funding.
How is capacity affected by this project: Sanitary sewer capacity will be increased for development in the western portion of the
community.
How is connectivity affected by this project: This lift station serves development north of the Cattail Lake Lift Station.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Master Plan.
How is this project leveraged with other stakeholders/projects/funds: The Billings Clinic will finance the lift station, and the City
will reimburse the Billings Clinic for the City's portion over 5 years. The Billings Clinic will not be reimbursed for their portion of
the lift station capacity, which is estimates as 8% of the capacity of the initial lift station construction.
Are there other affected projects: Yes, we may want to consider building the Norton East Ranch Outfall Diversion with this
project. Construction of the Diversion will take pressure off the existing Baxter Meadows Lift Station and limit the need to
upgrade that lift station farther into the future. Additionally, the Norton East Ranch Diversion would reduce early operational
challenges in the Davis Lane Lift Station due to odors associated with minimal flows.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
This will pay off the City's portion of the Davis Ln Lift Station
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Billings Clinic is constructing the Lift Station and will provide a payback district for the City's portion of the financing.
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF32
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Hidden Valley (Lift Station)
FY18 FY19 Unscheduled
$3,240,000
DESCRIPTION OF PROJECT
Design and Construct Hidden Valley Lift Station and Force Main
Describe the criticality (i.e., importance) of this project to the operation: Service area expansion of the City's sanitary sewer
collection system.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Collection Facilities Plan
Are there other affected projects: The Davis Lane Lift Station must be upgraded to accommodate flows from the Hidden Valley
Lift Station when the Hidden Valley Lift Station is constructed.
ALTERNATIVES CONSIDERED
Limit development on the northwestern edge of of the City due to no sanitary sewer availability.
ADVANTAGES OF APPROVAL
Increased service area of the City's sanitary sewer system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operating costs will be paid from the City's sewer enterprise fund.
FUNDING SOURCES
Payback district or other local share contribution from development at the time of construction.
New
Replacement
Equipment
Project
FY20 FY21 FY22
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF33
DEPARTMENT
WW IMPACT FEES
PROJECT NAME
Davis Ln Lift Station Debit Service
FY18 FY19
$800,000
Unscheduled
$800,000
DESCRIPTION OF PROJECT
This project will provide a debit service payment for the City's portion of the Davis Ln Lift Station.
Describe the criticality (i.e., importance) of this project to the operation: If we do not fund this debit service, the City will be in
default of our loan.
How is capacity affected by this project: Sanitary sewer capacity will be increased for development in the western portion of the
community.
How is connectivity affected by this project: This lift station serves development north of the Cattail Lake Lift Station.
What regulations or standards are attained with this project: Conformance with the City's Wastewater Master Plan.
How is this project leveraged with other stakeholders/projects/funds: The Billings Clinic will finance the lift station, and the City
will reimburse the Billings Clinic for the City's portion over 5 years. The Billings Clinic will not be reimbursed for their portion of
the lift station capacity, which is estimates as 8% of the capacity of the initial lift station construction.
Are there other affected projects: Yes, we may want to consider building the Norton East Ranch Outfall Diversion with this
project. Construction of the Diversion will take pressure off the existing Baxter Meadows Lift Station and limit the need to
upgrade that lift station farther into the future. Additionally, the Norton East Ranch Diversion would reduce early operational
challenges in the Davis Lane Lift Station due to odors associated with minimal flows.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
This will pay off the City's portion of the Davis Ln Lift Station
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Billings Clinic is constructing the Lift Station and will provide a payback agreement for the City's portion of the financing, to be paid back with
interest over a 5-year period. Repayments are expected to being in the year following construction.
New
Replacement
Equipment
Project
FY20
$800,000
FY21
$800,000
FY22
$800,000