WORK DIRECTIVE CHANGE
INSTRUCTIONS
A. GENERAL INFORMATION
This document was developed for use in situations involving changes in the Work which, if not
processed expeditiously, might delay the Project. These changes are often initiated in the field and
may affect the Contract Price or the Contract Time. This is not a Change Order, but only a directive
to proceed with Work that may be included in a subsequent Change Order.
For supplemental instructions and minor changes not involving a change in the Contract Price or
the Contract Time, a Field Order may be issued.
B. COMPLETING THE WORK DIRECTIVE CHANGE
Engineer initiates the form, including a description of the items involved and attachments.
Based on conversations between Engineer and Contractor, Engineer to indicate the following and
attach the same hereto:
METHOD OF DETERMINING CHANGE, IF ANY, IN CONTRACT PRICE: Indicate the method
to be used in determining the final cost of Work involved and the net effect on the Contract
Price. If the change involves an increase in the Contract Price and the estimated amount
is approached before the additional or changed work is completed, another Work Directive
Change must be issued to change the time or Contractor may stop the changed Work when
the estimated time is reached. If the Work Directive Change is not likely to change the
Contract Price, the space for estimated increase (decreased) should be marked "Not
Applicable".
METHOD OF DETERMINING CHANGE, IF ANY, IN CONTRACT TIME: Indicate the method
to be used in determining the change in Contract Time and the estimated increase or
decrease in Contract Time. If the change involves an increase in the Contract Time and the
estimated time is approached before additional or changed Work is completed, another
Work Directive Change must be issued to change the time or Contractor may stop the
changed Work when the estimated time is reached. If the Work Directive Change is not
likely to change the Contract Time, the space for estimated increase (decrease) should be
marked "Not Applicable".
Once Engineer has completed and signed this form, all copies should be sent to Owner for
authorization because Engineer alone does not have authority to authorize changes in Price or
Time. Once authorized by Owner, a copy should be sent by Engineer to Contractor.
Once the Work covered by this directive is completed for final cost and time determined, Contractor
should submit documentation for inclusion in a Change Order.
THIS IS A DIRECTIVE TO PROCEED WITH A CHANGE THAT MAY AFFECT THE CONTRACT PRICE
OR THE CONTRACT TIME. A CHANGE ORDER, IF ANY, SHOULD BE CONSIDERED PROMPTLY.
Rev. 6/04
WORK DIRECTIVE CHANGE
INSTRUCTIONS
A. GENERAL INFORMATION
This document was developed for use in situations involving changes in the Work which, if not
processed expeditiously, might delay the Project. These changes are often initiated in the field and
may affect the Contract Price or the Contract Time. This is not a Change Order, but only a directive
to proceed with Work that may be included in a subsequent Change Order.
For supplemental instructions and minor changes not involving a change in the Contract Price or
the Contract Time, a Field Order may be issued.
B. COMPLETING THE WORK DIRECTIVE CHANGE
Engineer initiates the form, including a description of the items involved and attachments.
Based on conversations between Engineer and Contractor, Engineer to indicate the following and
attach the same hereto:
METHOD OF DETERMINING CHANGE, IF ANY, IN CONTRACT PRICE: Indicate the method
to be used in determining the final cost of Work involved and the net effect on the Contract
Price. If the change involves an increase in the Contract Price and the estimated amount
is approached before the additional or changed work is completed, another Work Directive
Change must be issued to change the time or Contractor may stop the changed Work when
the estimated time is reached. If the Work Directive Change is not likely to change the
Contract Price, the space for estimated increase (decreased) should be marked "Not
Applicable".
METHOD OF DETERMINING CHANGE, IF ANY, IN CONTRACT TIME: Indicate the method
to be used in determining the change in Contract Time and the estimated increase or
decrease in Contract Time. If the change involves an increase in the Contract Time and the
estimated time is approached before additional or changed Work is completed, another
Work Directive Change must be issued to change the time or Contractor may stop the
changed Work when the estimated time is reached. If the Work Directive Change is not
likely to change the Contract Time, the space for estimated increase (decrease) should be
marked "Not Applicable".
Once Engineer has completed and signed this form, all copies should be sent to Owner for
authorization because Engineer alone does not have authority to authorize changes in Price or
Time. Once authorized by Owner, a copy should be sent by Engineer to Contractor.
Once the Work covered by this directive is completed for final cost and time determined, Contractor
should submit documentation for inclusion in a Change Order.
THIS IS A DIRECTIVE TO PROCEED WITH A CHANGE THAT MAY AFFECT THE CONTRACT PRICE
OR THE CONTRACT TIME. A CHANGE ORDER, IF ANY, SHOULD BE CONSIDERED PROMPTLY.