CONSTRUCTION ROUTE MAP
Construction traffic will use 191/Main Street as the primary route through the City to access the
project site. From Main Street drivers shall turn south on S. Wilson Ave to and then east on to E
Olive St. due to the availability of traffic signals at Main and Olive.
Delivery trucks will utilize the parking line on the south side of Olive along the project site frontage
to temporarily park and off load materials and equipment. These parking spots will be blocked for
the duration of the project. In addition, the parking spots on S Black along the project site
frontage will also be blocked for the duration of the project.
After making deliveries or pick-ups, vehicles will merge back on to E Olive St. and head east to S
Church Ave, turning north to head back to 191/Main Street.
Misc. Notes: The perimeter of the site will be barricaded from the public with a 6' tall temporary
chain link fence. Access will be through gates. Construction waste dumpsters will be staged on
E Olive St during in the blocked parking spots.
Project site, parking lanes closed for
construction use at frontage