HomeMy WebLinkAbout16- Construction Agreement - Dick Anderson Construction - Bozeman Sports Park(9�%/i Document A133TM -2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price a3ta AGREEMENT made as of the day of in he year �� �� ADDITIONS AND DELETIONS: (In words, indicate day, month and year) The author of this document has added information needed for its BETWEEN the Owner: completion. The author may also (Name, legal status and address) have revised the text of the original AIA standard form. An Additions and The City of Bozeman Deletions Report that notes added 121 N. Rouse Ave. information as well as revisions to the standard form text is available PO Box 1230 from the author and should be Bozeman, MT 59771-1230 reviewed. A vertical line in the left margin of this document indicates ("Owner") where the author has added necessary information and where and the Construction Manager: the author has added to or deleted (Alame, legal status and address) from the original AIA text. Dick Anderson Construction, Inc. This document has important legal 4498 Jackrabbit Lane consequences. Consultation with an Bozeman, MT 59718 attorney is encouraged with respect to its completion or modification. ("Construction Manager") AIA Document A201 T1"-2007, General Conditions of the Contract for the following Project: for Construction, is adopted in this (Name and address or location) document by reference. Do not use with other general conditions unless Bozeman Sports Park this document is modified. 4600 Baxter Lane Bozeman, MT 59718 The Architect: (Name, legal status and address) DOWL, LLC 2090 Stadium Drive Bozeman, MT 59715 ("Architect") The Owner's Designated Representative: (Name, address and other it formation) Carolyn Poissant, MLA, AICP Manager of Trails, Open Space and Parks Design and Development PO Box 1230 Bozeman, MT 59771-1230 406-582-2908 Email Address: cpoissant@bozeman.net AIA Document A133TM —2009 (formerly A121 TMCMc — 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. / This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA19) The Construction Manager's Designated Representative: (Name, address and other information) Kirk Hogan Civil Division Manager Dick Anderson Construction, Inc. 4498 Jackrabbit Lane Bozeman, MT 59718 406-586-0889 406-388-4263 (fax) The Architect's Designated Representative: (Name, address and other in formation) Jach Lowe, PE Senior Civil Engineer DOWL, LLC 2090 Stadium Drive Bozeman, MT 59715 406-586-8834 406-865-9847(fax) The Owner and Construction Manager agree as follows. AIA Document A133TM —2009 (formerly A121 TMCMC — 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 2 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA19) TABLE OF ARTICLES 1 EXHIBIT A GENERAL PROVISIONS 2 EXHIBIT A CONSTRUCTION MANAGER'S RESPONSIBILITIES 3 EXHIBIT A OWNER'S RESPONSIBILITIES 4 EXHIBIT A COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES 5 EXHIBIT A COMPENSATION FOR CONSTRUCTION PHASE SERVICES 6 EXHIBIT A COST OF THE WORK FOR CONSTRUCTION PHASE 7 EXHIBIT A PAYMENTS FOR CONSTRUCTION PHASE SERVICES 8 EXHIBIT A INSURANCE AND BONDS 9 EXHIBIT A DISPUTE RESOLUTION 10 EXHIBIT A TERMINATION OR SUSPENSION 11 EXHIBIT A MISCELLANEOUS PROVISIONS 12 EXHIBIT A SCOPE OF THE AGREEMENT EXHIBIT A GUARANTEED MAXIMUM PRICE AMENDMENT ARTICLE 1 GENERAL PROVISIONS § 1.1 The Contract Documents The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda and Exhibits issued prior to the execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract and are as fully a part of the Contract as if attached to this Agreement or repeated herein. Upon the Owner's acceptance of the Construction Manager's Guaranteed Maximum Price proposal, the Contract Documents will also include the documents described in Section 2.2.3 and identified in the Guaranteed Maximum Price Amendment and revisions prepared by the Architect and furnished by the Owner as described in Section 2.2.8. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. If anything in the other Contract Documents, other than a Modification, is inconsistent with this Agreement, this Agreement shall govern. § 1.2 Relationship of the Parties The Construction Manager accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to cooperate with the Architect and exercise the Construction Manager's best skill and judgment in furthering the interests of the Owner; to furnish efficient construction administration, management services and supervision; to furnish at all times an adequate supply of qualified workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner's interests. The Owner agrees to furnish or approve, in a timely manner, information required by the Construction Manager and to make payments to the Construction Manager in accordance with the requirements of the Contract Documents. § 1.3 General Conditions All references in this document to AIA Document A201 - 2007, General Conditions for Construction shall mean the attached version of said document, as modified by Owner. For the Preconstruction Phase, AIA Document A201T111- 2007, General Conditions of the Contract for Construction, shall apply only as specifically provided in this Agreement. For the Construction Phase, the general conditions of the contract shall be as set forth in A201-2007, AIA Document A133M — 2009 (formerly A121 TMCMc — 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 3 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA19) which document is incorporated herein by reference. The term "Contractor" as used in A201-2007 shall mean the Construction Manager. ARTICLE 2 CONSTRUCTION MANAGER'S RESPONSIBILITIES The Construction Manager's Preconstruction Phase responsibilities are set forth in Sections 2.1 and 2.2. The Construction Manager's Construction Phase responsibilities are set forth in Section 2.3. The Owner and Construction Manager may agree, in consultation with the Architect, for the Construction Phase to commence prior to completion of the Preconstruction Phase, in which case, both phases will proceed concurrently. The Construction Manager shall identify a representative authorized to act on behalf of the Construction Manager with respect to the Project. § 2.1 Preconstruction Phase § 2.1.1 The Construction Manager shall provide a preliminary evaluation of the Owner's program, schedule and construction budget requirements, each in terms of the other. § 2.1.2 Consultation; Assistance The Construction Manager shall schedule and conduct meetings with the Architect and Owner to discuss such matters as procedures, progress, coordination, and scheduling of the Work. The Construction Manager shall advise the Owner and the Architect on proposed site use and improvements, selection of materials, and building systems and equipment. The Construction Manager shall also provide recommendations consistent with the Project requirements to the Owner and Architect on constructability; availability of materials and labor; advisability of accepting donated or discounted materials and/or services, time requirements for procurement, installation and construction; and factors related to construction cost including, but not limited to, costs of alternative designs or materials, preliminary budgets, life -cycle data, and possible cost reductions. § 2.1.2.1 Assistance with Design and Engineering of Phase I Site Plan The Construction Manager shall assist the Architect with the preparation of the Phase I site plan, including: .1 Efficient layout of site infrastructure and amenities .2 Cost-effective and durable specifications for materials and methods of construction .3 Opportunities for inclusion of donated materials and in-kind services that conform to the Master Site Plan § 2.1.2.2 Assistance with Construction Documents ("CDs") The Construction Manager will review plans, details, and specifications provided by the Architect at 70%, 90%, and 100% completion. The Construction Manager will advise the Owner and Architect with regard to revising the CDs as necessary or advisable to comply with Owner Requirements. § 2.1.3 Preliminary Project Schedule When Project requirements in Section 3. 1.1 have been sufficiently identified, the Construction Manager shall prepare and update periodically, as well as at Owner's request and promptly following any material change with respect thereto, a preliminary Project schedule for the Architect's review and the Owner's acceptance. The Construction Manager shall obtain the Architect's and Owner's approval for the portion of the preliminary Project schedule relating to the performance of the Architect's services. The preliminary Project schedule shall coordinate and integrate the Construction Manager's services, the Architect's services, other Owner consultants' services, and the Owner's responsibilities and identify items that could affect the Project's timely completion. The updated preliminary Project schedule shall include the following: submission of the Guaranteed Maximum Price proposal; components of the Work; times of commencement and completion required of each Subcontractor; and ordering and delivery of products, including those that must be ordered well in advance of construction. § 2.1.4 Phased Construction The Construction Manager shall provide recommendations with regard to accelerated or fast-track scheduling, procurement, or phased construction. The Construction Manager shall take into consideration cost reductions, cost information, constructability, provisions for temporary facilities and procurement and construction scheduling issues. § 2.1.5 Cost Estimates § 2.1.5.1 Preliminary Cost Estimates Based on the preliminary design and other design criteria prepared by the Architect, the Construction Manager shall prepare preliminary estimates of the Cost of the Work or the cost of AIA Document A133TM —2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA© Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 4 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA19) program requirements using area, volume or similar conceptual estimating techniques for the Architect's review and Owner's approval. If the Architect or Construction Manager suggests alternative materials and systems, the Construction Manager shall provide cost evaluations of those alternative materials and systems. § 2.1.5.2 As the Architect progresses with the preparation of any Schematic Design, Design Development and Construction Documents, the Construction Manager shall prepare and update, at appropriate intervals agreed to by the Owner, Construction Manager and Architect, estimates of the Cost of the Work of increasing detail and refinement and allowing for the further development of the design until such time as the Owner and Construction Manager agree on a Guaranteed Maximum Price for the Work. Such estimates shall be provided for the Architect's review and the Owner's approval. The Construction Manager shall inform the Owner and Architect when estimates of the Cost of the Work exceed the latest approved Project budget and make recommendations for corrective action. § 2.1.5.3 Final Cost Estimate The Construction Manager will prepare a final pre -construction, pre-bid cost estimate for each portion of the project to be constructed under the Phase I site plan, including any alternative bid items. § 2.1.6 Subcontractors and Suppliers The Construction Manager will: .1 Make recommendations to the Owner regarding division of work in order to facilitate competitive bidding and awarding of subcontracts. .2 Develop bidders' interest in the Project. .3 Prepare pre -qualification criteria and bid packages for material supplier and contractors. .4 Perform all advertising and receive subcontractor and supplier bids. .5 Conduct pre-bid conferences with subcontractors. .6 Review competitive sealed bids from subcontractors and make recommendations to the Owner. § 2.1.7 Donations of Materials and Services The Construction Manager will: .1 Develop bidders' interest in donating materials and/or services. .2 The Construction Manager will assist Owner to develop a protocol for the acceptance of donations of materials/and or services from subcontractors. The Owner will be responsible for final approval of the donation protocol. .3 The Construction Manager, in consultation with Owner, will determine whether any construction materials and/or services are suitable to be donated to the Project. The Construction Manager will, in consultation with the Owner, create a list of any materials and/or services appropriate for donation, along with the dates those materials and/or services will be needed during the Construction Phase. The Owner will have final approval authority for the inclusion of materials/and or services on the list of potential donations. .4 The Construction Manager will provide the list of potential donations to the Bozeman Sports Park Foundation for the solicitation of donations, a description of any supporting documentation the City deems necessary, and the deadline for the submission of a list of committed donors and supporting documentation. .5 The Construction Manager will notify the Owner of potential opportunities for donation of materials and services, and review all donations and supporting documentation to verify they meet project design and engineering specifications. For donations the Construction Manager deems acceptable, the City will determine the value of the donation based on the engineering pre-bid estimate for that item. The Owner will have final approval authority for the acceptance of donations. .6 Donations accepted by the Owner will be considered "provided by Owner" and will be deducted from the final cost estimate and bid. § 2,1.8 The Construction Manager shall prepare, for the Architect's review and the Owner's acceptance, a procurement schedule for items that must be ordered well in advance of construction. The Construction Manager shall expedite and coordinate the ordering and delivery of materials that must be ordered well in advance of construction. If the Owner agrees to procure any items prior to the establishment of the Guaranteed Maximum Price, the Owner shall procure the items on terms and conditions reasonably acceptable to the Construction Manager. Upon the establishment of the Guaranteed Maximum Price, the Owner shall assign all contracts for these items to the Construction Manager and the Construction Manager shall thereafter accept responsibility for them. AIA Document A133M — 2009 (formerly A121 TMCMc — 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 5 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) § 2.1.9 Extent of Responsibility The Construction Manager shall exercise reasonable care in preparing schedules and estimates. The Construction Manager, however, does not warrant or guarantee estimates except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall exercise reasonable care in its review of the Drawings and Specifications and shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require. § 2.1.9 Notices and Compliance with Laws The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, toles and regulations, and lawful orders of public authorities applicable to its performance under this Contract, and with equal employment opportunity programs, and other programs as may be required by governmental and quasi governmental authorities for inclusion in the Contract Documents. § 2.2 Guaranteed Maximum Price Proposal and Contract Time § 2.2.1 Upon receipt of subcontractor bids, the Construction Manager shall prepare a Guaranteed Maximum Price proposal for the Owner's review and acceptance. The Guaranteed Maximum Price in the proposal shall be the sum of the Construction Manager's estimate of the Cost of the Work,the Owner -authorized Allowances, and the Construction Manager's Fee. § 2.2.2 Reserved. § 2.2.3 The Construction Manager shall include with the Guaranteed Maximum Price proposal a written statement of its basis, which shall include the following: .1 A complete list of all Drawings and Specifications, including all Addenda thereto, and the Conditions of the Contract; .2 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the Guaranteed Maximum Price proposal to supplement the information provided by the Owner and contained in the Drawings and Specifications; .3 A statement of the proposed Guaranteed Maximum Price, including a statement of the estimated Cost of the Work organized by trade categories or systems, General Conditions Costs, Allowances, insurance, surety and bonding costs, governmental fees, and the Construction Manager's Fee; .4 The anticipated date of Substantial Completion upon which the proposed Guaranteed Maximum Price is based; .5 A date by which the Owner must accept the Guaranteed Maximum Price; and .6 A schedule of reasonably anticipated Allowances, a statement of the basis for each, and an estimate of the amount of Allowances by category. § 2.2.4 In preparing the Construction Manager's Guaranteed Maximum Price proposal, the Construction Manager shall recommend a contingency amount to Owner. Upon Owner's approval, the contingency shall be included in the Guaranteed Maximum Price and shall be controlled by the Construction Manager. The Construction Manager shall include a statement explaining the basis for the contingency amount. If approved by Owner, the contingency amount shall be available for use to cover the Construction Manager's costs, expenses, overhead and profit attributable to (a) cost due to general area -wide labor disputes; (b) increases in bid or purchase order agreements; (c) corrective work approved by the Owner; (d) labor disputes within manufacturing or transportation industries causing delays in receipt of materials or equipment not the fault of the Construction Manager, and (e) scope gaps. § 2.2.5 The Construction Manager shall meet with the Owner and Architect to review the Guaranteed Maximum Price proposal and the written statement of its bases. In the event that the Owner and Architect discover any inconsistencies or inaccuracies in the information presented, they shall promptly notify the Construction Manager, who shall make appropriate adjustments to the Guaranteed Maximum Price proposal, its basis, or both. § 2.2.6 If the Owner notifies the Construction Manager that the Owner has accepted the Guaranteed Maximum Price proposal in writing before the date specified in the Guaranteed Maximum Price proposal, the Guaranteed Maximum Price proposal shall be deemed effective without further acceptance from the Construction Manager. Following acceptance of a Guaranteed Maximum Price, the Owner and Construction Manager shall execute the Guaranteed Maximum Price Amendment amending this Agreement, a copy of which the Owner shall provide to the Architect. AIA Document A133TI-2009 (formerly A121 TMCMC — 2003). Copyright ©1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 6 Document, or any portion of it, may result in severe civil and criminal penalties, and will he prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA19) The Guaranteed Maximum Price Amendment shall set forth the agreed upon Guaranteed Maximum Price with the information and assumptions upon which it is based and shall include all information required in 2.2.3 above. § 2.2.7 The Construction Manager shall not incur any cost to be reimbursed as part of the Cost of the Work prior to the commencement of the Construction Phase, unless the Owner provides prior written authorization for such costs. § 2.2.8 The Owner shall authorize the Architect to provide the revisions to the Drawings and Specifications to incorporate the agreed upon assumptions and clarifications contained in the Guaranteed Maximum Price Amendment. The Owner shall promptly furnish those revised Drawings and Specifications to the Construction Manager as they are revised. The Construction Manager shall notify the Owner and Architect of any inconsistencies between the Guaranteed Maximum Price Amendment and the revised Drawings and Specifications. § 2.2.9 The Construction Manager shall include in the Guaranteed Maximum Price all sales, consumer, use and similar taxes for the Work provided by the Construction Manager that are legally enacted, whether or not yet effective, at the time the Guaranteed Maximum Price Amendment is executed. § 2.2.10 The Construction Manager shall obtain two written quotes or may advertise for bids for procurements over five thousand dollars ($5,000.00) up to eighty thousand dollars ($80,000.00). For procurements over eighty thousand dollars ($80,000.00) Construction Manager shall advertise for bids as required by §§ 7-5-4302, MCA. § 2.3 Construction Phase § 2.3.1 General § 2.3.1.1 For purposes of Section 8.1.2 of A201-2007, the date of commencement of the Work shall mean the date of commencement of the Construction Phase. § 2.3.1.2 The Construction Phase shall commence upon the Owner's acceptance of the Construction Manager's Guaranteed Maximum Price proposal or the Owner's issuance of a Notice to Proceed, whichever occurs earlier. § 2.3.2 Administration § 2.3.2.1 Those portions of the Work that the Construction Manager does not customarily perform with the Construction Manager's own personnel shall be performed under subcontracts or by other appropriate agreements with the Construction Manager. The Owner may designate specific persons and processes (including processes which comply with relevant procurement laws and policies) from whom, or entities from which, the Construction Manager shall obtain bids. The Construction Manager shall obtain bids from Subcontractors and from suppliers of materials or equipment fabricated especially for the Work and shall deliver such bids to the Architect. The Construction Manager will be responsible for analyzing then reviewing all bids with the Architect and the Owner, and reviewing the complete scope, after which time a recommendation will be made for approval by the Owner. The Owner shall then determine, with the advice of the Construction Manager and the Architect, which bids will be accepted. The Construction Manager shall not be required to contract with anyone to whom the Construction Manager has reasonable objection. The Construction Manager will be the registered builder on the Project, coordinate the Work, and be responsible for delivery of the Project on schedule and of the specified quality. The Construction Manager will sign and hold the contracts with the various Subcontractors and suppliers and be responsible to the Owner for the resultant Work. § 2.3.2.2 If the Guaranteed Maximum Price has been established and when a specific bidder (1) is recommended to the Owner by the Construction Manager, (2) is qualified to perform that portion of the Work, and (3) has submitted a bid that conforms to the requirements of the Contract Documents without reservations or exceptions, but the Owner requires that another bid be accepted, then unless a specific bidder that may be considered a "related party" according to Section 6. 10, the Construction Manager may require that a Change Order be issued to adjust the Contract Time and the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Construction Manager and the amount and time requirement of the subcontract or other agreement actually signed with the person or entity designated by the Owner. § 2.3.2.3 Subcontracts or other agreements shall conform to the applicable payment provisions of this Agreement, and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. If the Subcontract is awarded on a cost plus fee basis, the Construction Manager shall provide in the Subcontract for the Owner to receive AIA Document All 33T" —2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 7 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05117/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) the same audit rights with regard to the Subcontractor as the Owner receives with regard to the Construction Manager in Section 6.11 below. § 2.3.2.4 If the Construction Manager recommends a specific bidder that may be considered a "related party" according to Section 6. 10, then the Construction Manager shall promptly notify the Owner in writing of such relationship and notify the Owner of the specific nature of the contemplated transaction, according to Section 6.10.2. § 2.3.2.5 The Construction Manager shall schedule and conduct meetings to discuss such matters as procedures, progress, coordination, scheduling, and status of the Work. The Construction Manager shall prepare and promptly within seven days distribute minutes to the Owner and Architect for the review and written approval of the Owner and Architect. § 2.3.2.6 Upon the execution of the Guaranteed Maximum Price Amendment, the Construction Manager shall prepare and submit to the Owner and Architect a construction schedule for the Work and submittal schedule in accordance with Section 3.10 of A201-2007. § 2.3.2.7 The Construction Manager shall record the progress of the Project. On a monthly basis, or otherwise as reasonably required by or agreed to by the Owner, the Construction Manager shall submit written progress reports to the Owner and Architect, showing percentages of completion and other information required by the Owner. The Construction Manager shall also keep, and make available to the Owner and Architect, a daily log containing a record for each day of weather, portions of the Work in progress, number of workers on site, identification of equipment on site, problems that might affect progress of the Work, accidents, injuries, and other information required by the Owner. § 2.3.2.8 The Construction Manager shall develop a system of cost control for the Work, including regular monitoring of actual costs for activities in progress and estimates for uncompleted tasks and proposed changes. The Construction Manager shall identify variances between actual and estimated costs and report the variances to the Owner and Architect and shall provide this information in its monthly reports to the Owner and Architect, in accordance with Section 2.3.2.7 above. § 2.3.2.9 The Construction Manager shall ensure all contracts with Subcontractors contain all provisions required by law, including, but not limited to, compliance with provisions addressing prevailing wages (§ 18-2-403, -422, MCA); Montana residential preferences (§ 18-2-403, MCA); nondiscrimination (§49-3-207, MCA); and, maintenance of records requirements (§ 18-2-406 and -422, MCA). The nondiscrimination provision in Section 16.1 of A201-2007 shall be used. § 2.3.2.10 Utilizing the construction schedules provided by the various Subcontractors, the Construction Manager shall update the Project construction schedule incorporating the activities of the Subcontractors on the Project, including activity sequences and durations, allocation of labor and materials, and delivery of products requiring long -lead time and procurement. The Construction Manager shall maintain Shop Drawings, Product Data and Samples and other submittal material from the Subcontractors in a separate tabular schedule. The Construction Manager shall update and reissue the Project construction schedule as required to show current conditions. If an update indicates that the previously approved Project construction schedule may not be met, the Construction Manager shall recommend corrective action to the Owner and Architect. § 2.3.2.11 The Construction Manager shall be responsible for coordinating the sequence of construction and the assigning of space in areas where the Subcontractors are performing work. § 2.3.2.12 The Construction Manager shall determine that the Work of each Subcontractor is being performed in accordance with the requirements of the Contract Documents to guard the Owner against defects and deficiencies in the Work. As appropriate, the Construction Manager shall have the authority, upon written authorization from the Owner, to require additional inspection or testing of the Work in accordance with the provisions of the Contract Documents, whether or not such Work is fabricated, installed or completed. The Construction Manager, in consultation with the Architect, may reject Work that does not conform to the requirements of the Contract Documents. The cost of additional inspections or testing of the Work as mutually agreed between the Parties pursuant to this subsection shall be borne by the Owner. AIA Document A133T1— 2009 (formerly A121 T1dCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 8 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. / This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA19) § 2.3.2.13 The Construction Manager shall schedule and coordinate the sequence of construction in accordance with the Contract Documents and the latest approved Project construction schedule, as well as schedule and coordinate any outside inspections required by law so as to avoid unnecessary delays. § 2.3.2.14 The Construction Manager shall arrange for the delivery, storage, protection and security of Owner - purchased materials, systems and equipment that are part of the Project until such items are incorporated into the Project, if such materials, systems and equipment are identified in the plans and specifications. Owner shall coordinate with Construction Manager and endeavor to deliver Owner -purchased materials for "just in time" delivery to minimize on site storage, in as much as reasonably possible. § 2.3.2.15 The Construction Manager shall review requests for changes, assist in negotiating the Subcontractor's proposals, submit recommendations to the Architect and Owner and, if they are accepted by the Owner, prepare Change Orders and Construction Directives which incorporate the Architect's modifications to the Documents. § 2.3.2.16 In collaboration with the Architect, the Construction Manager shall establish and implement procedures for expediting the processing and approval of shop drawings, product data, samples and other submittals. The Construction Manager shall review all shop drawings, product data, samples and other submittals from the Subcontractors. The Construction Manager shall coordinate submittals with information contained in related documents and transmit to the Architect those that have been approved by the Construction Manager. The Construction Manager's actions shall be taken with such reasonable promptness to cause no unreasonable delay in the Work or in the activities of the Owner or Subcontractors. § 2.3.2.17 The Construction Manager shall maintain at the Site or nearby primary office location for the Owner one record copy of all Contracts, Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition, approved shop drawings, product data, samples and similar required submittals. The Construction Manager shall maintain records, in duplicate, of principal building layout lines, elevations of the bottom of the footings, floor levels and key site elevations certified by a qualified surveyor or professional engineer. The Construction Manager shall make all such records and record Drawings available to the Architect and upon completion of the Project shall deliver them to the Owner. § 2.3.2.18 With the Architect and the Owner's agents, the Construction Manager shall conduct the final testing and start-up of utilities, operating systems and equipment. § 2.4 Professional Services Section 3.12.10 of A201-2007 shall apply to both the Preconstruction and Construction Phases. § 2.5 Hazardous Materials Section 10.3 of A201-2007 shall apply to both the Preconstruction and Construction Phases. ARTICLE 3 OWNER'S RESPONSIBILITIES § 3.1 Information and Services Required of the Owner § 3.1.1 The Owner shall provide information with reasonable promptness, regarding requirements for and limitations on the Project, including a written program which shall set forth the Owner's objectives, constraints, and criteria, including schedule, space requirements and relationships, flexibility and expandability, special equipment, systems, sustainability and site requirements. § 3.1.2 Reserved. § 3.1.3 The Owner shall establish and periodically update the Owner's budget for the Project, including (1) the budget for the Cost of the Work as defined in Section 6.1.1, (2) the Owner's other costs, and (3) reasonable contingencies related to all of these costs. If the Owner significantly increases or decreases the Owner's budget for the Cost of the Work, the Owner shall notify the Construction Manager and Architect. The Owner and the Architect, in consultation with the Construction Manager, shall thereafter agree to a corresponding change in the Project's scope and quality. AIA Document A133T^' — 2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIAO Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 9 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA19) § 3.1.4 Structural and Environmental Tests, Surveys and Reports. During the Preconstruction Phase, the Owner shall furnish the following information or services with reasonable promptness. The Owner shall also furnish any other information or services under the Owner's control and relevant to the Construction Manager's performance of the Work with reasonable promptness after receiving the Construction Manager's written request for such information or services. Except to the extent Construction Manager knows, or in the exercise of reasonable care and diligence should know, of any inaccuracy, the Construction Manager shall be entitled to rely on the accuracy of information and services furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work. § 3.1.4.1 The Owner shall furnish tests, inspections and reports required by law and as otherwise agreed to by the parties, such as structural, mechanical, and chemical tests, tests for air and water pollution, and tests for hazardous materials. § 3.1.4.2 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. The surveys and legal information shall include, as applicable, grades and lines of streets, alleys, pavements and adjoining property and structures; designated wetlands; adjacent drainage; rights-of-way, restrictions, easements, encroachments, zoning, deed restrictions, boundaries and contours of the site; locations, dimensions and necessary data with respect to existing buildings, other improvements and trees; and information concerning available utility services and lines, both public and private, above and below grade, including inverts and depths. All the information on the survey shall be referenced to a Project benchmark. § 3.1.4.3 The Owner, when such services are reasonably requested, shall furnish services of geotechnical engineers, which may include but are not limited to test borings, test pits, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, seismic evaluation, ground corrosion tests and resistivity tests, including necessary operations for anticipating subsoil conditions, with written reports and appropriate recommendations. § 3.1.4.4 During the Construction Phase, the Owner shall furnish information or services required of the Owner by the Contract Documents with reasonable promptness. The Owner shall also furnish any other information or services under the Owner's control and relevant to the Construction Manager's performance of the Work with reasonable promptness after receiving the Construction Manager's written request for such information or services. § 3.2 Owner's Designated Representative The Owner shall identify a representative authorized to act on behalf of the Owner with respect to the Project. The Owner's representative shall render decisions promptly and furnish information expeditiously, so as to avoid unreasonable delay in the services or Work of the Construction Manager. Except as otherwise provided in Section 4.2.1 of A201-2007, the Architect does not have such authority. The term "Owner" means the Owner or the Owner's authorized representative. § 3.2.1 Legal Requirements. The Owner shall furnish all legal, insurance and accounting services, including auditing services, that may be reasonably necessary at any time for the Project to meet the Owner's needs and interests. § 3.3 Architect The Owner has retained an Architect to provide services, duties and responsibilities as described in the executed agreement between the Owner and the Architect, and any further modifications to the agreement. The Owner shall provide the Construction Manager a copy of that agreement upon request by the Construction Manager. ARTICLE 4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES § 4.1 Compensation § 4.1.1 Reserved.: § 4.1.2 For the Construction Manager's Preconstruction Phase services described in Sections 2.1 and 2.2: (Paragraph Deleted) The fixed fee for Preconstruction Phase services will be $20,000. AIA Document A133TM —2009 (formerly A121 TMCMC — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 10 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) § 4.1.3 If the Preconstruction Phase services covered by this Agreement have not been completed within (24) ( (24) ) months of the date of this Agreement, through no fault of the Construction Manager, the Construction Manager may terminate this Agreement in accordance with Article 10. (Paragraph Deleted) § 4.2 Payments § 4.2.1 Unless otherwise agreed, payments for services shall be made monthly in proportion to services performed in accordance with Section 4.2.2. § 4.2.2 Payments of undisputed charges are due and payable upon presentation of the Construction Manager's invoice. Amounts unpaid (30) ( (30) ) days after the invoice date shall beat* interest at the rate entered below, or in the absence thereof at the legal rate prevailing from time to time at the principal place of business of the Construction Manager. (Paragraph Deleted) 1.00 % per month ARTICLE 5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES § 5.1 For the Construction Manager's performance of the Work as described in Section 2.3, the Owner shall pay the Construction Manager the Contract Sum in current funds. The Contract Sum is the Cost of the Work as defined in Section 6. 1.1 plus the Construction Manager's Fee. § 5.1.1 The Construction Manager's Fee: (Paragraphs Deleted) A fee of 5.5% (five and one-half percent) of the Cost of the Work not including the General Conditions Costs, any recommended contingency, bonds, surety or insurance costs, taxes or governmental fees. The value of donated construction materials and services, if any, will be included in the Cost of the Work for purposes of calculating the Construction Manager's Fee. The value of donations will be determined by the City, based on the engineering pre- bid estimates for the materials or service donated. § 5.1.2 Limitations, if any, on a Subcontractor's overhead and profit for increases in the cost of its portion of the Work are: 1) Subcontractor's overhead is limited to 10% and profit is limited to 5%. (Paragraphs Deleted) (Table Deleted) § 5.2 Guaranteed Maximum Price § 5.2.1 The Construction Manager guarantees that the Contract Sum shall not exceed the Guaranteed Maximum Price set forth in the Guaranteed Maximum Price Amendment, as it is amended from time to time. To the extent the Cost of the Work exceeds the Guaranteed Maximum Price, the Construction Manager shall bear such costs in excess of the Guaranteed Maximum Price without reimbursement or additional compensation from the Owner. To the extent the cost of the IT ork is less than the Guaranteed Maximum Price, the Construction Manager shall not be entitled to the difference or any portion thereof and the difference behneen the cost of the If ork and Guaranteed Maximum Price shall accrue to the Owner. Savings from any unused contingency controlled by Owner or Owner Allowances shall accrue to Owner. Total General Conditions Costs shall not decrease or increase after the establishment of the Guaranteed Maximum Price unless the Contract Time is adjusted in accordance with the Contract. § 5.2.2 The Guaranteed Maximum Price is subject to additions and deductions by Change Order as provided in the Contract Documents and the Date of Substantial Completion shall be subject to adjustment as provided in the Contract Documents. AIA Document A133TM —2009 (formerly A121 TMCMC —2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 11 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA19) § 5.3 Changes in the Work § 5.3.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions. The Owner shall issue such changes in writing. The Architect may make minor changes in the Work as provided in Section 7.4 of AIA Document A201-2007, General Conditions of the Contract for Construction. The Construction Manager may be entitled to an equitable adjustment in the Contract Sum or the Contract Time as a result of changes in the Work based on Owner's changes. § 5.3.2 Adjustments to the Guaranteed Maximum Price on account of changes in the Work subsequent to the execution of the Guaranteed Maximum Price Amendment may be determined by any of the methods listed in Section 7.3.3 of AIA Document A201-2007, General Conditions of the Contract for Construction. § 5.3.3 Adjustements to subcontracts shall be calculated in accordance with Section 7.3.3 of the AIA Document A201 - 2007. § 5.3.4 In calculating adjustments to the Guaranteed Maximum Price, the terms "cost" and "costs" as used in the above -referenced provisions of AIA Document A201-2007 shall mean the Cost of the Work as defined in Sections 6.1 to 6.7 of this Agreement and the term "fee" shall mean the Construction Manager's Fee as defined in Section 5.1 of this Agreement. (Paragraph Deleted) ARTICLE 6 COST OF THE WORK FOR CONSTRUCTION PHASE § 6.1 Costs to Be Reimbursed § 6.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior written consent of the Owner. The Cost of the Work shall include only the items set forth in Sections 6,1 through 6.7 as more particularly described below and as previously identified as part of the Guaranteed Maximum Price approved by Owner. § 6.1.2 Where any cost is subject to the Owner's prior approval, the Construction Manager shall obtain this approval in writing prior to incurring the cost. The parties shall endeavor to identify any such costs prior to executing Guaranteed Maximum Price Amendment. § 6.1.3 The Owner and Construction Manager agree that the Cost of the Work attributed as incidental and direct expenses incurred by the Construction Manager for the Project shall only include those specific, determined, fixed and settled costs set forth in Exhibit B (General Conditions Costs). General Conditions Costs shall only be charged by Construction Manager for these incidental and direct expenses incurred during the Contract Time as defined in Section 8.1.1 of AIA Document A201-2007. § 6.2 Labor Costs § 6.2.1 The following labor costs are incorporated by reference and included as General Conditions Costs: .1 Wages of construction workers directly employed by the Construction Manager to perform the construction of the Work at the site or, with the Owner's prior approval, at off-site workshops. § .2 Wages or salaries of the Construction Manager's supervisory and administrative personnel when stationed at the site with the Owner's prior approval. ( § .3 Wmployee bonuses will not be considered reimbursable labor or labor burden costs. Bonuses paid to the Construction Manager's employees will be considered a non -reimbursable cost.. (Paragraph Deleted) §4 Costs paid or incurred by the Construction Manager for taxes (including payroll taxes), insurance, contributions, assessments and benefits required by law or collective bargaining agreements and, for personnel not covered by such agreements, cenefits agreed to in advance in writing by Owner uch as sick leave, medical and health benefits, AIA Document A133TM —2009 (formerly A121 TICMC —2003). Copyright ©1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 12 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) holidays, vacations and pensions, provided such costs are based on wages and salaries included in the Cost of the Work § 6.3 Subcontract Costs Payments shall be made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts and applicable law. § 6.4 Costs of Materials and Equipment Incorporated in the Completed Construction § 6.4.1 Costs, including transportation and storage, of materials and equipment incorporated or to be incorporated in the completed construction. § 6.4.2 Costs of materials described in the preceding Section 6.4.1 in excess of those actually installed to allow for reasonable waste and spoilage. Unused excess materials, if any, shall become the Owner's property at the completion of the Work or, at the Owner's option, shall be sold by the Construction Manager. Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the Work. § 6.5 Costs of Other Materials and Equipment, Temporary Facilities, Miscellaneous General Conditions Costs and Related Items § 6,5.1 The following costs are incorporated by reference and included in General Conditions Costs: .1 Costs of transportation, storage, installation, maintenance, dismantling and removal of materials, supplies, temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Construction Manager at the site and fully consumed in the performance of the Work. Costs of materials, supplies, temporary facilities, machinery, equipment and tools that are not fully consumed shall be based on the cost or value of the item at the time it is first used on the Project site less the value of the item when it is no longer used at the Project site. Costs for items not fully consumed by the Construction Manager shall be based onmeair market value. § Rental charges for temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Construction Manager at the site and costs of transportation, installation, minor repairs, dismantling and removal. The total rental cost of any Construction Manager -owned item may not exceed the purchase price of any comparable item. Major repairs, overhauls, and/or replacements are to be covered by the rental rates and are not reimbursable. Rates of Construction Manager -owned equipment and quantities of equipment shall be subject to the Owner's prior written approval. § Costs of removal of debris from the site of the Work and its proper and legal disposal. § Costs of document reproductions, facsimile transmissions and long-distance telephone calls, postage and parcel delivery charges, telephone service at the site and reasonable petty cash expenses of the site office. § 6 osts of materials and equipment suitably stored off the site at a mutually acceptable location, subject to the Owner's prior written approval. (Paragraph Deleted) Cnstruction Manager must provide proof of insurance for materials and equipment stored off site. Construction Manager will provide to the Owner any and all supporting documentation reasonably requested and access to such materials and equipment. .6 Fees of laboratories for tests required by the Contract Documents, except those related to defective or nonconforming Work for which reimbursement is excluded by Section 13.5.3 of AIA Document A201-2007 or by other provisions of the Contract Documents. AIA Document A133TM —2009 (formerly A121 TMCMc —2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 13 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA19) (Paragraph Deleted) .7 Costs for electronic equipment and software, directly related to the Work with the Owner's prior written approval. § 6.6 Miscellaneous Costs § 6.6.1 Premiums for that portion of insurance and bonds required by the Contract Documents that can be directly attributed to this Contract. Self-insurance for either full or partial amounts of the coverages required by the Contract Documents, with the Owner's prior written approval. § 6.6.2 Sales, use or similar taxes imposed by a governmental authority that are related to the Work and for which the Construction Manager is liable. (Paragraph Deleted) § 6.7 Other Costs and Emergencies § 6.7.1 Other costs incurred in the performance of the Work if, and only to the extent, approved in advance in writing by the Owner. § 6.7.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency affecting the safety of persons and property, as provided in Section 10.4 of AIA Document A201-2007. § 6.7.3 Costs of repairing or correcting damaged or nonconforming Work executed by the Construction Manager, Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused by negligence or failure to fulfill a specific responsibility of the Construction Manager and only to the extent that the cost of repair or correction is not recovered by the Construction Manager from insurance, sureties, Subcontractors, suppliers, or others. § 6.7.4 The costs described in Sections 6.1 through 6.7 shall be included in the Cost of the Work, notwithstanding any provision of AIA Document A201-2007 or other Conditions of the Contract which may require the Construction Manager to pay such costs, unless such costs are excluded by the provisions of Section 6.8. § 6.7.5 Notwithstanding the provisions of Sections 6.1 through 6.7, it is the intent of this Agreement for the Construction Manager to provide management, site supervision, and supporting equipment and services as defined in Section 6.1.3 which are paid as General Conditions Costs. These General Conditions Costs shall be determined and mutually agreed upon between Owner and Construction Manager prior to the Guaranteed Maximum Price Amendment following completion of Pre -Construction Services. The General Conditions Costs shall not exceed $25,062.50 in any given month during the total Project duration, plus an additional fee of $27,000 (single lump sum) for Payment and Performance bonds, and $3000 (single lump sum) for mobilization and demobilization. § 6.8 Costs Not To Be Reimbursed § 6.8.1 The Cost of the Work shall not include the items listed below and these items shall not be included as General Conditions Costs: .1 Exhibit B of A133-2009 is strictly excluded from this section, any costs included in Exhibit Bare not governed by the definitions within these documents. Salaries and other compensation of the Construction Manager's personnel stationed at the Construction Manager's principal office or offices other than the Ssie office, except as specifically provided in Section 6.2, or as may be provided in Article 11; .2 Expenses of the Construction Manager's principal office and offices other than the site office; 3 Overhead and general expenses, except as may be expressly included in Sections 6.1 to 6.7 (costs of the Construction manager's home office computer services or other outside computer processing services shall be considered overhead and general expenses); .4 The Construction Manager's capital expenses, including interest on the Construction Manager's capital employed for the Work; .5 Except as provided in Section 6.7.3 of this Agreement, costs due to the negligence or failure of the Construction Manager, Subcontractors and suppliers or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract; .6 Any cost not specifically and expressly described in Sections 6.1 to 6.7; AIA Document A133TM —2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 14 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA19) .7 Costs, other than costs included in Change Orders approved by the Owner, that would cause the Guaranteed Maximum Price to be exceeded; an8 Costs for services incurred during the Preconstruction Phase; and. 9 Fees and assessments for the building permit and other permits and licenses which shall be paid by Owner based on the actual cost imposed by the issuing authority. § 6.9 Discounts, Rebates and Refunds § 6.9.1 Cash discounts obtained on payments made by the Construction Manager shall accrue to the Owner if (1) before making the payment, the Construction Manager included them in an Application for Payment and received payment from the Owner, or (2) the Owner has deposited funds with the Construction Manager with which to make payments; otherwise, cash discounts shall accrue to the Construction Manager. Trade discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Construction Manager shall make provisions so that they can be obtained. § 6.9.2 Amounts that accrue to the Owner in accordance with the provisions of Section 6.9.1 shall be credited to the Owner as a deduction from the Cost of the Work. § 6.10 Related Party Transactions § 6.10.1 For purposes of Section 6.10, the term "related party" shall mean a parent, subsidiary, affiliate or other entity having common ownership or management with the Construction Manager; any entity in which any stockholder in, or management employee of, the Construction Manager owns any interest in excess of ten percent in the aggregate; or any person or entity which has the right to control the business or affairs of the Construction Manager. The term "related party" includes any member of the immediate family of any person identified above. § 6.10.2 If any of the costs to be reimbursed arise from a transaction between the Construction Manager and a related party, the Construction Manager shall notify the Owner in writing of the specific nature of the contemplated transaction, including the identity of the related party and the anticipated cost to be incurred, before any such transaction is consummated or cost incurred. If the Owner in its sole discretion, after such notification, authorizes the proposed transaction, then the cost incurred shall be included as a cost to be reimbursed, and the Construction Manager shall procure the Work, equipment, goods or service from the related party, as a Subcontractor, according to the terms of Sections 2.3.2.1, 2.3.2.2 and 2.3.2.3. If the Owner fails to authorize the transaction, the Construction Manager shall procure the Work, equipment, goods or service from some person or entity other than a related party according to the terms of Sections 2.3.2.1, 2.3.2.2 and 2.3.2.3. § 6.11 Accounting Records The Construction Manager shall keep full and detailed records and accounts related to the Ccos of the Work and exercise such controls as may be necessary for proper financial management under this Contract and to substantiate all costs incurred. The accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner's staff, auditors, and agents shall, during regular business hours and upon reasonable notice, be afforded access to, and shall be permitted to audit and copy, the Construction Manager's records and accounts, including complete documentation supporting accounting entries, books, correspondence, instructions, drawings, receipts, subcontracts, Subcontractor's proposals, purchase orders, vouchers, memoranda and other data relating to this Contract for any proper purpose, including Construction Manager's compliance with Contract requirements and provisions for pricing Change Orders and evaluating invoices or claims. The Construction Manager shall preserve these records for a period of five (5)thrars after final payment, or for such longer period as may be required by law. ARTICLE 7 PAYMENTS FOR CONSTRUCTION PHASE SERVICES § 7.1 Progress Payments § 7.1.1 Based upon Applications for Payment submitted to the Architect by the Construction Manager and Certificates for Payment issued by the Architect and approved by the Owner, the Owner shall make progress payments on account of the Contract Sum to the Construction Manager as provided below and elsewhere in the Contract Documents. § 7.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month., AIA Document All 33 TM —2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 15 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) § 7.1.3 Notice of Alternative Billing Cycle and Extended Payment Provision. Proner shall make payment of the certified amount to the Construction Manager not later than thethirty ( (30) ) days after th Application for Payment is received by the Architect unless the Owner gives notice of disapproval pursuant to 28-2-2103, MCA and any other requirements of this Agreement. (Paragraphs Deleted) (Fe§ 7.1.4 iVith each Application for Payment, the Construction Manager shall submit payrolls, petty cash accounts, receipted invoices with sufficient detail including company name, address, phone number, and a detailed description including labor, equipment and materials identifj4ng the number of hours and rates included, or detailed invoices with check vouchers attached, and any other evidence required by the Owner or Architect to demonstrate that cash disbursements ah-eady made by the Construction Manager on account of the Cost of the Work equal or exceed progress payments already received by the Construction Manager, less that portion of those payments attributable to the Construction Manager's Fee, plus payrolls for the period covered by the present Application for Payment. § 7.1.5 Each Application for Payment shall be based on the most recent Owner -approved schedule of values which at a minimum shall identify each Subcontractor and all components of the Guaranteed Maximum Price submitted by the Construction Manager in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Construction Manager's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This schedule, unless objected to by the Owner, shall be used as a basis for reviewing the Construction Manager's Applications for Payment. § 7.1.6 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. The percentage of completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed, or (2) the percentage obtained by dividing (a) the expense that has actually been incurred by the Construction Manager on account of that portion of the Work for which the Construction Manager has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. § 7.1.7 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: .1 Take that portion of the Guaranteed Maximum Price properly allocable to completed Work as determined by multiplying the percentage of completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the Owner -approved schedule of values.; .2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work, or if approved in advance by the Owner in writing (and provided that the Construction Manager shall provide the Owner with evidence of insurance acceptable to Owner for full replacement and naming the Owner as additional insured, provide a bill of sale and provide for inspection by the Owner), suitably stored off the site at a location agreed upon in writing; 3 Add the Construction Manager's Fee, less retainage of Five percent ( 5.00 %). The Construction Manager's Fee shall be computed upon the Cost of the Work at the rate stated in Section 5.1; .4 Subtract retainage of Five percent ( 5.00 %) from that portion of the Work that the Construction Manager self -performs; retention shall be deposited in the interest bearing account; .5 Subtract the aggregate of previous payments made by the Owner; .6 Subtract the shortfall, if any, indicated by the Construction Manager in the documentation required by Section 7.1.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's auditors in such documentation; and .7 Subtract amounts, if any, for which the Owner has withheld or nullified a Certificate for Payment as provided in Section 9.5 of AIA Document A201-2007. § 7.1.8 The Owner and Construction Manager shall agree upon (1) a mutually acceptable procedure for review and approval of payments to Subcontractors and (2) the percentage of retainage held on Subcontracts, and the Construction Manager shall execute subcontracts in accordance with those agreements. AIA Document Al33TM —2009 (formerly A121 TMCMe —2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. (flit. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 16 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) § 7.1.9 Except with the Owner's prior written approval, the Construction Manager shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. § 7.1.10 In taking action on the Construction Manager's Applications for Payment, the Architect shall be entitled to rely on the accuracy and completeness of the information furnished by the Construction Manager and shall not be deemed to represent that the Architect has made a detailed examination, audit or arithmetic verification of the documentation submitted in accordance with Section 7.1.4 or other supporting data; that the Architect has made exhaustive or continuous on-site inspections; or that the Architect has made examinations to ascertain how or for what purposes the Construction Manager has used amounts previously paid on account of the Contract. Such examinations, audits and verifications, if required by the Owner, will be performed by the Owner's auditors acting in the sole interest of the Owner. § 7.1.11 The Construction Manager shall develop and implement procedures for the timely review and processing of applications for payment by Subcontractors for progress and final payments. § 7.1.12 Based on the Construction Manager's observations and evaluations of each Subcontractor's application for payment, the Construction Manager shall review and certify the amounts due the respective Subcontractors and shall incorporate such certified amounts into the Application for Payment developed under § 7.1.5 above. § 7.2 Final Payment § 7.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Construction Manager when .1 the Construction Manager has fully performed the Contract except for the Construction Manager's responsibility to correct Work as provided in Section 12.2.2 of AIA Document A201-2007, and to satisfy other requirements, if any, which necessarily extend beyond final payment; .2 the Construction Manager has submitted a final accounting for the Cost of the Work and a final Application for Payment; and .3 a final Certificate for Payment has been issued by the Architect. The Owner's final payment to the Construction Manager shall be made no later than thirty (30) days after the issuance and Owner approval of the Architect's final Certificate for Payment. § 7.2.2 The amount of final payment shall be calculated as follows: (1) take the sum of the Cost of the Work (substantiated by the Construction Manager's final accounting) and the Construction Manager's Fee, not to exceed the Guaranteed Maximum Price; (2) subtract amounts, if any, for which the Owner withholds, in whole or in part, a final Certificate of Payment as provided in Section 9.5.1 of the AIA A201-2007 or other provisions of the Contract Documents; and (3) subtract the aggregate of previous payments made by Owner.. § 7.2.3 The Architect will, within seven days after receipt of the final Application for Payment, either issue to the Owner for Owner's approval a final Certificate for Payment with a copy to the Construction Manager, or notify the Construction Manager and Owner in writing of the Architect's or Owner's reasons for withholding a certificate as provided in Section 9.5.1 of the AIA Document A201-2007. The time periods stated in this Section supersede those stated in Section 9.4.1 of the AIA Document A201-2007. The Owner may retain auditors or other agents as the Owner deems necessary to perform services, review, or take any other action regarding final payment the cost of which shall be borne by the Owner. § 7.2.4 If the Owner's auditors report the Cost of the Work as substantiated by the Construction Manager's final accounting to be less than claimed by the Construction Manager, the Construction Manager shall be entitled to request the parties enter into the decision and mediation process set forth in Sections 15.2 and 15.3 of the AIA Document A201-2007 regarding the disputed amount. A request for a decision, mediation and payment of the final certified amount less the disputed amount shall be made by the Construction Manager within 30 days after the Construction Manager's receipt of a copy of the Architect's final Certificate for Payment. Failure to request a decision and mediation with in this 30 day period shall result in the substantiated amount reported by the Owner's auditors becoming binding on the Construction Manager. AIA Document A133Tm —2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 17 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) (Paragraph Deleted) ARTICLE 8 INSURANCE AND BONDS For all phases of the Project, the Construction Manager shall purchase and maintain insurance, and the Construction Manager shall provide bonds as set forth in Article I 1 of AIA Document A201-2007. (Paragraph Deleted) (Table Deleted) ARTICLE 9 DISPUTE RESOLUTION § 9.1 Any Claim between the Owner and Construction Manager shall be resolved in accordance with the provisions set forth in this Article 9 and Article 15 of A201-2007. (Paragraphs Deleted) ARTICLE 10 TERMINATION OR SUSPENSION § 10.1 Termination Prior to Establishment of the Guaranteed Maximum Price § 10.1.1 Prior to the execution of the Guaranteed Maximum Price Amendment, the Owner may terminate this Agreement upon not less than seven days' written notice to the Construction Manager for the Owner's convenience and without cause, and the Construction Manager may terminate this Agreement, upon not less than seven days' written notice to the Owner, for the reasons set forth in Section 14. 1.1 of A201-2007. § 10.1.2 In the event of termination of this Agreement pursuant to Section 10.1.1, the Construction Manager shall be equitably compensated for Preconstruction Phase services performed by the Construction Manager prior to receipt of a notice of termination pursuant to the terms for the applicable phase of preconstruction services described in Exhibit C. In no event shall the Construction Manager's compensation under this Section exceed the compensation set forth in Section 4.1. (Paragraphs Deleted) § 10.2 Termination Subsequent to Establishing Guaranteed Maximum Price Following execution of the Guaranteed Maximum Price Amendment and subject to the provisions of Section 10.2.1 and 10.2.2 below, the Contract may be terminated as provided in Article 14 of AIA Document A201-2007. § 10.2.1 If the Owner terminates the Contract after execution of the Guaranteed Maximum Price Amendment, the amount payable to the Construction Manager pursuant to Sections 14.2 and 14.4 of A201-2007 shall not exceed the amount the Construction Manager is entitled tofor Work completed and shall be made in accordance with the payment provisions of Article 7 of this Agreement. § 10.2.2 If the Construction Manager terminates the Contract after execution of the Guaranteed Maximum Price Amendment, the amount payable to the Construction Manager under Section 14.1.3 of A201-2007 shall not exceed the amount the Construction Manager is entitled to for Work completed and shall be made in accordance with the payment provisions of Article 7 of this Agreement. § 10.3 Suspension The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201-2007. In such case, the amount payable to the Construction Manager shall not exceed the amount the Construction Manager is entitled to for Work completed and shall be made in accordance with the payment provisions of Article 7 of this Agreementt. ARTICLE 11 'MISCELLANEOUS PROVISIONS 11.1 Terms in this Agreement shall have the same meaning as those in A201-2007. § 11.2 Ownership and Use of Documents Section 1.5 of A201-2007 shall apply to both the Preconstruction and Construction Phases. AIA Document A133 TM — 2009 (formerly A121 TMCMc — 2003). Copyright© 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° 18 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA19) § 11.3 Governing Law Section 13.1 of A201-2007 shall apply to both the Preconstruction and Construction Phases. § 11.4 Assignment The Owner and Construction Manager, respectively, bind themselves, their agents, successors, assigns and legal representatives to this Agreement. Neither the Owner nor the Construction Manager shall assign this Agreement in whole or in part without the written consent of the other, except that the Owner may assign this Agreement to a lender providing financing for the Project if the lender agrees to assume the Owner's rights and obligations under this Agreement. Except as provided in Section 13.2.2 of A201-2007, neither party to the Contract shall assign the Contract as a whole without written consent of the other. If either party attempts to make such an assignment without such consent, that party shall nevertheless remain legally responsible for all obligations under the Contract. § 11.5 Attorney Fees. In the event either party files suit to enforce their rights under this Agreement, the prevailing party shall be entitled to recover their costs and attorney's fees, including those of the City Attorney's Office from the other party, in addition to any other damages awarded by the court. ARTICLE 12 SCOPE OF THE AGREEMENT § 12.1 This Agreement represents the entire and integrated agreement between the Owner and the Construction Manager and supersedes all prior negotiations, representations or agreements, either written or oral. This Agreement may be amended only by written instrument signed by both Owner and Construction Manager. § 12.2 The following documents comprise the Agreement: .1 AIA Document A133-2009, Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price .2 AIA Document A201 2007, General Conditions of the Contract for Construction (Paragraph Deleted) Other documents: (Paragraph Deleted) Exhibit A: Guaranteed Maximum Price Amendment Exhibit B: General Conditions Costs Exhibit C: Preconstruction Phase Payments This Agreement is entered into as of the day and year first written above. OWNER (Signature) CONS RUCTIO MANAG ��T-✓ l''IU�,gPI ,��t�s /�. ll�l��l!sl� � '° (P inted name nd title) (Printed name and title) AIA Document A133 TM —2009 (formerly A121 TMCMe — 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. Init. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® 19 Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. t This document was produced by AIA software at 16:12:25 on 05/17/2016 under Order No. 1601131298 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA19) AIA Document A133 TIM - 2009 Exhibit A Guaranteed Maximum Price Amendment for the following PROJECT: (Name and address or location) Bozeman Sports Park 4600 Baxter Lane Bozeman, MT 59718 THE OWNER: (Name, legal status and address) The City of Bozeman Montana 121 N. Rouse Ave. PO Box 1230 Bozeman, MT 59771-1230 ("Owner") and the Construction Manager: (Name, legal status and address) Dick Anderson Construction, Inc. 4498 Jackrabbit Lane Bozeman, MT 59718 ("Construction Manager") ARTICLE A.1 § A.1.1 Guaranteed Maximum Price Pursuant to Section 2.2.6 of the Agreement, the Owner and Construction Manager hereby amend the Agreement to establish a Guaranteed Maximum Price. As agreed by the Owner and Construction Manager, the Guaranteed Maximum Price is an amount that the Contract Sum shall not exceed. The Contract Sum consists of the Construction Manager's Fee plus the Cost of the Work, as that term is defined in Article 6 of this Agreement. § A.1.1.1 The Contract Sum is guaranteed by the Construction Manager not to exceed « ($ « » ), subject to additions and deductions by Change Order as provided in the Contract Documents. § A.1.1.2 Itemized Statement of the Guaranteed Maximum Price. Provided below is an itemized statement of the Guaranteed Maximum Price organized by trade categories, allowances, contingencies, alternates, the Construction Manager's Fee, and other items that comprise the Guaranteed Maximum Price. (Provide below or reference an attachment.) § A.1.1.3 The Guaranteed Maximum Price is based on the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. AIA Document A201--2007, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. AIA Document A133" — 2009 Exhibit A. Copyright 9 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent 1 possible under the law. This draft was produced by AIA software at 19:95:90 on 12/02/2015 under order No. 7109973622 which expires on 12/01/2016, and is not for resale. User Notes: (3B9ADAIF) (State the numbers or other identification of accepted alternates. If the Contract Documents permit the Owner to accept other alternates subsequent to the execution of this Amendment, attach a schedule of such other alternates showing the amount for each and the date when the amount expires.) « » § A.1.1.4 Allowances included in the Guaranteed Maximum Price, if any: (Idents allowance and state exclusions, if any, from the allowance price.) Item Price ($0.00) § A.1.1.5 Assumptions, if any, on which the Guaranteed Maximum Price is based: § A.1.1.6 The Guaranteed Maximum Price is based upon the following Supplementary and other Conditions of the Contract: Document Title Date § A.1.1.7 The Guaranteed Maximum Price is based upon the following Specifications: (Either list the Specifications here, or refer to an exhibit attached to this Agreement.) Section Title Date § A.1.1.8 The Guaranteed Maximum Price is based upon the following Drawings: (Either list the Drawings here, or refer to an exhibit attached to this Agreement.) Number c» Title Date Pages Pages § A.1.1.9 The Guaranteed Maximum Price is based upon the following other documents and information: (List any other documents or information here, or refer to an exhibit attached to this Agreement.) t» ARTICLE A.2 § A.2.1 The anticipated date of Substantial Completion established by this Amendment: « » « » OWNER (Signature) (Printed name and title) CONSTRUCTION MANAGER (Signature) (Printed name and title) AIA Document A133' - 2009 Exhibit A. Copyright 9 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIAO Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of 2 this AIA• Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possibleunder the law. This draft was produced by AIA software at 14:45:40 on 12/02/2015 under Order No. 7109973622 which expires on 12/01/2016, and is not for resale. User Notes: (3B9ADAIF) 10.14 m -- to AIA Document A133 — 2009, Standard Form of Agreement Between Owner and Construction Manager as Constructor (Form GC - CONSTRU(`TION PHASE GENERAL CONDITIONS COSTS PLEASE SPECI1,Y HOW EACH CA ERGORY IS TO BE MONTHLY LUMP SUM CHARGED E Otfiee Fxpenses, including: S12,062.50 month S 96,500 E lump cum 1 (,3(/CM field office equipment and supplies; records and records nianawment; meeting expenses; site signage; quality control; all printing and mailing expenses and rill other adininistratixe expenses Construction Management Labor including: �S 13,000 f aracanth � Ssum 104,000 lonaP C,CiCM9 cast management, safety, anti oneral conditions labor (including all fringe and insurance) Monthly Total: Lung Sunt Total: Other expenses not listed above (add to list as necessary): [ Payment and Performance Bonds / month S_.. 27,000 — lump sum 1 Mobilization & Demobilization 5 /month S 3,000 lump sum f month S E lump sunt j i TOTAL: 5 28,812.50 / month $230,500 lump sum 10.4y"33194 to AIA Document A133 — 2009, Standard Form of Agreement Between Owner and Construction Manager as Constructor PRECONSTRUCTION PHASE PAYMENTS Preconstruction services will be provided on a fixed fee basis. PHASE ONE: The period of time from the time the General Contractor/Construction Manager contract commences until Conditional Site Plan approval is obtained from the Community Development Department and the 70% complete set of Construction Documents is submitted to the City by the Architect. Fixed Fee for Phase One: $_10,000.00 (_ten thousand Dollars) PHASE TWO: The period of time from the time Conditional Site Plan approval from the Community Development Department is obtained and the 70% complete set of Construction Documents is submitted to the City by the Design Consultant until the Owner agrees to a Guaranteed Maximum Price as set forth in Section 5.2 of the AIA A-133 — 2009. Fixed Fee for Phase Two: $_10,000.00 (_ten thousand—Dollars) -IM AIA Document A201TM —2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) Bozeman Spoils Park Bozeman, Montana ADDITIONS AND DELETIONS: The author of this document has THE OWNER: added information needed for its (Alain, legal status and address) completion. The author may also have revised the text of the original AIA standard form. An Additions and The City of Bozeman Montana Deletions Report that notes added 121 N. Rouse Ave. information as well as revisions to PO Box 1230 the standard form text is available Bozeman, MT 59771-1230 from the author and should be reviewed. A vertical line in the left ("Owner") margin of this document indicates where the author has added THE ARCHITECT: necessary information and where (Name, legal status and address) the author has added to or deleted DOWL, LLC from the original AIA text. 2090 Stadium Drive Bozeman, MT 59715 This document has important legal consequences. Consultation with an attorney is encouraged with respect TABLE OF ARTICLES to its completion or modification. 1 GENERAL PROVISIONS 2 OWNER 3 CONTRACTOR 4 ARCHITECT 5 SUBCONTRACTORS 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 7 CHANGES IN THE WORK 8 TIME 9 PAYMENTS AND COMPLETION 10 PROTECTION OF PERSONS AND PROPERTY 11 INSURANCE AND BONDS 12 UNCOVERING AND CORRECTION OF WORK 13 MISCELLANEOUS PROVISIONS 14 TERMINATION OR SUSPENSION OF THE CONTRACT AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) 15 CLAIMS AND DISPUTES AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 2 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) INDEX (Topics and numbers in bold are section headings.) (Index may not accurately reflect amended Contract provisions.) Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3 Acceptance of Work 9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3 Access to Work 3.16, 6.2.1, 12.1 Accident Prevention 10 Acts and Omissions 3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.4.2, 13.7, 14.1, 15.2 Addenda 1.1.1, 3.11 Additional Costs, Claims for 3.7.4, 3.7.5, 6.1.1, 7.3.7.5, 10.3, 15.1.4 Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.5 Additional Insured 11.1.4 ' Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.5 Administration of the Contract 3.1.3, 4.2,9.4, 9.5 Advertisement or Invitation to Bid 1.1.1 Aesthetic Effect 4.2.13 Allowances 3.8, 7.3.8 All-risk Insurance 11.3.1, 11.3.1.1 Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.6.3, 9.7, 9. 10, 11.1.3 Approvals 2.1.1, 2.2.2, 2.4, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12. 10, 4.2.7, 9.3.2, 13.5.1 Arbitration 8.3.1, 11.3.10,13.1, 15.3.2, 15.4 ARCHITECT 4 Architect, Definition of 4.1.1 Architect, Extent of Authority 2.4, 3.12.7, 4.1, 4.2, 5.2, 6.3, 7.1.2, 7.3.7, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.5.1, 13.5.2,14.2.2, 14.2.4, 15.1.3, 15.2.1 Architect, Limitations of Authority and Responsibility 2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3,4.2.6,4.2.7,4.2.10,4.2.12,4.2.13,5.2.1,7.4, 9.4.2, 9.5.3, 9.6.4, 15.1.3, 15.2 Architect's Additional Services and Expenses 2.4, 11.3.1.1, 12.2.1, 13.5.2, 13.5.3, 14.2.4 Architect's Administration of the Contract 3.1.3, 4.2, 3.7.4, 15.2, 9.4.1, 9.5 Architect's Approvals 2.4, 3.1.3, 3.5, 3.10.2, 4.2.7 Architect's Authority to Reject Work 3.5, 4.2.6, 12.1.2, 12.2.1 Architect's Copyright 1.1.7, 1.5 Architect's Decisions 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.5.2, 15.2, 15.3 Architect's Inspections 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.5 Architect's Instructions 3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.5.2 Architect's Interpretations 4.2.11, 4.2.12 Architect's Project Representative 4.2.10 Architect's Relationship with Contractor 1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.4.2, 13.5, 15.2 Architect's Relationship with Subcontractors 1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3.7 Architect's Representations 9.4.2, 9.5.1, 9.10.1 Architect's Site Visits 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.5 Asbestos 10.3.1 Attorneys' Fees 3.18.1, 9.10.2, 10.3.3 Award of Separate Contracts 6.1.1, 6.1.2 Award of Subcontracts and Other Contracts for Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements 1.1.1, 5.2.1, 11.4.1 Binding Dispute Resolution 9.7, 11.3.9, 11.3.10, 13.1, 15.2.5, 15.2.6.1, 15.3. 1, 15.3.2, 15.4.1 Boiler and Machinery Insurance 11.3.2 Bonds, Lien AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) 7.3.7.4, 9.10.2, 9.10.3 Bonds, Performance, and Payment 7.3.7.4, 9.6.7, 9.10.3, 11.3.9, 11.4 Building Permit 3.7.1 Capitalization 1.3 Certificate of Substantial Completion 9.8.3, 9.8.4, 9.8.5 Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.3 Certificates of Inspection, Testing or Approval 13.5.4 Certificates of Insurance 9.10.2, 11.1.3 Change Orders 1. 1. 1, 2.4, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.6, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.3.1.2, 11.3.4, 11.3.9, 12.1.2, 15.1.3 Change Orders, Definition of 7.2.1 CHANGES IN THE WORK 2.2.1, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3. 1. 1, 11.3.9. Claims, Definition of 15.1.1 CLAIMS AND DISPUTES 3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4 Claims and Timely Assertion of Claims 15.4.1 Claims for Additional Cost 3.2.4, 3.7.4, 6.1.1, 7.3.9, 10.3.2, 15.1.4 Claims for Additional Time 3.2.4, 3.7.4, 6.1.1, 8.3.2, 10.3.2, 15.1.5 Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages 3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3,5, 11.3.7, 14.1.3, 14.2.4, 15.1.6 Claims Subject to Arbitration 15.3.1, 15.4.1 Cleaning Up 3.15, 6.3 Commencement of the Work, Conditions Relating to 2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.3.1, 11.3.6, 11.4. 1, 15.1.4 Commencement of the Work, Definition of 8.1.2 Communications Facilitating Contract Administration 3.9.1, 4.2.4 Completion, Conditions Relating to 3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9. 1, 9.10, 12.2, 13.7, 14.1.2 COMPLETION, PAYMENTS AND 9 Completion, Substantial 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 13.7 Compliance with Laws 1.6, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 10.2.2, 11. 1, 11.3, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14. 1. 1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3 Concealed or Unknown Conditions 3.7.4, 4.2.8, 8.3.1, 10.3 Conditions of the Contract 1.1.1, 6.1.1, 6.1.4 Consent, Written 3.4.2, 3.7.4, 3.12.8, 3.14.2, 4.1.2, 9.3.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 11.3.1, 13.2, 13.4.2, 15.4.4.2 Consolidation or Joinder 15.4.4 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 1.1.4, 6 Construction Change Directive, Definition of 7.3.1 Construction Change Directives 1. 1. 1, 3.4.2, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1 Construction Schedules, Contractor's 3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2 Contingent Assignment of Subcontracts 5.4, 14.2.2.2 Continuing Contract Performance 15.1.3 Contract, Definition of 1.1.2 CONTRACT, TERMINATION OR SUSPENSION OF THE 5.4.1.1, 11.3.9, 14 Contract Administration 3.1.3, 4, 9.4,9.5 Contract Award and Execution, Conditions Relating to 3.7.1, 3.10, 5.2, 6.1, 11.1.3, 11.3.6, 11.4.1 Contract Documents, Copies Furnished and Use of 1.5.2, 2.2.5, 5.3 Contract Documents, Definition of 1.1.1 Contract Sum 3.7.4, 3.8, 5.2.3, 7.2, 7.3, 7.4, 9.1, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.3.1, 14.2.4, 14.3.2, 15.1.4, 15.2.5 Contract Sum, Definition of 9.1 Contract Time 3.7.4, 3.7.5, 3.10.2, 5.2.3, 7.2.1.3, 7.3.1, 7.3.5, 7.4, 8.1.1, 8.2.1, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 14.3.2, 15.1.5.1, 15.2.5 Contract Time, Definition of Init. AIA Document A201Tm — 2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 4 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) 8.1.1 CONTRACTOR 3 Contractor, Definition of 3.1, 6.1.2 Contractor's Construction Schedules 3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2 Contractor's Employees 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11. 1. 1, 11.3.7, 14.1, 14.2. 1.1 Contractor's Liability Insurance 11.1 Contractor's Relationship with Separate Contractors and Owner's Forces 3.12.5, 3.14.2, 4.2.4, 6, 11.3.7, 12.1.2, 12.2.4 Contractor's Relationship with Subcontractors 1.2.2, 3.3.2, 3.18.1.,3.18.2, 5, 9.6.2, 9.6.7, 9.10.2, 11.3.1.2, 11.3.7, 11.3.8 Contractor's Relationship with the Architect 1.1.2, 1.5, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.3, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3.7, 12, 13.5, 15.1.2, 15.2.1 Contractor's Representations 3.2.1,3.2.2,3.5,3.12.6,6.2.2,8.2.1,9.3.3,9.8.2 Contractor's Responsibility for Those Performing the Work 3.3.2,3,18,5.3,6.1.3,6.2,9.5.1, 10.2.8 Contractor's Review of Contract Documents 3.2 Contractor's Right to Stop the Work 9.7 Contractor's Right to Terminate the Contract 14.1, 15.1.6 Contractor's Submittals 3.10, 3.11, 3.12.4,4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2,`9.10.3, 11.1.3, 11.4.2 Contractor's Superintendent 3.9, 10.2.6 Contractor's Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.5, 7.3.7, 8.2, 10, 12, 14, 15.1.3 Contractual Liability Insurance 11.1.1.8, 11.2 Coordination and Correlation 1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1 Copies Furnished of Drawings and Specifications 1.5, 2.2,5, 3.11 Copyrights 1.5, 3.17 Correction of Work 2.3, 2.4, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2 Correlation and Intent of the Contract Documents 1.2 Cost, Definition of 7.3.7 Costs 2.4, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.7, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.3, 12.1.2, 12.2.1, 12.2.4, 13.5, 14 Cutting and Patching 3.14, 6.2.5 Damage to Construction of Owner or Separate Contractors 3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 11.1.1, 11.3, 12.2.4 Damage to the Work 3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 11.3.1, 12.2.4 Damages, Claims for 3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.1.1, 11.3.5, 11.3.7, 14.1.3, 14.2.4, 15.1.6 Damages for Delay 6.1.1, 8.3.3, 9.5.1.6, 9.7, 10.3.2 Date of Commencement of the Work, Definition of 8.1.2 Date of Substantial Completion, Definition of 8.1.3 Day, Definition of 8.1.4 Decisions of the Architect 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 15.2, 6.3, 7.3.7, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.5.2, 14.2.2, 14.2.4, 15.1, 15.2 Decisions to Withhold Certification 9.4.1, 9.5, 9.7, 14.1.1.3 Defective or Nonconforming Work, Acceptance, Rejection and Correction of 2.3, 2.4, 3.5, 4.2.6, 6.2.5, 9.5.1, 9.5.2, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1 Definitions 1.1,2.1.1,3.1.1,3.5,3.12.1,3.12.2,3.12.3,4.1.1, 15.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1 Delays and Extensions of Time 3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.5, 15.2.5 Disputes 6.3, 7.3.9, 15.1, 15.2 Documents and Samples at the Site 3.11 Drawings, Definition of 1.1.5 Drawings and Specifications, Use and Ownership of 3.11 Effective Date of Insurance 8.2.2, 11.1.2 Emergencies 10.45 14.1.1.2, 15.1.4 Employees, Contractor's 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3.3, 11.1.1, 11.3.7, 14.1, 14.2.1.1 Equipment, Labor, Materials or 1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15. 1, AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 5 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2 Execution and Progress of the Work 1.1.3, 1.2.1, 1.2.2, 2.2.3, 2.2.5, 3.1, 3.3.1, 3.4.1, 3.5, 3.7.1, 3.10.1, 3.12, 3.14, 4.2, 6.2.2, 7.1.3, 7.3.5, 8.2, 9.5.1, 9.9.1, 10.2, 10.3, 12.2, 14.2, 14.3.1, 15.1.3 Extensions of Time 3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3, 7.4, 9.5.1, 9.7, 10.3.2, 10.4, 14.3, 15.1.5, 15.2.5 Failure of Payment 9.5.1.3, 9.7, 9.10.2, 13.6, 14.1.1.3, 14.2.1.2 Faulty Work (See Defective or Nonconforming Work) Final Completion and Final Payment 4.2.1, 4.2.9, 9.8.2, 9.10, 11.1.2, 11.1.3, 11.3.1, 11.3.5, 12.3, 14.2.4, 14.4.3 Financial Arrangements, Owner's 2.2.1, 13.2.2, 14.1.1.4 Fire and Extended Coverage Insurance 11.3.1.1 GENERAL PROVISIONS 1 Governing Law 13.1 Guarantees (See Warranty) Hazardous Materials 10.2.4, 10.3 Identification of Subcontractors and Suppliers 5.2.1 Indemnification 3.17, 3.18, 9.10.2, 10.3.3, 10.3.5, 10.3.6, 11.3.1.2, 11.3.7 Information and Services Required of the Owner 2.1.2, 2.2, 3.2.2, 3.12.4, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.6.1, 9.6,4, 9,9.2, 9.10.3, 10.3.3,11.2, 11.4, 13.5.1, 13.5.2,14.1.1.4,14.1.4,15.1.3 Initial Decision 15.2 Initial Decision Maker, Definition of 1.1.8 Initial Decision Maker, Decisions 14.2.2, 14.2.4, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5 Initial Decision Maker, Extent of Authority 14.2.2, 14.2.4, 15.1.3, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5 Injury or Damage to Person or Property 10.2.8, 10.4 Inspections 3.1.3, 3.3.3, 3.7.1, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 12.2.1, 13.5 Instructions to Bidders 1.1.1 Instructions to the Contractor 3.2.4, 3.3.1, 3.8.1, 5.2.1, 7, 8.2.2, 12, 13.5.2 Instruments of Service, Definition of 1.1.7 Insurance 3.18.1, 6.1.1, 7.3.7, 9.3.2, 9.8.4, 9.9.1, 9.10.2, 11 Insurance, Boiler and Machinery 11.3.2 Insurance, Contractor's Liability 11.1 Insurance, Effective Date of 8.2.2, 11.1.2 Insurance, Loss of Use 11.3.3 Insurance, Owner's Liability 11.2 Insurance, Property 10.2.5, 11.3 Insurance, Stored Materials 9.3.2 INSURANCE AND BONDS 11 Insurance Companies, Consent to Partial Occupancy 9.9.1 Intent of the Contract Documents 1.2.1, 4.2.7, 4.2.12, 4.2.13, 7.4 Interest 13.6 Interpretation 1.2.3, 1.4, 4.1.1, 5.1, 6.1.2, 15. 1.1 Interpretations, Written 4.2.11, 4.2.12, 15.1.4 Judgment on Final Award 15.4.2 Labor and Materials, Equipment 1.1.3, 1.1.6,3.4,3.5,3.8.2,3.8.3,3.12,3.13,3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2 Labor Disputes 8.3.1 Laws and Regulations 1.5, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 9.9.1, 10.2.2,11.1.1,11.3,13.1,13.4,13.5.1,13.5.2,13.6, 14, 15.2.8, 15.4 Liens 2.1.2, 9.3.3, 9.10.2, 9.10.4, 15.2.8 Limitations, Statutes of 12.2.5, 13.7, 15.4.1.1 Limitations of Liability 2.3, 3.2.2, 3.5, 3.12.10, 3.17, 3.18.1, 4.2.6, 4.2.7, 4.2.12, 6.2.2, 9.4.2, 9.6.4, 9.6.7, 10.2.5, 10.3.3, 11. 1.2, 11.2, 11.3.7, 12.2.5, 13.4.2 Limitations of Time 2.1.2, 2.2, 2.4, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2.7, 5.2, 5.3, 5.4.1, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 11.1.3, 11.3.1.5, 11.3.6, 11.3.10, 12.2, 13.5, 13.7, 14, 15 Loss of Use Insurance 11.3.3 Material Suppliers 1.5, 3.12.1, 4.2.4, 4.2.6, 5.2.1, 9.3, 9.4.2, 9.6, 9.10.5 Materials, Hazardous AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American (nit. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) 10.2.4, 10.3 Materials, Labor, Equipment and 1.1.3, 1.1.6, 1.5.1,3.4.1,3.5,3.8.2,3.8.3,3.12,3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.7, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1.2, 10.2.4, 14.2.1.1, 14.2.1.2 Means, Methods, Techniques, Sequences and Procedures of Construction 3.3.1, 3.12.10, 4.2.2, 4.2.7, 9.4.2 Mechanic's Lien 2.1.2, 15.2.8 Mediation 8.3.1, 10.3.5, 10.3.6, 15.2.1, 15.2.5, 15.2.6, 15.3, 15.4.1 Minor Changes in the Work 1.1.1, 3.12.8, 4.2.8, 7.1,7.4 MISCELLANEOUS PROVISIONS 13 Modifications, Definition of 1.1.1 Modifications to the Contract 1.1.1, 1.1.2, 3.11, 4.1.2, 4.2.1, 5.2.3, 7, 8.3.1, 9.7, 10.3.2, 11.3.1 Mutual Responsibility 6.2 Nonconforming Work, Acceptance of 9.6.6, 9.9.3, 12.3 Nonconforming Work, Rejection and Correction of 2.3, 2.4, 3.5, 4.2.6, 6.2.4, 9.5.1, 9.8.2, 9.9.3, 9.10.4, 12.2.1 Notice 2.2.1,2.3,2.4,3.2.4,3.3.1,3.7.2,3.12.9, 5.2.1, 9.7, 9.10, 10.2.2, 11.1.3, 12.2.2.1, 13.3, 13.5.1, 13.5.2, 14.1, 14.2, 15.2.8, 15.4.1 Notice, Written 2.3, 2.4, 3.3.1, 3,9.2, 3.12.9, 3.12.10, 5.2.1, 9.7, 9. 10, 10.2.2, 10.3, 11.1.3, 11.3.6, 12.2.2.1, 13.3, 14, 15.2.8, 15.4.1 Notice of Claims 3.7.4, 10.2.8, 15.1.2,15.4 Notice of Testing and Inspections 13.5.1, 13.5.2 Observations,Contractor's 3.2,3.7.4 Occupancy 2.2.2, 9.6.6, 9.8, 11.3.1.5 Orders, Written 1.1.1, 2.3, 3.9.2, 7, 8.2.2, 11.3.9, 12.1, 12.2.2.1, 13.5.2, 14.3.1 OWNER 2 Owner, Definition of 2,1.1 Owner, Information and Services Required of the 2.1.2, 2.2, 3.2.2, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.3.2, 9.6.1, 9.6.4, 9.9.2, 9.10.3, 10.3.3, 11.2, 11.3, 13.5.1, 13.5.2, 14.1.1.4, 14.1.4, 15.1.3 Owner's Authority 1.5, 2.1.1, 2.3, 2.4, 3.4.2, 3.8.1, 3.12.10, 3.14.2, 4.1.2, 4.1.3, 4.2.4, 4.2.9, 5.2.1, 5.2.4, 5.4.1, 6.1, 6.3, 7.2.1, 7.3.1, 8.2.2, 8.3.1, 9.3.1, 9.3.2, 9.5.1, 9.6.4, 9.9.1, 9.10.2, 10.3.2, 11.1.3, 11.3.3, 11.3.10, 12.2.2, 12.3, 13.2.2, 14.3, 14.4, 15.2.7 Owner's Financial Capability 2.2.1, 13.2.2, 14.1.1.4 Owner's Liability Insurance 11.2 Owner's Relationship with Subcontractors 1.1.2, 5.2, 5.3, 5.4, 9.6.4, 9.10.2, 14.2.2 Owner's Right to Carry Out the Work 2.4, 14.2.2 Owner's Right to Clean Up 6.3 Owner's Right to Perform Construction and to Award Separate Contracts 6.1 Owner's Right to Stop the Work 2.3 Owner's Right to Suspend the Work 14.3 Owner's Right to Terminate the Contract 14.2 Ownership and Use of Drawings, Specifications and Other Instruments of Service 1.1.1, 1.1.6, 1.1.7, 1.5, 2.2.5, 3.2.2, 3.11, 3.17, 4.2.12, 5.3 Partial Occupancy or Use 9.6.6, 9.9, 11.3.1.5 Patching, Cutting and 3.14, 6.2.5 Patents 3.17 Payment, Applications for 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5, 9.6.3, 9.7, 9.8.5, 9.10. 1, 14.2.3, 14.2.4, 14.4.3 Payment, Certificates for 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9. 10. 1, 9.10.3, 13.7, 14.1.1.3, 14.2.4 Payment, Failure of 9.5.1.3, 9.7, 9.10.2, 13.6, 14.1.1.3, 14.2.1.2 Payment, Final 4.2.1, 4.2.9, 9.8.2, 9.10, 11.1.2, 11.1.3, 11.4.1, 12.3, 13.7, 14.2.4, 14.4.3 Payment Bond, Performance Bond and 7.3.7.4, 9.6.7, 9.10.3, 11.4 Payments, Progress 9.3, 9.6, 9.8.5, 9.10.3, 13.6, 14.2.3, 15.1.3 PAYMENTS AND COMPLETION 9 Payments to Subcontractors 5.4.2, 9.5.1.3, 9.6.2, 9.6.3, 9.6.4, 9.6.7, 14.2.1.2 PCB 10.3.1 Performance Bond and Payment Bond 7.3.7.4, 9.6.7, 9.10.3, 11.4 AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 7 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) Permits, Fees, Notices and Compliance with Laws Safety of Persons and Property 2.2.2, 3.7, 3.13, 7.3.7.4, 10.2.2 10.2, 10.4 PERSONS AND PROPERTY, PROTECTION OF Safety Precautions and Programs 10 3.3.1, 4.2.2, 4.2.7, 5.3, 10.1, 10.2, 10.4 Polychlorinated Biphenyl Samples, Definition of 10.3.1 3.12.3 Product Data, Definition of Samples, Shop Drawings, Product Data and 3.12.2 3.11, 3.12, 4.2.7 Product Data and Samples, Shop Drawings Samples at the Site, Documents and 3.11, 3.12, 4.2.7 3.11 Progress and Completion Schedule of Values 4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.3 9.2, 9.3.1 Progress Payments Schedules, Construction 9.3, 9.6, 9.8.5, 9.10.3, 13.6, 14.2.3, 15.1.3 3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.5.2 Project, Definition of Separate Contracts and Contractors 1.1.4 1. 1.4, 3.12.5, 3.14.2, 4.2.4, 4.2.7, 6, 8.3.1, 12.1.2 Project Representatives Shop Drawings, Definition of 4.2.10 3.12.1 Property Insurance Shop Drawings, Product Data and Samples 10.2.5, 11.3 3.11, 3.12, 4.2.7 PROTECTION OF PERSONS AND PROPERTY Site, Use of 10 3.13, 6.1.1, 6.2.1 Regulations and Laws Site Inspections 1.5, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 4.1.1, 9.6.4, 9.9. 1, 3.2.2, 3.3.3, 3.7.1, 3.7.4, 4.2, 9.4.2, 9.10.1, 13.5 10.2.2, 11.1, 11.4, 13.1, 13.4, 13.5.1, 13.5.2, 13.6, 14, Site Visits, Architect's 15.2.8, 15.4 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.5 Rejection of Work Special Inspections and Testing 3.5, 4.2.6, 12.2.1 4.2.6, 12.2.1, 13.5 Releases and Waivers of Liens Specifications, Definition of 9.10.2 1.1.6 Representations Specifications 3.2.1, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.4.2, 9.5. 1, 1.1.1,1.1.6,1.2.2,1.5,3.11,3.12.10,3.17,4.2.14 9.8.2, 9.10.1 Statute of Limitations Representatives 13.7, 15.4.1.1 2.1.1, 3.1.1, 3.9, 4.1.1, 4,2.1, 4.2.2, 4.2.10, 5.1.1, Stopping the Work 5.1.2, 13.2.1 2.3, 9.7, 10.3, 14.1 Responsibility for Those Performing the Work Stored Materials 3.3.2, 3.18, 4.2.3, 5.3, 6.1.3, 6.2,`6.3, 9.5.1, 10 6.2.1, 9.3.2, 10.2.1.2, 10.2.4 Retainage Subcontractor, Definition of 9.3.1, 9.6.2, 9.8.5, 9.9.1,_9.10.2, 9.10.3 5.1.1 Review of Contract Documents and Field Conditions SUBCONTRACTORS by Contractor 5 3.2,3.12.7, 6.1.3 Subcontractors, Work by Review of Contractor's Submittals by Owner and 1.2.2, 3.3.2, 3.12.1, 4.2.3, 5.2.3, 5.3, 5.4, 9.3.1.2, Architect 9.6.7 3.10.1, 3.10.2, 3.11, 3.12, 4.2, 5.2, 6.1.3, 9.2, 9.8.2 Subcontractual Relations Review of Shop Drawings, Product Data and 5.3, 5.4, 9.3.1.2, 9.6, 9.10, 10.2.1, 14.1, 14.2.1 Samples by Contractor Submittals 3.12 3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 7.3.7, 9.2, 9.3, Rights and Remedies 9.8, 9.9.1, 9.10.2, 9.10.3, 11.1.3 1.1.2, 2.3, 2.4,3.5, 3.7.4, 3.15.2, 4.2.6, 5.3, 5.4, 6. 1, Submittal Schedule 6.3, 7.3.1, 8.3, 9.5.1, 9.7, 10.2.5, 10.3, 12.2.2, 12.2.4, 3.10.2, 3.12.5, 4.2.7 13.4, 14, 15.4 Subrogation, Waivers of Royalties, Patents and Copyrights 6.1.1, 11.3.7 3.17 Substantial Completion Rules and Notices for Arbitration 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 15.4.1 12.2, 13.7 Init. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the / maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) Substantial Completion, Definition of 9.8.1 Substitution of Subcontractors 5.2.3, 5.2.4 Substitution of Architect 4.1.3 Substitutions of Materials 3.4.2, 3.5, 7.3.8 Sub -subcontractor, Definition of 5.1.2 Subsurface Conditions 3.7.4 Successors and Assigns 13.2 Superintendent 3.9, 10.2.6 Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.7, 8.2, 8.3.1, 9.4.2, 10, 12, 14, 15.1.3 Surety 5.4.1.2, 9.8.5, 9.10.2, 9.10.3, 14.2.2, 15.2.7 Surety, Consent of 9.10.2, 9.10.3 Surveys 2.2.3 Suspension by the Owner for Convenience 14.3 Suspension of the Work 5.4.2, 14.3 Suspension or Termination of the Contract 5.4.1.1, 14 Taxes 3.6, 3.8.2.1, 7.3.7.4 Termination by the Contractor 14.1, 15.1.6 Termination by the Owner for Cause 5.4.1.1, 14.2, 15.1.6 Termination by the Owner for Convenience 14.4 Termination of the Architect 4.`1.3 Termination of the Contractor 14.2.2 TERMINATION OR SUSPENSION OF THE CONTRACT 14 Tests and Inspections 3.1.3, 3.3.3, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 10.3.2,11.4.1, 12.2.1, 13.5 TIME 8 Time, Delays and Extensions of 3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.5, 15.2.5 Time Limits 2.1.2, 2.2, 2.4, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2, 5.2, 5.3, 5.4, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 11.1.3, 12.2, 13.5, 13.7, 14, 15.1.2, 15.4 Time Limits on Claims 3.7.4, 10.2.8, 13.7, 15.1.2 Title to Work 9.3.2, 9.3.3 Transmission of Data in Digital Form 1.6 UNCOVERING AND CORRECTION OF WORK 12 Uncovering of Work 12.1 Unforeseen Conditions, Concealed or Unknown 3.7.4, 8.3.1, 10.3 Unit Prices 7.3.3.2, 7.3.4 Use of Documents 1.1.1, 1.5, 2.2.5, 3.12.6, 5.3 Use of Site 3.13, 6.1.1, 6.2.1 Values, Schedule of 9.2, 9.3.1 Waiver of Claims by the Architect 13.4.2 Waiver of Claims by the Contractor 9.10.5, 13.4.2, 15.1.6 Waiver of Claims by the Owner 9.9.3, 9.10.3, 9.10.4, 12.2.2.1, 13.4.2, 14.2.4, 15.1.6 Waiver of Consequential Damages 14.2.4, 15.1.6 Waiver of Liens 9.10.2, 9.10.4 Waivers of Subrogation 6.1.1, 11.3.7 Warranty 3.5, 4.2.9, 9.3.3, 9.8.4, 9.9.1, 9.10.4, 12.2.2, 13.7 Weather Delays 15.1.5.2 Work, Definition of 1.1.3 Written Consent 1.5.2,3.4.2,3.7.4,3.12.8,3.14.2,4.1.2,9.3.2,9.8.5, 9.9.1, 9.10.2, 9.10.3, 11.4.1, 13.2, 13.4.2, 15.4.4.2 Written Interpretations 4.2.11, 4.2.12 Written Notice 2.3, 2.4, 3.3.1, 3.9, 3.12.9, 3.12.10, 5.2.1, 8.2.2, 9.7, 9.10, 10.2.2, 10.3, 11.1.3, 12.2.2, 12.2.4, 13.3, 14, 15.4.1 Written Orders 1.1.1, 2.3, 3.9, 7, 8.2.2, 12.1, 12.2, 13.5.2, 14.3.1, 15.1.2 AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 9 reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) (Paragraphs Deleted) ARTICLE 1 GENERAL 1. PROVISIONS § 1.1.1 THE CONTRACT DOCUMENTS The Contract Documents are enumerated in the AIA A] 3 3 Agreement between the Owner and Construction Manager as Constructor (hereinafter the Agreement) and consist of the Agreement, Conditions of the Contract (General, Supplementary and other Conditions), the Guaranteed Maximum Price Amendment, Drawings, Specifications, Addenda issued prior to execution of the Contract, other documents listed in the Agreement and Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work issued by the Architect. Unless specifically enumerated in the Agreement, the Contract Documents do not include the advertisement or invitation to bid, Instructions to Bidders, sample forms, other information furnished by the Owner in anticipation of receiving bids or proposals, the Contractor's bid or proposal, or portions of Addenda relating to bidding requirements. § 1.1.2 THE CONTRACT The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract maybe amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Contractor and the Architect or the Architect's consultants, (2) between the Owner and a Subcontractor or a Sub -subcontractor, (3) between the Owner and the Architect or the Architect's consultants or (4) between any persons or entities other than the Owner and the Contractor. The use of the term "Contractor" herein shall mean the Construction Manager. § 1.1.3 THE WORK , The term "Work" means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations. The Work may constitute the whole or a part of the Project. The Contractor acknowledges and agrees that the Contract Documents are sufficient to provide for the completion of the Work and include Work, whether or not shown or described in the Contract Documents, which reasonably may be inferred to be required or useful for the completion of the Work in accordance with applicable laws, codes, and customary standards for the construction industry. § 1.1.4 THE PROJECT The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner and by separate contractors. § 1.1.5 THE DRAWINGS The Drawings are the graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work,generally including plans, elevations, sections, details, schedules and diagrams. § 1.1.6 THE SPECIFICATIONS The Specifications are that portion of the Contract Documents consisting of the written requirements for materials, equipment, systems, standards and workmanship for the Work, and performance of related set -vices. § 1.1.7 DESIGN DOCUMENTS Design Documents are representations, in any medium of expression now known or later developed, of the tangible and intangible creative work performed by the designers under their respective employment or professional services agreements. Design Documents may include, without limitation, studies, surveys, models, sketches, drawings, specifications, and other similar materials. Ownership of any Design Documents is defined in contracts between Owner and the Architect. § 1.1.8 INITIAL DECISION MAKER The Initial Decision Maker shall be a neutral third party chosen by mutual agreement of the Owner and Contractor. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Inst. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 10 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 1.1.9 SITE The term Site refers to that portion of the property on which the Work is to be performed or which has been otherwise set aside for use by the Contractor. § 1.1.10 PUNCH LIST The term Punch List means, collectively, unfinished items of the construction of the Project, which unfinished items of construction are minor or insubstantial details of construction, mechanical adjustment or decoration remaining to be performed, the non -completion of which would not materially affect the use of the Project, and which are capable of being completed within thirty (30) days of Substantial Completion, subject to the availability of special order parts and materials. By mutual agreement of the Parties, the Punch List may also include other unfinished items that are not capable of being completed within thirty (30) days of Substantial Completion due to environmental conditions beyond the reasonable control of Contractor. § 1.1.11 NOTICE TO PROCEED The term Notice to Proceed means formal written notice to begin performing specific services or acts including Construction Phase services, Pre -Construction Phase services or any other enumerated service or act set forth in the Contract. § 1.2 CORRELATION AND INTENT OF THE CONTRACT DOCUMENTS § 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results. § 1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. § 1.2.3 Unless otherwise stated in the Contract Documents, words that have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings. § 1.3 CAPITALIZATION Terms capitalized in these General Conditions include those that are (1) specifically defined, (2) the titles of numbered articles or (3) the titles of other documents published by the American Institute of Architects. § 1.4 INTERPRETATION § 1.4.1 In the interest of brevity the Contract Documents frequently omit modifying words such as "all" and "any" and articles such as "the" and "an," but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement. § 1.4.2 In the event of conflict among the various provisions of the Contract Documents, the terms shall be interpreted in the following order of priority: 1 Modifications to the Contract .2 The Agreement (AIA A133-2009) 3 General Conditions (this AIA A201-2007) Specifications shall control over drawings, and details in drawings shall control over large-scale drawings. 1.5 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER DESIGN DOCUMENTS § 1.5.1 Provided all payments have been made to Architect in accordance with its agreement with Owner, the Design Documents are the Owner's exclusive property. The Owner owns all copyrights in and to the Design Documents. The Contractor, Subcontractors, Sub -subcontractors, and material or equipment suppliers shall not own or claim a copyright in the Design Documents. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of the Owner's reserved rights. AIA Document A201 Tn — 2007. Copyright O 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 11 reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 1.5.2 The Contractor, Subcontractors, Sub -subcontractors and material or equipment suppliers are authorized to use and reproduce the Design Documents provided to them solely and exclusively for execution of the Work. All copies made under this authorization shall bear the copyright notice, if any, shown on the Design Documents. The Contractor, Subcontractors, Sub -subcontractors, and material or equipment suppliers may not use the Design Documents on other projects or for additions to this Project outside the scope of the Work without the specific written consent of the Owner. § 1.6 TRANSMISSION OF DATA IN DIGITAL FORM If the parties intend to transmit Design Documents or any other information or documentation in digital form, they shall endeavor to establish necessary protocols governing such transmissions, unless otherwise already provided in the Contract or the Contract Documents. (Paragraphs Deleted) ARTICLE 2 1. OWNER § 2.1.1 The Owner is the entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Owner shall designate in writing a representative who shall have express authority to bind the Owner with respect to all matters requiring the Owner's approval or authorization. Except as otherwise provided in Section 4.2.1, the Architect does not have such authority. The term "Owner" means the Owner or the Owner's authorized representative. (Paragraph Deleted) § 2.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER § 2.2.1 Prior to commencement of the Work, the Contractor may request in writing that the Owner provide reasonable evidence that the Owner has made financial arrangements to fulfill the Owner's obligations under the Contract. Thereafter, the Contractor may only request such evidence if (1) the Owner fails to make payments to the Contractor as the Contract Documents require; (2) a change in the Work materially changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner's ability to make payment when due. The Owner shall furnish such evidence as a condition precedent to commencement or continuation of the Work or the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. § 2.2.2 Except for trade permits and fees that are the responsibility of the Contractor under the Contract Documents, including those required under Section 3.7.1, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities including those charges and costs related to zoning changes and environmental impact statements. § 2.2.3 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the Site. The Contractor shall be entitled to rely on the accuracy of information furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work. § 2.2.4 The Owner shall furnish information or services required of the Owner by the Contract Documents with reasonable promptness. The Owner shall also furnish any other information or services under the Owner's control and relevant to the Contractor's performance of the Work with reasonable promptness after receiving the Contractor's written request for such information or services. § 2.2.5 Unless otherwise provided in the Contract Documents, the Owner shall furnish to the Contractor one copy of the Contract Documents for purposes of making reproductions pursuant to Section 1.5.2. § 2.3 OWNER'S RIGHT TO STOP THE WORK If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 1 L reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Section 6.1.3. This right shall be in addition to, and not in limitation of, other rights of the Owner. § 2.4 OWNER'S RIGHT TO CARRY OUT THE WORK If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a ten-day period after receipt of written notice from the Owner, or such shorter time as may be reasonable under the circumstances, to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of correcting such deficiencies, including Owner's expenses and compensation for the Architect's additional services made necessary by such default, neglect or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner. (Paragraphs Deleted) ARTICLE 3 1. CONTRACTOR § 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Contractor shall be lawfully licensed, if required in the jurisdiction where the Project is located. The Contractor shall designate in writing a representative who shall have express authority to bind the Contractor with respect to all matters under this Contract. The term "Contractor" means the Contractor or the Contractor's authorized representative. § 3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. § 3.1.3 The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents either by activities or duties of the Architect in the Architect's administration of the Contract, or by tests, inspections or approvals required or performed by persons or entities other than the Contractor. The Contractor waives any rights, claims, or causes of action against Owner as a result of activities or duties of the Architect in the Architect's administration of the Contract or representations made by the Architect in the Design Documents. The Contractor acknowledges any such rights, claims, or causes of action accrue against the Architect and Conti -actor may seek redress from Architect in the event that becomes necessary. § 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR § 3.2.1 By executing the Contract, the Contractor represents that the Contractor has reviewed and understands the Contract Documents, has visited the Site and is familiar with local conditions under which the Work is to be performed, has correlated personal observations with the requirements of the Contract Documents, and has notified the Architect of and obtained clarification of any discrepancies which have become apparent during the bidding or proposal period. § 3,2.2 The Contractor must carefully study and compare the Contract Documents among themselves and further compare the Contract Documents with any other information furnished by the Owner pursuant to Section 3.2 before commencing Work at the Site and at frequent intervals during its progress. § 3.2.3 The Contractor must take field measurements and verify Site conditions, and must carefully compare such field measurements and Site conditions and other information known to the Contractor with the Contract Documents, before ordering any material or doing any Work at the Site. § 3.2.4 The Contractor must make frequent inspections during the progress of the Work to confirm that Work previously performed by the Contractor is in compliance with the Contract Documents, specifications, and applicable laws and regulations bearing on the performance of the Work and that portion of Work previously performed by the Contractor or by others are in proper condition to receive subsequent Work. § 3.2.5 If the Contractor believes that any portions of the Contract Documents do not comply with applicable laws, statutes, ordinances, building codes, and rules and regulations, or any orders by code enforcement officials or the Owner or its designees acting in the capacity of building code inspectors or Referenced Standards, the Contractor must promptly notify the Owner and the Architect of the non-compliance as provided in Section 3.2.6 and request direction before proceeding with the affected Work. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 13 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible tinder the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) § 3.2.6 The Contractor must promptly notify the Owner and the Architect in writing of any apparent errors, inconsistencies, omissions, ambiguities, construction impracticalities or code violations discovered as a result of the Contractor's review of the Contract Documents including any differences between actual and indicated dimensions, locations and descriptions, and must give the Owner and the Architect timely notice in writing of same and of any corrections, clarifications, additional Drawings or Specifications, or other information required to define the Work in greater detail or to permit the proper progress of the Work. The Contractor must provide similar notice with respect to any variance between its review of the Site and physical data and Site conditions observed. § 3.2.7 If the Contractor performs any Work involving an apparent error, inconsistency, ambiguity, construction impracticality, omission or code violation in the Contract Documents of which the Contractor is aware, or which could reasonably have been discovered by the review required by Section 3.2, without prompt written notice to the Owner and the Architect and request for correction, clarification or additional information, as appropriate, the Contractor does so at its own risk and expense and all claims relating thereafter are specifically waived. § 3.2.8 If the Contractor believes that additional cost or time is involved because of clarifications or instructions the Architect issues in response to the Contractor's notices or requests for information pursuant to Section 3.2, the Contractor shall make Claims as provided in Article 15. If the Contractor fails to perform the obligations of Section 3.2, the Contractor shall pay such costs and damages to the Owner as would have been avoided if the Contractor had performed such obligations. If the Contractor performs those obligations, the Contractor shall not be liable to the Owner or Architect for damages resulting from errors, inconsistencies or omissions in the Contract Documents, for differences between field measurements or conditions and the Contract Documents, or for nonconformities of the Contract Documents to applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities. § 3.2.9 Nothing contained in this Section 3.2 is intended to shift responsibility from the Architect to the Contractor for the design of the Project, or to require the Contractor to assume liability for the design of the Project. § 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES § 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor's best skill and attention. The Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters. If the Contract Documents give specific instructions concerning construction means, methods, techniques, sequences or procedures, the Contractor shall evaluate the jobsite safety thereof and, except as stated below, shall be fully and solely responsible for the jobsite safety of such means, methods, techniques, sequences or procedures. If the Contractor determines that such means, methods, techniques, sequences or procedures may not be safe, the Contractor shall give timely written notice to the Owner and Architect and shall not proceed with that portion of the Work without further written instructions from the Architect and Owner. If the Contractor is then instructed to proceed with the required means, methods, techniques, sequences or procedures without acceptance of changes proposed by the Contractor, the Owner shall be solely responsible for any loss or damage arising solely from those Owner -required means, methods, techniques, sequences or procedures. § 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor's employees, Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for, or on behalf of, the Contractor or any of its Subcontractors. § 3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work. § 3.4 LABOR AND MATERIALS § 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. Contractor must comply with all applicable hiring preference and prevailing wage provisions of Title 18, Chapter 2, Montana Code Annotated. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 14 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 3.4.2 Except in the case of minor changes in the Work authorized by the Architect in accordance with Sections 3.12.8 or 7.4, the Contractor may make substitutions only with the written consent of the Owner, after evaluation by the Architect and in accordance with a Change Order or Construction Change Directive. § 3.4.3 The Contractor shall enforce strict discipline and good order among the Contractor's employees and other persons carrying out the Work. The Contractor shall not permit employment of unfit persons or persons not properly skilled in tasks assigned to them. Persons permitted to perform Work under Contractor or any Subcontractor or Sub - Subcontractor shall meet all employment eligibility, safety training, security or drug/alcohol testing requirements required by law or by Owner. Any person not complying with all such requirements shall be immediately removed from the Site. § 3.5 WARRANTY §3.5.1 The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be free from defects, except for those inherent in the quality of the Work the Contract Documents require or permit. Work, materials, or equipment not conforming to these requirements may be considered defective. The Contractor's warranty excludes remedy for damage or defect caused by abuse, alterations to the Work not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. If required by the Architect, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. §3.5.2 The Contractor's general warranty and any additional or special warranties are not limited by the Contractor's obligations to specifically correct defective or nonconforming Work as provided in Article 12, nor are they limited by any other remedies provided in the Contract Documents. The Contractor shall also be liable for any damage to property or persons (including death) including direct damages relating to any breach of the Contractor's general warranty or any additional or special warranties required by the Contract Documents. §3.5.3 The Contractor must furnish all special warranties required by the Contract Documents to the Owner no later than ten (10) days after Substantial Completion. The Owner may require additional special warranties in connection with the approval of "Or -Equals" or Substitutions, Allowance items, Work that is defective or nonconforming, or the acceptance of nonconforming Work pursuant to Article 12. § 3.6 TAXES The Contractor shall pay sales, consumer, use and similar taxes, including unemployment compensation taxes, for the Work provided by the Contractor that are legally enacted when bids are received or negotiations concluded, whether or not yet effective or merely scheduled to go into effect. The Contractor shall pay all state and federal taxes levied on its business, income,' or property, and shall make all contributions for Social Security and other wage or payroll taxes. The Contractor shall be solely responsible for such payments, and shall indemnify the Owner and hold it harmless for any assessment and payment of same. § 3.7 PERMITS, FEES, NOTICES AND COMPLIANCE WITH LAWS § 3.7.1 Unless otherwise provided in the Contract Documents, the Owner shall secure and pay for the building permits and fees as well as for other permits, fees, licenses, and inspections by government agencies necessary for proper execution and completion of the Work that are customarily secured after execution of the Contract and legally required at the time bids are received or negotiations concluded. § 3.7.2 The Contractor shall comply with and give notices required by applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities applicable to performance of the Work. § 3.7.3 If the Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Contractor shall assume appropriate responsibility for such Work and shall bear the costs attributable to correction. § 3.7.4 If the Contractor encounters conditions at the Site that are (1) subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, that differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, the Contractor shall promptly AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 15 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This documentwas produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) provide written notice to the Owner and the Architect before conditions are disturbed and in no event later than seven days after first observance of the conditions. The Architect will promptly investigate such conditions and, if the Architect determines that they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the Site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall promptly notify the Owner and Contractor in writing, stating the reasons. If either party disputes the Architect's determination or recommendation, that party may proceed as provided in Article 15. § 3.7.5 If, in the course of the Work, the Contractor encounters human remains or recognizes the existence of burial markers, archaeological sites or wetlands not indicated in the Contract Documents, the Contractor shall immediately suspend any operations that would affect them and shall notify the Owner and Architect. Upon receipt of such notice, the Owner shall promptly take any action necessary to obtain governmental authorization required to resume the operations. The Contractor shall continue to suspend such operations until otherwise instructed by the Owner but shall continue with all other operations that do not affect those remains or features. Requests for adjustments in the Contract Sum and Contract Time arising from the existence of such remains or features may be made as provided in Article 15. § 3.8 ALLOWANCES § 3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by allowances shall be supplied for such amounts and by such persons or entities as the Owner may direct, but the Contractor shall not be required to employ persons or entities to whom the Contractor has reasonable objection. § 3.8.2 Unless otherwise provided in the Contract Documents, .1 Allowances shall cover the cost to the Contractor of materials and equipment delivered at the Site and all required taxes, less applicable trade discounts; .2 Contractor's costs for unloading and handling at the Site, labor, installation costs, overhead, profit and other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but not in the allowances; and .3 Whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the allowances under Section 3.8.2.1 and (2) changes in Contractor's costs under Section 3.8.2.2. § 3.8.3 Materials and equipment under an allowance shall be selected by the Owner with reasonable promptness. § 3.9 SUPERINTENDENT § 3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance at the Project Site during performance of the Work. The superintendent shall represent the Contractor, and communications given to the superintendent shall be as binding as if given to the Contractor. The superintendent must provide his or her email address, cell phone number and pager number to Owner and Architect and must be available to be contacted during all business hours, and outside of business hours in the event of an emergency. § 3.9.2 The Contractor, as soon as practicable after award of the Contract, shall furnish in writing to the Owner through the Architect the name and qualifications of a proposed superintendent. The Architect may reply within 14 days to the Contractor in writing stating (1) whether the Owner or the Architect has reasonable objection to the proposed superintendent or (2) that the Architect requires additional time to review. Failure of the Architect to reply within the 14 day period shall constitute notice of no reasonable objection. § 3.9.3 The Contractor shall not employ a proposed superintendent to whom the Owner or Architect has made reasonable and timely objection. The Contractor shall not change the superintendent without the Owner's consent, which shall not unreasonably be withheld or delayed. § 3.10 CONTRACTOR'S CONSTRUCTION SCHEDULES § 3.10.1 The Contractor, promptly with the Owner's acceptance of the Guaranteed Maximum Price, shall prepare and submit for the Owner's and Architect's approval a Contractor's construction schedule for the Work ("Construction AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 16 reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) Schedule"). The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. Thereafter, the Contractor shall prepare and update the Construction Schedule on a monthly basis ("Current Construction Schedule"), if not more frequently at the Contractor's discretion, to be submitted to the Owner with each Application for Payment. § 3.10.2 The Contractor shall prepare a submittal schedule, thirty (30) days after Owner gives Contractor Notice to Proceed, and thereafter as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Owner's and Architect's approval. The Owner's and Architect's approval shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor's Construction Schedule, and (2) allow the Owner and Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals. § 3.10.3 The Contractor shall perform the Work in accordance with the most recent schedules approved by the Owner and Architect but in any event not exceed the Contract Time. § 3.10.4 The Construction Schedule shall be in a detailed format satisfactory to the Owner and the Architect and shall also: (1) provide a graphic representation of all activities and events that will occur during performance of the Work; (2) identify each phase of construction and occupancy; and (3) set forth dates that are critical in ensuring the timely and orderly completion of the Work in accordance with the requirements of the Contract Documents (hereinafter referred to as Milestone Dates), including scheduling all government inspections. Upon review and acceptance by the Owner and the Architect of the Milestone Dates, the construction schedule shall be deemed part of the Contract. If not accepted, the Construction Schedule shall be promptly revised by the Contractor in accordance with the recommendations of the Owner and the Architect and resubmitted for acceptance. The Contractor shall monitor the progress of the Work for conformance with the requirements of the Construction Schedule and shall promptly advise the Owner of any delays or potential delays. The accepted construction schedule shall be updated to reflect actual conditions as set forth in Section 3.10.1 or if requested by either the Owner or the Architect. In the event any progress report indicates any delays, the Contractor shall propose an affirmative plan to correct the delay, including overtime and/or additional labor, if necessary. In no event shall any progress report constitute an adjustment in the Contract Time, any Milestone Date or the Contract Sum unless any such adjustment is agreed to by the Owner and authorized pursuant to Change Order. § 3.11 DOCUMENTS AND SAMPLES AT THE SITE The Contractor shall maintain at the Site for the Owner one copy of the Drawings, Specifications, Addenda, Current Construction Schedule, Change Orders and other Modifications, in good order and marked currently to indicate field changes and selections made during construction, and one copy of approved Shop Drawings, Product Data, Samples and similar required submittals. The Contractor shall display a Current Construction Schedule at the site for reference and reliance by the Owner and Architect. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed. If any of the items submitted pursuant to this Section 3.11 are not reasonably acceptable to the Architect or the Owner, Contractor shall correct and resubmit the item(s). § 3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES § 3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the Work by the Contractor or a Subcontractor, Sub -subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work. § 3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. § 3.12.3 Samples are physical examples that illustrate materials, equipment or workmanship and establish standards by which the Work will be judged. § 3.12.4 Shop Drawings, Product Data, Samples and similar submittals are not Contract Documents. Their purpose is to demonstrate the way by which the Contractor proposes to conform to the information given and the design AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 17 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals. Review by the Architect is subject to the limitations of Section 4.2.7. Informational submittals upon which the Architect is not expected to take responsive action may be so identified in the Contract Documents. Submittals that are not required by the Contract Documents may be returned by the Architect without action. § 3.12.5 The Contractor shall review for compliance with the Contract Documents, approve and submit to the Architect Shop Drawings, Product Data, Samples and similar submittals required by the Contract Documents in accordance with the submittal schedule approved by the Architect or, in the absence of an approved submittal schedule, with reasonable promptness and in such sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. The Contractor must provide the Owner and the Architect with copies of all submittals made to regulatory agencies. § 3.12.6 By submitting Shop Drawings, Product Data, Samples and similar submittals, the Contractor represents to the Owner and Architect that the Contractor has (1) reviewed and approved them, (2) determined and verified materials, field measurements and field construction criteria related thereto, or will do so and (3) checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents. § 3.12.7 The Contractor shall perform no portion of the Work for which the Contract Documents require submittal and review of Shop Drawings, Product Data, Samples or similar submittals until the respective submittal has been approved by the Architect. The Contractor must correct at its cost, and without any adjustment in Contract Time, any Work the correction of which is required due to the Contractor's failure to obtain approval of a submittal required to have been obtained prior to proceeding with the Work, including, but not limited to, correction of any conflicts in the Work resulting from such failure. § 3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved of responsibility for deviations from requirements of the Contract Documents by the Architect's approval of Shop Drawings, Product Data, Samples or similar submittals unless the Contractor has specifically informed the Architect in writing of such deviation at the time of submittal and (1) the Architect has given written approval to the specific deviation as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples or similar submittals by the Architect's approval thereof. § 3.12.9 The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data, Samples or similar submittals, to revisions other than those requested by the Architect on previous submittals. In the absence of such written notice, the Architect's approval of a resubmission shall not apply to such revisions. § 3.12.10 The Contractor shall not be required to provide professional services that constitute the practice of architecture or engineering unless such services are specifically required by the Contract Documents for a portion of the Work or unless the Contractor needs to provide such services in order to carry out the Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. The Contractor shall not be required to provide professional services in violation of applicable law. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of the Contractor by the Contract Documents, the Owner and the Architect will specify all performance and design criteria that such services must satisfy. The Contractor shall cause such services or certifications to be provided by a properly licensed design professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings and other submittals prepared by such professional. Shop Drawings and other submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to the Architect. The Owner and the Architect shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications and approvals performed or provided by such design professionals, provided the Owner and Architect have specified to the Contractor all performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10, the Architect will review, approve or take other appropriate action on submittals only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. The Contractor shall not be responsible for the adequacy of the performance and design criteria specified in the Contract Documents. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 18 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) § 3.13 USE OF SITE § 3.13.1 The Contractor shall confine operations at the Site to areas permitted by applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities and the Contract Documents and shall not unreasonably encumber the Site with materials or equipment. Only materials and equipment which are to be used in the Work shall be brought to and stored on the Project Site by the Contractor. After equipment is no longer required for the Work, it shall be promptly removed from the Project Site. § 3.13.2 Except as may be specifically provided in the Contract Documents, the Contractor shall provide all necessary temporary facilities, including power, water, sanitation, scaffolding, storage, and reasonable security. If Owner makes any such facilities available to Contractor, it is without representation or warranty as to their adequacy for Contractor's use, and Contractor shall indemnify, defend, and hold Owner harmless from and against any claims arising out of Contractor's use of such facilities. § 3.13.3 The Contractor shall ensure that the Work, at all times, is performed in a manner that affords reasonable access, both vehicular and pedestrian, to the site of the Work and all adjacent areas. The Work shall be performed, to the fullest extent reasonably possible, in such a manner that public areas adjacent to the site of the Work shall be free from all debris, building materials and equipment likely to cause hazardous conditions. Without limitation of any other provision of the Contract Documents, Contractor shall not interfere with the occupancy or beneficial use of (1) any areas and buildings adjacent to the site of the Work or (2) the Building in the event of partial occupancy, as more specifically described in Paragraph 9.9, without prior approval of the Owner and Architect. § 3.13.4 Without prior approval of the Owner, the Contractor shall not permit any workers to use any Owner's facilities at the Project site, including, without limitation, lavatories, toilets, entrances and parking areas other than those designated by the Owner. § 3.13.5 The Contractor shall, for the duration of this Agreement, maintain all areas used by it in performance of the Contract free from excessive dust as reasonably determined and directed by the Architect or the Owner, and shall comply with the OSHA standards and those of all other regulatory agencies, statutes and laws. Industry accepted methods of dust control suitable for the areas involved will be permitted, where such is in compliance with the foregoing and with the approval of the Architect and the Owner. No separate payment will be made for dust control beyond what may be previously approved by Owner as a General Condition Cost or as included as a subcontract bid package item. § 3.13.6 The Contractor shall perform all work in strict conformity with all applicable laws, rules and regulations relating to pollution of any land, stream, and the atmosphere. The Contractor shall, at its expense, provide suitable facilities to prevent the introduction of any substances or materials onto the land, or into any stream, river, lake or other body of water including groundwater or the atmosphere. §3.13.7 The Contractor shall not permit or suffer the introduction or use of any intoxicants, including alcohol or illegal drugs, upon the Site. § 3.13.8 In the event that any items of archeological or historical value are discovered by Contractor or any of its Subcontractors or any of their representatives or employees, the Contractor shall immediately notify the Owner and await its decision before proceeding with any work. Any item found shall not be the Contractor's property and shall be promptly delivered to the Owner. § 3.14 CUTTING AND PATCHING § 3.14.1 The Contractor shall be responsible for cutting, fitting or patching required to complete the Work or to make its parts fit together properly. All areas requiring cutting, fitting and patching shall be restored to the condition existing prior to the cutting, fitting and patching, unless otherwise required by the Contract Documents. § 3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of the Owner or separate contractors by cutting, patching or otherwise altering such construction, or by excavation. The Contractor shall not cut or otherwise alter such construction by the Owner or a separate contractor except with written consent of the Owner and of such separate contractor; such consent shall not be unreasonably withheld. The Contractor shall not unreasonably withhold from the Owner or a separate contractor the Contractor's consent to cutting or otherwise altering the Work. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 19 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) § 3.15 CLEANING UP, WORK HOURS AND NOISE § 3.15.1 Work will be performed in accordance with the Contract Documents and the Bozeman Municipal Code or other applicable law governing the Contractor's performance of the Work. No delays resulting from compliance with applicable laws or regulations may form the basis for any claim by the Contractor for delay damages or additional compensation or for any extensions of the Contract Time. The Contractor must not permit work outside of hours established in the Contract Documents on a Saturday, Sunday or other City, State or federal holiday without the written consent of the Owner, given after prior written notice to the Owner and Architect; such consent, if given, may be conditioned upon payment by the Contractor of the Owner's, Architect's and any other applicable consultants' additional costs and fees, testing or regulatory agency costs incurred in monitoring such off -hours Work. The Contractor must notify the Owner as soon as possible if Work must be performed outside such times in the interest of the safety and protection of persons or property at the Site or adjacent thereto, or in the event of an emergency. In no event shall the Contractor permit Work to be performed at the Site without the presence of the Contractor's superintendent or person responsible for the protection of persons and property at the Site and compliance with all applicable laws and regulations, if different from the superintendent. § 3.15.2 The Contractor must comply with the Bozeman Municipal Code, (Chpt. 16, Article 6) (Noise) and any successor or substitute provisions covering the regulation of noise. It is the duty of the Contractor to familiarize itself with those provisions and perform the Work in compliance with those provisions. § 3.15.3 The Contractor must keep the Site and adjacent areas free from accumulation of waste materials or rubbish caused by operations under the Contract on a daily basis, and must keep tools, construction equipment, machinery and surplus materials suitably stored when not in use. If the Contractor fails to do so in a manner reasonably satisfactory to the Owner or the Architect within forty-eight (48) hours after notice or as otherwise required by the Contract Documents, the Owner may clean the Site and back charge the Contractor for all costs associated with the cleaning.At completion of the Work, the Contractor shall remove waste materials, rubbish, the Contractor's tools, construction equipment, machinery and surplus materials from and about the Project. (Paragraph Deleled) § 3.16 ACCESS TO WORK The Contractor shall provide the Owner and Architect access to the Work in preparation and progress wherever located. § 3.17 ROYALTIES, PATENTS AND COPYRIGHTS The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims for infringement of copyrights and patent rights and shall hold the Owner and Architect harmless from loss on account thereof, but shall not be responsible for such defense or loss when a particular design, process or product of a particular manufacturer or manufacturers is required by the Contract Documents, or where the copyright violations are contained in Drawings, Specifications or other documents prepared by the Owner or Architect. However, if the Contractor has reason to believe that the required design, process or product is an infringement of a copyright or a patent, the Contractor shall be responsible for such loss unless such information is promptly furnished to the Architect. § 3.18 INDEMNIFICATION § 3.18.1 To the fullest extent permitted by law the Contractor shall release and shall indemnify, defend, and hold harmless the Owner, Architect, Architect's consultants, and agents and employees of any of them (the "Indemnitees") from and against claims, damages, losses and expenses, including but not limited to attorneys' fees, liabilities (including liability where activity is inherently or intrinsically dangerous) or damages of whatever kind or nature connected therewith and including claims for loss of productivity, claims for additional storage and handling charges, claims for escalation of the cost of labor and materials, claims for home office overhead, liens against funds, and claims related to the removal, handling or use of hazardous materials that may be asserted against, recovered from or suffered by the City occasioned by, growing or arising out of or resulting from or in any way related to: (i) the negligent, reckless, of- intentional misconduct of the Contractor; or (ii) any negligent, reckless, of - intentional misconduct of any of the Contractor's subcontractors, suppliers, or agents; provided that the Construction Manager shall not be required to indemnify the Owner, Architect, Architect's consultants, of- the agents and employees of them for damages arising out of bodily injury to persons or damage to property caused by or resulting AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 20 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the / maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) from negligence of the Owner, its agents, officers or employees. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity that would otherwise exist as to an Indemnitee. Contractor's indemnity under this Section 3.18 shall be without regard to and without any right to contribution from any insurance maintained by Owner or Architect. § 3.18.2 In claims against any person or entity indemnified under this Section 3.18 by an employee of the Contractor a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under Section 3.18.1 shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers' compensation acts, disability benefit acts or other employee benefit acts. (Parag)-aph Deleted) § 3.18.3 Should any Indemnitee be required to bring an action against the Contractor to assert its right to defense or indemnification under this Agreement or under the Contractor's applicable insurance policies required by the Contract the Indemnitee shall be entitled to recover reasonable costs and attorney fees incurred in asserting its right to indemnification or defense but only if a court of competent jurisdiction determines the Contractor was obligated to defend the claim(s) or was obligated to indemnify the Indemnitee for a claim(s) or any portion(s) thereof. § 3.18.4 The obligations of this Section 3.18 shall survive termination of the Contract and completion of the Project. ARTICLE 4 1. ARCHITECT § 4.1.1 Use of the term "Architect" in the Agreement refers to the Design Consultant for the Project as described in the Solicitation for Statements of Qualification (RFQ) and Proposals (RFP) for General Contractor/Construction Manager Services for the Bozeman Sports Park Project published on March 27, 2016 and April 3, 2016. The Architect is referred to throughout the Contract Documents as if singular in number. § 4.1.2 Duties, responsibilities and limitations of authority of the Architect as set forth in the Contract Documents shall not be restricted, modified or extended without written consent of the Owner, Contractor and Architect. Consent shall not be unreasonably withheld. § 4.1.3 If the employment of the Architect is terminated, the Owner shall employ a successor architect whose status under the Contract Documents shall be that of the Architect. § 4.2 ADMINISTRATION OF THE CONTRACT § 4.2.1 The Architect will provide administration of the Contract as described in the Contract Documents and will be an Owner's representative during construction until the date the Architect issues the final Certificate for Payment. The Architect will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents. § 4.2.2 The Architect will visit the Site at intervals appropriate to the stage of construction, or as otherwise agreed with the Owner, to become generally familiar with the progress and quality of the portion of the Work completed, and to determine in general if the Work observed is being performed in a manner indicating that the Work, when fully completed, will be in accordance with the Contract Documents. The Architect will not have control over, charge of, or responsibility for, the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, since these are solely the Contractor's rights and responsibilities tinder the Contract Documents, except as provided in Section 3.3.1. § 4.2.3 On the basis of the site visits, the Architect will keep the Owner reasonably informed about the progress and quality of the portion of the Work completed, and report to the Owner (1) known deviations from the Contract Documents and from the most recent Construction Schedule submitted by the Contractor, and (2) defects and deficiencies observed in the Work. The Architect will not be responsible for the Contractor's failure to perform the Work in accordance with the requirements of the Contract Documents. The Architect will not have control over or charge of and will not be responsible for acts or omissions of the Contractor, Subcontractors, or their agents or employees, or any other persons or entities performing portions of the Work. Init. AIA Document A20111 — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties, Unauthorized 21 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will he prosecuted to the. t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) § 4.2.4 COMMUNICATIONS FACILITATING CONTRACT ADMINISTRATION The Owner and Contractor shall endeavor to include the Architect in communications about matters arising out of or relating to the aspects of the Contract which involve the Architect. Communications by and with the Architect's consultants shall be through the Architect. Communications by and with Subcontractors and material suppliers shall be through the Contractor. Communications by and with separate contractors shall be through the Owner. § 4.2.5 Based on the Architect's evaluations of the Contractor's Applications for Payment, the Architect will review and certify the amounts due the Contractor and will issue Certificates for Payment in such amounts. § 4.2.6 The Architect has authority to reject Work that does not conform to the Contract Documents. Whenever the Architect considers it necessary or advisable, the Architect will have authority to require inspection or testing of the Work in accordance with Sections 13.5.2 and 13.5.3, whether or not such Work is fabricated, installed or completed. However, neither this authority of the Architect nor a decision made in good faith either to exercise or not to exercise such authority shall give rise to a duty or responsibility of the Architect to the Contractor, Subcontractors, material and equipment suppliers, their agents or employees, or other persons or entities performing portions of the Work. § 4.2.7 The Architect will review and approve, or take other appropriate action upon, the Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. The Architect's action will be taken in accordance with the submittal schedule approved by the Architect or, in the absence of an approved submittal schedule, with reasonable promptness while allowing sufficient time in the Architect's professional judgment to permit adequate review. Review of such submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the Contractor as required by the Contract Documents. The Architect's review of the Contractor's submittals shall not relieve the Contractor of the obligations under Sections 3.3, 3.5 and 3.12. The Architect's review shall not constitute approval of safety precautions or, unless otherwise specifically stated by the Architect, of any construction means, methods, techniques, sequences or procedures. The Architect's approval of a specific item shall not indicate approval of an assembly of which the item is a component. § 4.2.8 The Architect will prepare Change Orders and Construction Change Directives, and may authorize minor changes in the Work as provided in Section 7.4. The Architect will investigate and make determinations and recommendations regarding concealed and unknown conditions as provided in Section 3.7.4. § 4.2.9 The Architect will conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion pursuant to Section 9.8; receive and forward to the Owner, for the Owner's review and records, written warranties and related documents required by the Contract and assembled by the Contractor pursuant to Section 9.10; and issue a final Certificate for Payment pursuant to Section 9.10. § 4.2.10 If the Owner and Architect agree, the Architect will provide one or more project representatives to assist in carrying out the Architect's responsibilities at the Site. The duties, responsibilities and limitations of authority of such project representatives shall be as set forth in an exhibit to be incorporated in the Contract Documents. § 4.2.11 The Architect will interpret matters concerning performance of the Contractor under, and requirements of, the Contract Documents on written request of either the Owner or Contractor. The Architect's response to such requests will be made in writing within any time limits agreed upon or otherwise with reasonable promptness. § 4.2.12 Interpretations and decisions of the Architect will be consistent with the intent of, and reasonably inferable from, the Contract Documents and will be in writing or in the form of drawings. § 4.2.13 Decisions on matters relating to aesthetic effect will be mutually agreed upon between Owner and Architect. § 4.2.14 The Architect will review and respond to requests for information about the Contract Documents. The Architect's response to such requests will be made in writing within any time limits agreed upon or otherwise with AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 22 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) reasonable promptness. If appropriate, the Architect will prepare and issue supplemental Drawings and Specifications in response to the requests for information. (Paragraphs Deleted) ARTICLE 5 1. SUBCONTRACTORS § 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the Work at the site. The term "Subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term "Subcontractor" does not include a separate contractor or subcontractors of a separate contractor. § 5.1.2 A Sub -subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the Site. The term "Sub -subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Sub -subcontractor or an authorized representative of the Sub - subcontractor. § 5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK § 5.2.1 Unless otherwise stated in the Contract Documents or the bidding requirements, the Contractor, as soon as practicable after award of the Contract, shall furnish in writing to the Owner through the Architect the names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each principal portion of the Work. The Architect may reply within 14 days to the Contractor in writing stating (1) whether the Owner or the Architect has reasonable objection to any such proposed person or entity or (2) that the Architect requires additional time for review. Failure of the Owner or Architect to reply within the 14 -day period shall constitute notice of no reasonable objection. If in compliance with the terms and conditions of this Contract any Subcontractors are changed, the Contractor shall update this list throughout the Project and keep Owner and the Architect advised of any new Subcontractors employed. § 5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner or Architect has made reasonable and timely objection. The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable objection. § 5.2.3 If the Owner or Architect has reasonable objection to a person or entity proposed by the Contractor, the Contractor shall propose another to whom the Owner or Architect has no reasonable objection. If the proposed but rejected Subcontractor met all criteria set forth in the Contract Documents and was reasonably capable of performing the Work, the Contract Sum and Contract Time shall be increased or decreased by the difference, if any, occasioned by such change, and an appropriate Change Order shall be issued before commencement of the substitute Subcontractor's Work. However, no increase in the Contract Sum or Contract Time shall be allowed for such change unless the Contractor has acted promptly and responsively in submitting names as required. § 5.2.4 The Contractor shall not substitute a Subcontractor, person or entity previously selected without written consent of the Owner and the Architect. The Contractor shall notify the Owner and the Architect of any proposed substitution of Subcontractor a minimum of ten (10) days prior to the proposed change. Owner reserves the ability to not consent to a Subcontractor which is a "related party" as set forth in Section 6.10 of the AIA A133 Agreement between the Owner and Construction Manager as Constructor. § 5.3 SUBCONTRACTUAL RELATIONS § 5.3.1 By appropriate written agreement, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities, including the responsibility for safety of the Subcontractor's Work, which the Contractor, by these Documents, assumes toward the Owner and Architect. Each subcontract agreement shall preserve and protect the rights of the Owner and Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights, remedies and redress against the Contractor that the Contractor, by the Contract Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with Sub -subcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract Documents to which the Subcontractor AIA Document A201 T" — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 23 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) will be bound, and, upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of the proposed subcontract agreement that may be at variance with the Contract Documents. Subcontractors will similarly make copies of applicable portions of such documents available to their respective proposed Sub - subcontractors. § 5.3.2 All agreements with Subcontractors shall be substantially similar to the Contractor's standard form of subcontract, shall require the Subcontractor to abide by the terms of this Contract, and shall specifically provide that the Owner is an intended third party beneficiary of such subcontract. This Section 5.3.2 shall not be construed as granting any rights to a Subcontractor for payment from Owner. § 5.4 CONTINGENT ASSIGNMENT OF SUBCONTRACTS § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor in writing; and .2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract. When the Owner accepts the assignment of a subcontract agreement, the Owner assumes the Contractor's rights and obligations under the subcontract. § 5.4.2 Upon such assignment, if the Work has been suspended for more than thirty (30) days, the Subcontractor's compensation shall be equitably adjusted for increases in cost resulting from the suspension. § 5.4.3 Upon such assignment to the Owner under this Section 5.4, the Owner may further assign the subcontract to a successor contractor or other entity. If the Owner assigns the subcontract to a successor contractor or other entity, the Owner shall nevertheless remain legally responsible for all of the successor contractor's obligations under the subcontract. (Paragraph Deleted) § 5.4.4 Each Subcontract shall specifically provide that the Owner shall only be responsible to the Subcontractor for those obligations of the Contractor which accrue subsequent to the Owner's exercise of any rights under this Section 5.4. (Paragraph Deleted) ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE 1. CONTRACTORS § 6.1.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner's own forces, and to award separate contracts in connection with other portions of the Project or other construction or operations on the Site under Conditions of the Contract identical or substantially similar to these including those portions related to insurance and waiver of subrogation. If the Contractor claims that delay or additional cost is involved because of such action by the Owner, the Contractor shall make such Claim as provided in Article 15. § 6.1.2 When separate contracts are awarded for different portions of the Project or other construction or operations on the Site, the term "Contractor" in the Contract Documents in each case shall mean the Contractor who executes each separate Owner -Contractor Agreement. § 6.1.3 The Owner shall provide for coordination of the activities of the Owner's own forces and of each separate contractor with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with other separate contractors and the Owner in reviewing their construction schedules. The Contractor shall make any revisions to the Construction Schedule deemed necessary after a joint review and mutual agreement. The construction schedules shall then constitute the Construction Schedule to be used by the Contractor, separate contractors and the Owner until subsequently revised. § 6.1.4 Unless otherwise provided in the Contract Documents, when the Owner performs construction or operations related to the Project with the Owner's own forces, the Owner shall be deemed to be subject to the same obligations AIA Document A201 TM — 2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American (nit. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 24 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) and to have the same rights that apply to the Contractor under the Conditions of the Contract, including, without excluding others, those stated in Article 3, this Article 6 and Articles 10, 11 and 12. § 6.2 MUTUAL RESPONSIBILITY § 6.2.1 The Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities, and shall connect and coordinate the Contractor's construction and operations with theirs as required by the Contract Documents. § 6.2.2 If part of the Contractor's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Contractor so to report shall constitute an acknowledgment that the Owner's or separate contractor's completed or partially completed construction is fit and proper to receive the Contractor's Work, except as to defects not then reasonably discoverable. § 6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs that are payable to a separate contractor because of the Contractor's delays, improperly timed activities or defective construction. The Owner shall be responsible to the Contractor for costs the Contractor incurs because of a separate contractor's delays, improperly timed activities, damage to the Work or defective construction. § 6.2.4 The Contractor shall promptly remedy damage the Contractor causes to completed or partially completed construction or to property of the Owner or separate contractors as provided in Section 10.2.5. § 6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Contractor in Section 3.14. § 6.2.6 If a Subcontractor or separate contractor initiates legal or other proceedings against the Owner on account of damage alleged to have been caused by the Contractor or its employees, agents, or subcontractors, the Owner shall notify the Contractor who shall defend such proceedings at its own expense, and if judgment or award against the Owner arises therefrom, the Contractor shall pay or satisfy it and shall reimburse the Owner for attorneys' fees and court or other costs which the Owner has incurred over and above those paid for directly by the Contractor. § 6.3 OWNER'S RIGHT TO CLEAN UP If a dispute arises among the Contractor, separate contractors and the Owner as to the responsibility under their respective contracts for maintaining the Site and surrounding area free from waste materials and rubbish, the Owner may clean up and the Architect will allocate the cost among those responsible. (Paragraphs Deleted) ARTICLE 7 CHANGES IN THE . WORK § 7.1.1 Changes in the Work may be accomplished after execution of the Contract, and without invalidating the Contract, by Change Order, Construction Change Directive or order for a minor change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the Contract Documents. § 7.1.2 A Change Order shall be based upon agreement among the Owner, Contractor and Architect; a Construction Change Directive requires agreement by the Owner and Architect and may or may not be agreed to by the Contractor; an order for a minor change in the Work may be issued by the Architect alone. § 7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents, and the Contractor shall proceed promptly, unless otherwise provided in the Change Order, Construction Change Directive or order for a minor change in the Work. § 7.2 CHANGE ORDERS § 7.2.1 A Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect stating their agreement upon all of the following: .1 The change in the Work; .2 The amount of the adjustment, if any, in the Contract Sum; and AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIAO Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 25 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) .3 The extent of the adjustment, if any, in the Contract Time. § 7.2.2 Change Proposals. The Contractor must submit change proposals covering a contemplated Change Order within ten (10) days after request of the Owner, or the Architect or within ten (10) days of the event giving rise to the Contractor's claim for a change in the Contract Sum or Contract Time, unless a different time period is agreed to by the Parties. Unless agreed to in writing by the Owner, no increase in the Contract Sum or extension of the Contract Time will be allowed the Contractor for the cost or time involved in making change proposals. Change proposals will define or confirm in detail the Work which is proposed to be added, deleted, or changed and must include any adjustment which the Contractor believes to be necessary in (i) the Contract Sum, or (ii) the Contract " Time. Any proposed adjustment must include detailed documentation including but not limited to: cost, properly itemized and supported by sufficient substantiating data to permit evaluation including cost of labor, materials, supplies and equipment, rental cost of machinery and equipment, and additional bond cost. The Owner may, at its option, instruct the Contractor to proceed with the Work involved in the change proposal in accordance with this Section 7.2.2 without accepting the change proposal in its entirety. § 7.2.3 If the Owner determines that a change proposal is appropriate, the Architect will prepare and submit a request for a Change Order or contract amendment providing for an appropriate adjustment in the Contract Sum or Contract Time, or both, for further action by the Owner. No such change is effective until the Owner and Architect sign the Change Order. § 7.3 CONSTRUCTION CHANGE DIRECTIVES § 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect (after having been approved in writing by the Owner), directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly. § 7.3.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order. § 7.3.3 If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall be based on one of the following methods: .1 Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation; .2 Unit prices stated in the Contract Documents or subsequently agreed upon; .3 Cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee; or .4 As provided in Section 7.3.7. § 7.3.4 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities originally contemplated are materially changed in a proposed Change Order or Construction Change Directive so that application of such unit prices to quantities of Work proposed will cause substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably adjusted. § 7.3.5 Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved and advise the Architect of the Contractor's agreement or disagreement with the method, if any, provided in the Construction Directive for determining the proposed adjustment in the Contract Sum or Contract Time. § 7.3.6A Construction Change Directive signed by the Contractor indicates the Contractor's agreement therewith, including adjustment in Contract Sum and Contract Time or the method for determining them. Such agreement shall be effective immediately and shall be recorded as a Change Order. § 7.3.7 If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract Sum, the Owner and the Architect shall determine the method and the adjustment on the basis of reasonable expenditures AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIAc Document is protected by U.S. Copyright Law and International Treaties, Unauthorized 26 reproduction or distribution of this AIAO Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) and savings of those performing the Work attributable to the change, including, in case of an increase in the Contract Sum, an amount for overhead and profit as set forth in the Agreement, or if no such amount is set forth in the Agreement, a reasonable amount. In such case, and also under Section 7.3.3.3, the Contractor shall keep and present, in such form as the Architect may prescribe, an itemized accounting together with appropriate supporting data. Unless otherwise provided in the Contract Documents, costs for the purposes of this Section 7.3.7 shall be limited to the following: .1 Costs of labor, including social security, old age and unemployment insurance, fringe benefits required by agreement or custom, and workers' compensation insurance; .2 Costs of materials, supplies and equipment, including cost of transportation, whether incorporated or consumed; .3 Rental costs of machinery and equipment, exclusive of hand tools, whether rented from the Contractor or others; .4 Costs of premiums for all bonds and insurance, permit fees, and sales, use or similar taxes related to the Work; and .5 Additional costs of supervision and field office personnel directly attributable to the change. § 7.3.8 The amount of credit to be allowed by the Contractor to the Owner for a deletion or change that results in a net decrease in the Contract Sum shall be actual net cost as confirmed by the Architect. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for overhead and profit shall be figured on the basis of net increase, if any, with respect to that change. § 7.3.9 Pending final determination of the total cost of a Construction Change Directive to the Owner, the Contractor may request payment for Work completed under the Construction Change Directive in Applications for Payment. The Architect will make an interim determination for purposes of monthly certification for payment for those costs and certify for payment the amount that the Architect determines, in the Architect's professional judgment, to be reasonably justified. The Architect's interim determination of cost shall adjust the Contract Sum on the same basis as a Change Order, subject to the right of either party to disagree and assert a Claim in accordance with Article 15. § 7.3.10 When the Owner and Contractor agree with a determination made by the Architect concerning the adjustments in the Contract Sum and Contract Time, or otherwise reach agreement upon the adjustments, such agreement shall be effective immediately and the Architect will prepare a Change Order. Change Orders may be issued for all or any part of a Construction Change Directive. § 7.4 MINOR CHANGES IN THE WORK The Architect has authority to order minor changes in the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes will be effected by written order signed by the Architect and shall be binding on the Owner and Contractor. (Paragraphs Deleted) ARTICLE 8 1. TIME § 8.1.1 Unless otherwise provided, Contract Time is the period of time, including authorized adjustments, allotted in the Contract Documents for Substantial Completion of the Work. § 8.1.2 The date of commencement of the Work is the date established in the Agreement. § 8.1.3 The date of Substantial Completion is the date certified by the Architect in accordance with Section 9.8. § 8.1.4 The term "day" as used in the Contract Documents shall mean calendar day unless otherwise specifically defined. § 8.2 PROGRESS AND COMPLETION § 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Contract the Contractor confirms that the Contract Time is a reasonable period for performing the Work. § 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, prematurely commence operations on the Site or elsewhere prior to the effective date of insurance required by Article 11 to be AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 27 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) furnished by the Contractor and Owner or prior to approval of Certificates of Insurance, and Additional Insured Endorsement required to be submitted to Owner under the Contract. The date of commencement of the Work shall not be changed by the effective date of such insurance. § 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time. If Contractor's Work shall fall behind schedule for reasons that are not excused under the terms of the Contract, Contractor shall add additional workers or shifts, and/or work overtime as necessary to maintain the Construction Schedule. § 8.2.4 The Contractor must conform to the most recently approved Construction Schedule. The Contractor must complete the indicated Work or achieve the required percentage of completion, as applicable, within any interim completion dates established in the most recently approved Construction Schedule. § 8.2.5 The Contractor must maintain at the Site, available to the Owner and the Architect for their reference during the progress of the Work, a copy of the approved Construction Schedule and any approved revisions thereto. The Contractor must keep current records of and mark on a copy of the approved Construction Schedule the actual commencement date, progress, and completion date of each scheduled activity indicated on the Construction Schedule. § 8.2.6 The Contractor represents that its bid includes all costs, overhead and profit which may be incurred throughout the Contract Time and the period between Substantial and Final Completion. Accordingly, the Contractor may not make any claim for delay damages based in whole or in part on the premise that the Contractor would have completed the Work prior to the expiration of the Contract Time but for any claimed delay. § 8.2.7 If the Contractor's progress is not maintained in accordance with the approved Construction Schedule, or the Owner determines that the Contractor is not diligently proceeding with the Work or has evidence reasonably indicating that the Contractor will not be able to conform to the most recently approved Construction Schedule, the Contractor must, promptly and at no additional cost to the Owner, take all reasonable measures necessary to accelerate its progress to overcome the delay and prevent further delay in the progress of the Work and notify the Owner. § 8.2.8 The Owner reserves the right to issue a written directive to accelerate the Work that may be subject to an appropriate adjustment, if any, in the Contract Sum or Contract Time. If the Owner requires an acceleration of the Construction Schedule and no adjustment is made in the Contract Sum or Contract Time, or if the Contractor disagrees with any adjustment made, the Contractor must file a Claim as provided in Article 15 or the same will be deemed to be conclusively waived. § 8.3 DELAYS TO CONTRACTOR AND EXTENSIONS OF TIME § 8.3.1 If the Contractor is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or Architect, or of an employee of either, or of a separate contractor employed by the Owner; or by Owner -ordered changes in the Work; or by strikes or labor disputes, excusable weather delays as defined in § 15.1.5.2, unusual delay in deliveries beyond the Contractor's control, catastrophic events such as fire, flood and unavoidable casualties or other causes beyond the Contractor's control; or by delay authorized by the Owner pending mediation or other alternative dispute resolution; or by other causes that the Owner and Architect determine may justify delay ("Excusable Delay"), then the Contract Time shall be extended by Change Order for such reasonable time as requested by Contractor and agreed to by the Architect and Owner. The Contractor's sole remedy for Excusable Delays will be time extensions for completion of the Work. .1 The Contractor must provide written notice of any actual or prospective delay promptly, and in no event later than ten (10) days after the occurrence of the event giving rise to such delay. The notice must be given to the Owner and Architect within the specified time. In the case of a continuing delay, the Contractor must provide an initial notice and a further notice at each progress meeting throughout the duration of the delay. The Contractor's failure to provide the written notice within the ten (10) days prescribed above will be conclusively deemed a waiver of any claim for delay arising from such occurrence. .2 If strikes or labor disputes are to be considered as the basis for an excusable delay, they must be documented by data evidencing (i) the trades directly and indirectly involved in or affected by the AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 28 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) strike or labor dispute, (ii) reasons for the strike or labor dispute, (iii) the onset and duration of the strike or labor dispute, and (iv) the measures taken by the Contractor to avoid or overcome the effects of any delay. § 8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Article 15. § 8.3.3 This Section 8.3 does not preclude recovery of damages for delay by either party under other provisions of the Contract Documents. (Paragraphs Deleted) ARTICLE 9 PAYMENTS AND 1. COMPLETION The Contract Sum is stated in the Agreement and, including authorized adjustments, is the total amount payable by the Owner to the Contractor for performance of the Work under the Contract Documents. § 9.2 SCHEDULE OF VALUES Where the Contract is based on a stipulated sum or Guaranteed Maximum Price, the Contractor shall submit to the Architect, before the first Application for Payment, a schedule of values allocating the entire Contract Sum to the various portions of the Work and prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This schedule, unless objected to by the Owner, shall be used as a basis for reviewing the Contractor's Applications for Payment. § 9.3 APPLICATIONS FOR PAYMENT § 9.3.1 The Contractor must submit to the Architect itemized Applications for Payment for Work completed on a monthly basis in accordance with a schedule approved by the Owner. Each Application for Payment must be consistent with the approved Schedule of Values. In order to expedite the review and approval of Applications for Payment, the Contractor may submit to and review with the Architect and Owner a draft Application for Payment at a progress meeting prior to submitting a formal Application for Payment. § 9.3.2 The form of Application for Payment must be AIA Document G702, Application and Certificate for Payment, supported by AIA Document G703, Continuation Sheet (latest edition), or such other form as may be mutually agreed to by the Owner and Contractor. The application must be notarized and supported by sufficient data to demonstrate the Contractor's right to payment and compliance with the payment provisions of the Contract to the satisfaction of the Owner and Architect, such as copies of requisitions from Subcontractors and material suppliers, partial lien waivers, releases and other documents. Each Application for Payment must reflect approved Contract Modifications and the Contract retainage provided for in the Contract Documents. As provided in Section 7.3.9, Applications for Payment may include requests for payment on account of changes in the Work that have been properly authorized by Construction Change Directives, or by interim determinations of the Architect, but not yet included in Change Orders. § 9.3.3 Applications for Payment may include materials and equipment delivered and suitably stored at the Site for subsequent incorporation in the Work. The Owner has no obligation or responsibility to pay for materials stored off the Site; if specifically approved in writing in advance by the Owner, an Application for Payment may include materials and equipment stored off the Site at a location agreed upon in writing. Payment for materials and equipment stored on or off the Site is conditioned upon compliance by the Contractor with procedures satisfactory to the Owner to protect the Owner's interests. Payment for materials and equipment stored off the Site will, in addition, be conditioned upon the Contractor's provision of applicable insurance, storage and transportation to the Site. § 9.3.4 Applications for Payment may not include requests for payment of amounts for Work performed by a Subcontractor or Supplier that the Contractor does not intend to pay for said work. § 9.3.5 Until the conditions set forth in this Section have been satisfied by Contractor, the amount of each monthly Application for Payment must include the value of each line item as indicated on the approved Schedule of Values, to the extent completed, less Contract retainage of five percent (5%). The retainage will not be paid to the Contractor until thirty (30) days after all of the following conditions have been satisfied: (A) the Contractor has fully performed the Contract; (B) the Contractor has completed all Punch List items to the satisfaction of the Owner AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 29 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) and the Architect; (C) the Contractor has delivered to the Owner all Project close-out documents in duplicate, including (1) all maintenance and operating manuals; (2) marked sets of as -built drawings; (3) all guarantees and warranties required under the Contract Documents; and (4) a list of names, addresses, and telephone numbers for all subcontractors and others providing guarantees and warranties; and (D) the applicable governmental authorities have issued to the Owner the final use and occupancy permit for the Project. § 9.3.6 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner, no later than the time of payment. By submitting an Application for Payment, the Contractor further warrants that all Work for which payments have previously been received from the Owner are free and clear of liens, claims, security interests or encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or entities having provided labor, materials and equipment relating to the Work. § 9.3.7 In the Application for Payment, the Contractor must certify in writing that, in accordance with contractual arrangements, Subcontractors and suppliers: .1 have been paid from the proceeds of previous progress payments; and .2 will be paid in a timely manner from the proceeds of the progress payment currently due. In the event the Contractor has not paid or does not pay as certified, such failure constitutes a ground for termination under Section 14.2. § 9.4 CERTIFICATES FOR PAYMENT § 9.4.1 The Architect will, within seven (7) days after receipt of the Contractor's Application for Payment, either issue to the Owner a Certificate for Payment, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor and Owner in writing of the Architect's reasons for withholding certification in whole or in pant as provided in Section 9.5.1. § 9.4.2 The issuance of a Certificate for Payment will constitute a representation by the Architect to the Owner, based on the Architect's evaluation of the Work and the data comprising the Application for Payment, that, to the best of the Architect's knowledge, information and belief, the Work has progressed to the point indicated and that the quality of the Work is in accordance with the Contract Documents. The foregoing representations are subject to an evaluation of the Work for conformance with the Contract Documents upon Substantial Completion, to results of subsequent tests and inspections, to correction of minor deviations from the Contract Documents prior to completion and to specific qualifications expressed by the Architect. The issuance of a Certificate for Payment will further constitute a representation that the Contractor is entitled to payment in the amount certified. However, the issuance of a Certificate for Payment will not be a representation that the Architect made examination to ascertain how or for what purpose the Contractor has used money previously paid on account of the Contract Sum. § 9.5 DECISIONS TO WITHHOLD CERTIFICATION § 9.5.1 The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner, if in the Architect's opinion the representations to the Owner required by Section 9.4.2 cannot be made. If the Architect is unable to certify payment in the amount of the Application, the Architect will notify the Contractor and Owner as provided in Section 9.4.1. If the Contractor and Architect cannot agree on a revised amount, the Architect will promptly issue a Certificate for Payment for the amount for which the Architect is able to make such representations to the Owner. The Architect may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to such extent as may be necessary in the Architect's opinion to protect the Owner from loss for which the Contractor is responsible, including loss resulting from acts and omissions described in Section 3.3.2, because of .1 defective Work not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Contractor; .3 failure of the Contractor to make payments properly to Subcontractors or for labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum; .5 damage to the Owner or a separate contractor; .6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay; or AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties, Unauthorized 3D reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) .7 failure to comply with material provisions of the Contract. § 9.5.2 When the above reasons for withholding certification are removed, certification will be made for amounts previously withheld. § 9.5.3 If the Architect withholds certification for payment under Section 9.5.1.3, the Owner may, at its sole option, issue joint checks to the Contractor and to any Subcontractor or material or equipment suppliers to whom the Contractor failed to make payment for Work properly performed or material or equipment suitably delivered. If the Owner makes payments by joint check, the Owner shall notify the Architect and the Architect will reflect such payment on the next Certificate for Payment. § 9.6 PROGRESS PAYMENTS § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect. § 9.6.2 The Contractor shall pay each Subcontractor no later than seven (7) days after receipt of payment from the Owner the amount to which the Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of the Subcontractor's portion of the Work. The Contractor shall, by appropriate agreement with each Subcontractor, require each Subcontractor to make payments to Sub -subcontractors in a similar manner. § 9.6.3 The Architect will, on request, furnish to a Subcontractor, if practicable, information regarding percentages of completion or amounts applied for by the Contractor and action taken thereon by the Architect and Owner on account of portions of the Work done by such Subcontractor. § 9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has properly paid Subcontractors and material and equipment suppliers amounts paid by the Owner to the Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven (7) days, the Owner shall have the right to contact Subcontractors to ascertain whether they have been properly paid. Neither the Owner nor Architect shall have an obligation to pay or to see to the payment of money to a Subcontractor, except as may otherwise be required by law. § 9.6.5 Contractor payments to material and equipment suppliers shall be treated in a manner similar to that provided in Sections 9.6.2, 9.6.3 and 9.6.4, § 9.6.6 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the Owner shall not constitute acceptance of Work not in accordance with the Contract Documents. § 9.6.7 A'one percent (1%) Montana Construction Managers License (Gross Receipts) tax will be withheld from all payments to the Contractor in accordance with § 15-50-205 et seq., MCA. The Contractor shall be responsible for withholding the I% License Tax from payments made by the Owner to the Contractor for work performed by Subcontractors and the Contractor will file and transmit the necessary forms to the Montana Department of Revenue attendant to such subcontracts within ten (10) days of the award of the subcontract. All amounts withheld for the 1% License Tax are in addition to any retainage amounts otherwise authorized under the Agreement and/or any subcontracts. The Contractor will copy the Owner and Architect on all filings and transmittals made with or to the Department of Revenue in fulfillment of its obligations under this provision. § 9.7 FAILURE OF PAYMENT If the Architect does not issue a Certificate for Payment, through no fault of the Contractor, within seven (7) days afterreceiptof the Contractor's Application for Payment, or if the Owner does not pay the Contractor within seven (7) daysafter the date established in the Contract Documents the amount certified by the Architect or awarded by bindingdispute resolution, then the Contractor may, upon seven (7) additional days' written notice to the Owner and Architect,stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor's reasonable costs ofshut- down, delay and start-up, plus interest as provided for in the Contract Documents. (Paragraph Deleted) AIA Document A201 TM — 2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American (nit. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 31 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) If the Owner does not pay the Contractor within thirty (30) days after the Contractor submits an Application for Payment to the Architect, the Contractor may file a claim in accordance with Article 15 of this Contract. § 9.8 SUBSTANTIAL COMPLETION § 9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Conti -act Documents so that the Owner can occupy or utilize the Work for its intended use. § 9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete and that items remaining to be completed or corrected can be accomplished within another thirty (30) days, subject to the availability of special order parts and materials and environmental conditions beyond the reasonable control of the Contractor, the Contractor must give written notice to the Owner and the Architect and request an inspection of the Work as provided in Section 9.8.3. The Contractor's notice and request for an inspection must be accompanied by a comprehensive Punch List describing all items to be completed or corrected before final Completion and the submittals required by Section 9.8.2. The Contractor must proceed promptly to complete and correct items on the list. Failure to include an item on such list does not alter the Contractor's responsibility to complete all Work in accordance with the Contract Documents. § 9.8.3 In addition to the Punch List, the Contractor must submit the following with its request for a determination of Substantial Completion: 1. a use and occupancy permit; 1. final test reports as required by the Contract and certificates of inspection and approval required for use and occupancy; 2. Fire Inspection or report; 3. approvals from, and transfer documents for, all utilities; 4. Warranties and Guarantees as provided in this Contract; 5. final, approved operating and maintenance manuals; 6. all documents and verification of training required in accordance with any Commissioning Plan; and 7. Schedule to complete the Punch List and value of Work not yet complete. § 9.8.5 Following the inspection and completion or correction of Work required by the Owner or the Architect before issuance of a Certificate of Substantial Completion, the Contractor must notify the Owner and Architect and request another inspection by the Owner and the Architect to determine Substantial Completion. The Contractor must submit a revised Punch List with such notice. The Architect will promptly notify the Contractor if the Owner or the Architect do not concur that the Work is substantially complete. In such case, the Contractor must bear the cost of any additional services of the Owner or the Architect until the Work is determined to be Substantially Complete. § 9.8.6 When the Owner and the Architect concur that the Work is Substantially Complete and that Work remaining to be completed or corrected can be accomplished within a period of thirty (30) days, subject to the availability of special order parts and materials, the Architect will prepare a Certificate of Substantial Completion and a revised Punch List. The Certificate of Substantial Completion will fix the Date of Substantial Completion and the time periods within which the Contractor must finish all items on the Punch List accompanying the Certificate. § 9.8.7 The Certificate of Substantial Completion and accompanying Punch List must be submitted to the Owner and Contractor for execution, which will constitute their written acceptance of responsibilities assigned to them in such Certificate. § 9.8.8 To the extent provided in the Contract Documents or in the Certificate of Substantial Completion, the Owner, upon execution of the Certificate, will assume responsibility for security, operation, safety, maintenance, heat, utilities, damage to the Work (other than damage caused by the Contractor) and insurance. § 9.8.9 Warranties required by the Contract Documents will commence on the Date of Substantial Completion of the Work unless otherwise provided in the Certificate of Substantial Completion or the Contract Documents. § 9.8.10 Upon execution of the Certificate of Substantial Completion, the Contractor will deliver custody and control of such Work to the Owner. The Owner will thereafter provide the Contractor reasonable access to such Work to permit the Contractor to fulfill the correction, completion and other responsibilities remaining under the Contract and the Certificate of Substantial Completion. § 9.8.11 Unless otherwise provided in the Certificate of Substantial Completion, the Contractor must complete or correct all items included in the final Punch List within thirty (30) days, subject to the availability of special order parts and materials, after the Date of Substantial Completion. § 9.8.12 At the time of Substantial Completion, in addition to removing rubbish and leaving the building "broom clean," the Conti -actor must replace any broken or damaged materials, remove stains, spots, marks and dirt from decorated Work, clean all fixtures, vacuum all carpets and wet mop all other floors, replace HVAC filters, clean AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American (nit. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 32 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) HVAC coils, and comply with such additional requirements, if any, which may be specified in the Contract Documents. § 9.9 PARTIAL OCCUPANCY OR USE § 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when such portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to by the insurer as required under Section 11.3.1.5 and authorized by public authorities having jurisdiction over the Project. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the Owner and Contractor have accepted in writing the responsibilities assigned to each of them for payments, retainage, if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents. When the Contractor considers a portion substantially complete, the Contractor shall prepare and submit a list to the Architect as provided under Section 9.8.2. Consent of the Contractor to partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be determined by written agreement between the Owner and Contractor or, if no agreement is reached, by decision of the Architect. § 9.9.2 Immediately prior to such partial occupancy or use, the Owner, Contractor and Architect shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work. § 9.9.3 Any agreement as to the acceptance of the Work not complying with the requirements of the Contract Documents shall not be valid unless in writing. Unless otherwise agreed upon in writing, partial occupancy or use of a portion or portions of the Work shall not constitute acceptance of Work not complying with the requirements of the Contract Documents. § 9.10 FINAL COMPLETION AND FINAL PAYMENT §9.10.1 When the Contractor has completed or corrected all items on the final Punch List and considers that the Work is complete and ready for final acceptance, the Contractor must give written notice to the Owner and the Architect and request a final inspection of the Work as provided in Section 9.10.2. The Contractor's notice and request for a final inspection must be accompanied by a final Application for Payment and the Submittals required by Section 9.10.3. §9.10.2 Upon receipt of the Contractor's notice and request for final inspection, the Owner and the Architect will promptly make such inspection and, when the Owner and the Architect concur that the Work has been fully completed and is acceptable under the Contract Documents, the Architect will issue a Certificate of Final Completion to the Owner. The Contractor's notice and request for final inspection constitutes a representation by the Contractor to the Owner that the Work has been completed in full and strict accordance with terms and conditions of the Contract Documents. The Architect will promptly notify the Contractor if the Owner or the Architect do not concur that the Work is finally complete. In such case, the Contractor must bear the cost of any additional services of the Owner or the Architect until the Work is determined to be finally complete. § 9.10.3 Neither final payment nor any remaining retained percentage will become due until the Contractor submits the following documents to the Architect: 1. an affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the Owner or the Owner's property might be responsible or encumbered (less amounts withheld by Owner), have been paid or otherwise satisfied, submitted on AIA Document G706, Affidavit of Payment of Debts and Claims (latest edition) or such other form as may be prescribed by the Owner; 2. a release or waiver of claims except those that are pending. Notwithstanding applicable Montana law, if any liens have been filed Contractor shall release, waive or indemnify Owner therefi•om; 3. a certificate evidencing that the Contractor's liability insurance and Performance Bond remain in effect during the one-year correction period following Substantial Completion as set forth in Sections 12.2.2.1 and 12.2.2.2; 4. a written statement that the Contractor knows of no substantial reason that the insurance will not be renewable to cover the period required by the Contract Documents; 5. :consent of surety to final payment, submitted on AIA Document G707 (latest edition) or other form prescribed by the Owner; 6. other data required by the Owner establishing payment or satisfaction of obligations, such as receipts, releases and waivers of liens or claims, security interests or encumbrances arising out of the Contract, to the extent and in such form as may be prescribed by the Owner; 7. a certified building location survey and as -built site plan in the form and number required by the Contract AIA Document A201 TM —2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 33 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) Documents; 8. all warranties and bonds required by the Contract Documents; 9. Record Documents as provided in Section 3.1 land return of Contract Documents as provided therein; and 10. Attic stock items as required by the Contract Documents; and As applicable, documentation of approval by all authorities having jurisdiction that all necessary permits and licenses have been issued in the name of the Owner as to allow closeout and satisfaction of all requirements including the submission of acceptable as -built drawings and other required 11. documents. § 9.10.4 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by issuance of Change Orders affecting final completion, and the Architect so confirms, the Owner shall, upon application by the Contractor and certification by the Architect, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract Documents, and if bonds have been furnished, the written consent of surety to payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect prior to certification of such payment. Such payment shall be made under terms and conditions governing final payment, except that it shall not constitute a waiver of claims. (Paragraphs Deleted) ARTICLE 10 PROTECTION OF PERSONS AND 1. PROPERTY (Paragraphs Deleted) The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the performance of the Contract. The Contractor will maintain on Site a material safety data sheet on all chemicals and potentially hazardous materials brought on site by the Contractor or any subcontractor, supplier, or employee or agent of a subcontractor or supplier, including but not limited to paints, thinners, glues, mastics and solvents. The safety data sheets will be provided to the Owner and Architect upon Final Completion. § 10.2 SAFETY OF PERSONS AND PROPERTY § 10.2.1 The Contractor must take reasonable precautions for the safety of, and must provide reasonable protection to prevent damage, injury or loss to: .1 All persons at the Site and other persons who may be affected by the Work or other operations of the Contractor; 2 the Work and materials and equipment to be incorporated therein or otherwise utilized in the performance of the Contract, whether in storage on or off the Site, under care, custody or control of the Contractor or the Contractor's Subcontractors or Sub -subcontractors; and .3 other property at the Site or adjacent thereto, such as trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. The Contractor must repair and/or replace that portion of the Work and any materials or equipment to be incorporated therein and any tools or equipment of the Contractor necessary or beneficial to performance of the Work which are damaged or stolen due to vandalism, theft or any other criminal mischief at its expense whether or not covered by insurance. No extension of the Contract Time or increase in the Contract Sum will be granted to the Contractor as a consequence of any delay, impacts or inefficiencies resulting from any act of vandalism, theft or other criminal mischief whether or not caused or contributed to by the Contractor's negligence. § 10.2.2 The Contractor must implement and maintain, as required by the Contract Documents, applicable laws and regulations and orders of public authorities having jurisdiction (without limitation OSHA and State of Montana safety agencies and authorities), manufacturers' instructions or recommendations, existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including issuing appropriate notices, AIA Document A201 TM —2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 34 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) distributing material safety data sheets and other hazard communication information, providing protective clothing and equipment, posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent sites and utilities. § 10.2.3 The Contractor shall erect and maintain, as required by existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent sites and utilities. § 10.2.4 The Contractor must not load nor permit any pant of any structure at the Site to be loaded or subjected to stresses or pressures so as to endanger its safety or that of adjacent structures or property. § 10.2.5 The Contractor shall reject the use of any hazardous material in the construction of the Project, including but not limited to asbestos, asbestos products, polychlorinated biphenyl (PCB) or other toxic substances. It is the Owner's and Architect's intent to design, specify and approve only materials and products for this Project that are free of such hazardous material. If the Contractor becomes aware of that any Subcontractor, material supplier or manufacturer intends to supply or install products or services for the Project that contain such materials, the Contractor shall promptly notify the Architect in writing. Further, if any such materials are discovered in the course of the construction, the Contractor shall notify the Owner immediately. Construction Manager shall comply with all hazard communication requirements dictated by the Environmental Protection Agency, the Montana Department of Agriculture, OSHA, Hazard Communications Standard, 29 CFR 1910.1200, and applicable City of Bozeman ordinances. When explosives or other hazardous materials or equipment are stored or used or unusual methods are employed in the performance of the Work, the Contractor must exercise utmost care and conduct such activities under supervision of properly qualified personnel. § 10.2.6 If either Party suffers injury or damage to person or property because of an act or omission of the other Party, or of any of the other Party's employees or agents, or of others for whose acts it is contended that the other Party is liable, written notice of such injury or damage, whether or not insured, must be given to the other Party within a reasonable time not exceeding ten (10) days after the onset or occurrence of such damage or injury or such shorter time as may be required by the Occupational Safety Hazards Administration (OSHA). The notice must provide sufficient detail to enable the other Party to investigate the matter. If notice is not received within the time specified, any claim arising from the occurrence will be deemed to be conclusively waived, except to the extent of any applicable insurance (excluding self-insurance) coverage covering such occurrence. The provisions of this Section may not be used by the Contractor in lieu of the requirements of Article 7 when the Contractor is seeking an adjustment in the Contract Sum and are in addition to the requirements of Article 8 when the Contractor is seeking an adjustment in the Contract Time. § 10.2.7 The Contractor must promptly remedy, at its sole cost and expense, damage and loss to property referred to in Sections 10.2.1.2 and 10.2.1.3 caused in whole or in part by the Contractor, a Subcontractor, a Sub -subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable, unless otherwise instructed in writing by the Owner. This obligation is in addition to, and not in limitation of, the Contractor's obligations for indemnification under Section 3.18 and the Contractor's responsibility to repair and or replace that portion of the Work and any materials and equipment to be incorporated therein which are damaged as a result of criminal mischief as specified in Section 10.2.9. § 10.2.8 The Contractor shall designate a responsible member of the Contractor's organization at the Site whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise designated by the Contractor in writing to the Owner and Architect. (Paragraph Deleted) 10.2.9 If either party suffers injury or damage to person or property because of an act or omission of the other party, or of others for whose acts such party is legally responsible, written notice of such injury or damage, whether or not insured, shall be given to the other party as soon as possible. The notice shall provide sufficient detail to enable the other party to investigate the matter. AIA Document A201 TM — 2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 35 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the, t maximum extent possible under the law. This documentwas produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) § 10.3 HAZARDOUS MATERIALS § 10.3.1 The Contractor is responsible for compliance with any requirements included in the Contract Documents regarding hazardous materials. In the event the Contractor encounters on the Site material reasonably believed to be a Hazardous Material (other than those for which the Contractor may have specific responsibility for remediation under the Contract), and the Contractor's reasonable precautions will be inadequate to prevent foreseeable damage or injury and the Contractor cannot proceed with the Work in the absence of the removal, containment or remediation of the Hazardous Material, the Contractor must immediately stop Work in the area affected and report the condition to the Owner and the Architect immediately upon discovery, followed by notice in writing within 24 hours of discovery. § 10.3.2 Upon receipt of notice of suspected Hazardous Materials, Owner will cause an investigation to be made to verify the presence and extent of such materials, to determine whether such materials are in fact hazardous, and the steps necessary for their removal, containment or remediation. (Paragraph Deleted) § 10.3.3 If the Owner's investigation confirms the presence of Hazardous Materials which present a risk of injury or damage which will not be adequately protected against by the Contractor's reasonable precautions, then the Work in the affected area must not thereafter be resumed except at the written direction of the Owner. The Work in the affected area will be resumed promptly (i) in the absence of a finding of Hazardous Material by the Owner, (ii) upon the removal, containment or remediation of the Hazardous Materials, or (iii) upon the establishment of appropriate safety precautions. § 10.3.4 The Contractor may request a change in the Contract Sum or Contract Time if the Contractor incurs additional costs on account of or is delayed by the need to remove, contain or remediate Hazardous Materials which has not been rendered harmless at the Site unless the Contractor is responsible for same under the Contract. Any such requested change in the Contract Sum or Contract Time must be made in writing within ten (10) days of discovery of any Hazardous Materials, which has not been rendered harmless giving rise to the request for the change and must fully comply with Articles 7, 8, and 15 or any claim will be deemed conclusively waived by the Contractor. 10.3.5 The Owner shall not be responsible under this Section 10.3 for materials or substances the Contractor brings to the Site unless such materials or substances are required by the Contract Documents. The Owner shall be responsible for materials or substances required by the Contract Documents, except to the extent of the Contractor's fault or negligence in the use and handling of such materials or substances. § 10.3.6 The Contractor shall indemnify the Owner for the cost and expense the Owner incurs (1) for remediation of a material or substance the Contractor brings to the Site and negligently handles, or (2) where the Contractor fails to perform its obligations under Section 10.3.1, except to the extent that the cost and expense are due to the Owner's fault or negligence. (Paragraph Deleted) § 10.4 EMERGENCIES In an emergency affecting safety of persons or property, the Contractor must take all necessary action, without the necessity for any special instruction or authorization from the Owner or Architect, to prevent threatened damage, injury or loss. The Contractor must promptly, but in all events within twenty-four (24) hours of the emergency, report such action in writing to the Owner and Architect. If the Contractor incurs additional costs on account of or is delayed by such emergency, the Contractor may request a change in the Contract Sum or Contract Time to account for such additional costs or delay in accordance with Articles 7, 8 and 15. The Contractor must file any such request within ten (10) days of the emergency or it is deemed waived. Any adjustment in the Contract Sum or Contract Time shall be limited to the extent that the emergency work is not attributable to the fault or neglect of the Contractor or otherwise the responsibility of the Contractor under the Contract Documents. ARTICLE 11 INSURANCE AND BONDS § 11.1 CONTRACTOR'S LIABILITY INSURANCE § 11.1.1 The Contractor shall carry and maintain, as part of the Contract Sum, the following insurance coverage insuring the Owner and Project while under construction and all material and supplies purchased in connection with the construction of the Project against all risks and losses. All such insurance policies to be issued in the amounts and terms provided as follows and approved by Owner and to provide Owner with certificates of insurance, and if requested by Owner, copies of policies and applicable endorsements. Contractor shall give Owner immediate notice of any material reduction, cancellation, termination or non -renewal of the insurance required by this Section 11.1. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties, Unauthorized 36 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) Any company writing this insurance shall at all times be licensed and qualified to do business in the State of Montana. Contractor's insurance shall be primary and non-contributory. Such insurance shall include: .2 Commercial General Liability with a minimum limit of liability of Two Million Dollars ($2,000,000) per occurrence, Five Million Dollars ($5,000,000) annual aggregate, for bodily injury and property damage coverage including the following coverages: Contractual Liability; Premises and Operations; Independent Contractors; Personal Injury; Products and Completed Operations; and explosion, collapse and underground event. The policy must name the City of Bozeman as additional insured. (Paragraph Deleted) .3 Automobile Liability Insurance of not less than One Million Dollars ($1,000,000) combined single limit per occurrence to include coverage for owned, non -owned, hired motor vehicles, uninsured/underinsured motorists, and automobile contractual liability. The policy must name the City of Bozeman as additional insured. .3 Worker's Compensation/Employer's Liability meeting all statutory requirements of the State of Montana and with the following minimum Employers' Liability limits: bodily injury by accident — One Million Dollars ($1,000,000) each accident; bodily injury by disease — One Million Dollars ($1,000,000) policy limits; and bodily injury by disease — One Million Dollars ($1,000,000) each employee. Contractor shall not commence work under this Agreement until such insurance has been obtained and certificates of insurance, with binders, or certified copies of the insurance policy including additional insureds endorsement shall have been filed with the Owner and the Architect. (Paragraph Deleted) The insurance requirements of this Section 11.1 shall also apply in full to all Subcontractors hired to perform the Work. § 11.1.2 The insurance required by Section 11.1.1 shall be written for not less than limits of liability specified in the Contract Documents or required by law, whichever coverage is greater. Coverages, whether written on an occurrence or claims -made basis, shall be maintained without interruption from the date of commencement of the Work until one year after the date of Substantial Completion, and, with respect to the Contractor's completed operations coverage, until the expiration of the period for correction of Work or for such other period for maintenance of completed operations coverage as specified in the Contract Documents. § 11.1.3 Certificates of insurance acceptable to the Owner shall be filed with the Owner prior to commencement of the Work and thereafter upon renewal or replacement of each required policy of insurance and upon request by the Owner. An additional certificate evidencing continuation of liability coverage, including coverage for completed operations, shall be submitted with the final Application for Payment as required by Section 9.10.2 and thereafter upon renewal or replacement of such coverage until the expiration of the time required by Section 11.1.2. Information concerning reduction of coverage on account of revised limits or claims paid under the General Aggregate, or both, shall be furnished by the Contractor with reasonable promptness. § 11.1.4 The Contractor shall cause the commercial liability coverage required by the Contract Documents to include (1) the City of Bozeman, the Architect and the Architect's consultants as additional insureds for claims caused in whole or in part by the Contractor's negligent acts or omissions during the Contractor's operations; and (2) the City of Bozeman as additional insureds for claims caused in whole or in part by the Contractor's negligent acts or omissions during the Contractor's completed operations. § 11.2 OWNER'S LIABILITY INSURANCE The City shall maintain coverage for its risks through the Montana Municipal Interlocal Authority. § 11.3 PROPERTY INSURANCE § 11.3.1 Unless otherwise provided, the Contractor shall purchase and maintain, in a company or companieslawfully authorized to do business in Montana, property insurance written on a builder's risk "all-risk" policy form in the AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Inst. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 37 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) amount of the initial Contract Sum, plus value of subsequent Contract Modifications and cost ofmaterials supplied or installed by others, comprising total value for the entire Project at the site on a replacement costbasis without optional deductibles. Such property insurance shall be maintained, unless otherwise provided in theContract Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance,until final payment has been made as provided in Section 9.10 or until no person or entity other than the Owner has an insurable interest in the property required by this Section 11.3 to be covered, whichever is later. This insurance shall include interests of the Owner, the Contractor, Subcontractors and Sub -subcontractors in the Project. § 11.3.1.1 Property insurance shall be on an "all-risk" policy form and shall include, without limitation, insurance against the perils of fire (with extended coverage) and physical loss or damage including, withoutduplication of coverage, theft, vandalism, malicious mischief, collapse, earthquake, flood, windstorm, falsework,testing and startup, temporary buildings and debris removal including demolition occasioned by enforcement of anyapplicable legal requirements, and shall cover reasonable compensation for Architect's and Contractor's services andexpenses required as a result of such insured loss. The Parties may mutually agree in writing to separate limits forinsurance covering the risk of flood and/or earthquake. § 11.3.1.2 Reserved. § 11.3.1.3 If the property insurance requires deductibles, the Owner shall pay costs not covered because of such deductibles. The Owner waives all rights of action against the Contractor for loss of use of the Owner's property, including consequential losses due to fire or other hazards however caused. § 11.3.1.4 This property insurance shall cover portions of the Work stored off the site, and also portions of the Work intransit. § 11.3.1.5 Partial occupancy or use in accordance with Section 99 shall not commence until the insurance company orcompanies providing property insurance have consented to such partial occupancy or use by endorsement or otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of the insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse or reduction of insurance. § 11.3.2 BOILER AND MACHINERY INSURANCE The Contractor shall purchase and maintain boiler and machinery insurance required by the ContractDocuments or by law, which shall specifically cover such insured objects during installation and until final acceptanceby the Owner; this insurance shall include interests of the Owner, Contractor, Subcontractors and Sub-subcontractorsin the Work, and the Owner and Contractor, shall be named insureds. § 11.3.3 LOSS OF USE INSURANCE The Owner, at the Owner's option, may maintain such insurance as will insure the Owner against loss of use of the Owner's property due to fire or other hazards, however caused. § 11.3.4 If the Contractor requests in writing that insurance for risks other than those described herein or other special causes of loss be included in the property insurance policy, and the Owner agrees to include such insurance, the cost thereof shall be charged to the Contractor by appropriate Change Order. § 11.3.5 Before an exposure to loss may occur, the Contractor shall file with the Owner a copy ofeach policy that includes _insurance coverages required by this Section 11.3. Each policy shall contain all generallyapplicable conditions, definitions, exclusions and endorsements related to this Project. Each policy shall contain aprovision that the policy will not be canceled or allowed to expire, and that its limits will not be reduced, until at least30 days' prior written notice has been given to the Owner. 11.3.6 The Contractor shall AIA Document A201 TM —2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties, Unauthorized 38 reproduction or distribution oft his AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) pay Subcontractors their just shares of insurance proceeds received by the Contractor, and by appropriate agreements, written where legally required for validity, shall require Subcontractors to make payments to their Sub - subcontractors in similar manner. § 11.4 PERFORMANCE BOND AND PAYMENT BOND § 11.4.1 The Contractor shall furnish a Performance Bond and Labor and Material Payment Bond meeting all statutory requirements of the State of Montana, in form and substances satisfactory to the Owner and, without limitation, complying with the following specific requirements: 1. 2. Except as otherwise required by statute, the form and substance of such bond(s) shall be satisfactory to the Owner in the Owner's sole judgment. Bond(s) shall be executed by a responsible surety licensed in Montana and listed in the latest U.S. Dept. of Treasury Circular #570, with a Best's rating of no less than A/XII. Said bonds shall remain in effect through the warranty period, and until all of the Contractor's obligations to the Owner are fulfilled. 3. The Performance Bond and the Labor and Material Payment Bond shall be in an amount equal to or exceeding one hundred percent (1001/o) of the Contract Sum. 4. The Contractor shall require the attorney-in-fact who executes the required bond(s) on behalf of the surety to affix thereto a certified and current copy of his power of attorney indicating the monetary limit of such power. 5. Every Bond under this Paragraph 11.4.1 must display the Surety's Bond Number. A rider including the following provision shall be attached to each Bond: (1) Surety agrees that it is obligated under the bond(s) to any successor, grantee or assignee of the Owner. 6. The City of Bozeman shall be named as obligee on the bonds. (Paragraph Deleted) The Contractor shall deliver the required bonds to the Owner not later than three (3) days following the date the Agreement is executed and prior to the commencement of any work under the Agreement. Premiums for all bonds shall be part of the Contract Sum. § 11.4.2 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering payment of obligations arising under the Contract, the Contractor shall promptly furnish a copy of the bonds or shall authorize a copy to be furnished. (Paragraph Deleted) § 11.4.3 The Contractor shall keep the surety informed of the progress of the Work, and, where necessary, obtain the surety's consent to, or waiver of: (1) notice of changes in the Work; (2) request for reduction or release of retention; (3) request for final payment; and (4) any other material required by the surety. The Owner may, in the Owner's sole discretion, inform surety of the progress of the Work and obtain consents as necessary to protect the Owner's rights, interest, privileges and benefits under and pursuant to any bond issued in connection with the Work. (Paragraph Deleted) ARTICLE 12 UNCOVERING AND CORRECTION OF 1. WORK § 12.1.1 If a portion of the Work is covered contrary to the Architect's request or to requirements specifically expressed in the Contract Documents, it must, if requested in writing by the Architect, upon written authorization from the Owner, be uncovered for the Architect's examination and be replaced at the Contractor's expense without change in the Contract Time. § 12.1.2 If a portion of the Work has been covered that the Architect has not specifically requested to examine prior to its being covered, the Architect may request, upon written authorization from the Owner, to see such Work and it shall be uncovered by the Contractor. If such Work is in accordance with the Contract Documents, costs of uncovering and replacement shall, by appropriate Change Order, be at the Owner's expense. If such Work is not in accordance with the Contract Documents, such costs and the cost of correction shall be at the Contractor's expense unless the condition was caused by the Owner or a separate contractor in which event the Owner shall be responsible for payment of such costs. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 39 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) § 12.2 CORRECTION OF WORK § 12.2.1 BEFORE OR AFTER SUBSTANTIAL COMPLETION The Contractor shall promptly correct Work rejected by the Architect or failing to conform to the requirements of the Contract Documents, whether discovered before or after Substantial Completion and whether or not fabricated, installed or completed. Costs of correcting such rejected Work, including additional testing and inspections, the cost of uncovering and replacement, and compensation for the Architect's services and expenses made necessary thereby, shall be at the Contractor's expense. § 12.2.1.1 Within 48 hours after written notice from the Architect or the Owner that any component of the Work does not conform to the Contract Documents, or immediately upon oral notice, if the nonconformance constitutes a threat to the safety of persons or property, the Contractor without waiting for the resolution of disputes that may exist, shall commence to correct such nonconformance, shall thereafter use its best efforts to correct such nonconformance to the satisfaction of the Architect and the Owner, and except where an extension of time is granted in writing by the Owner, shall complete necessary corrections so that the nonconformance is eliminated to the satisfaction of the Architect and the Owner within thirty (30) days of such notice or as soon as reasonably possible. The Contractor shall bear all costs of correcting the nonconformance, including additional testing and inspections and additional service fees of the Architect. It is the intent that the obligations under this subparagraph 12.2.1.1 shall continue to apply after completion and final payment. § 12.2.1.2 If the Contractor fails to correct nonconforming Work as provided in subparagraph 12.2.1.1, the Owner may correct it in accordance with the provisions of this Agreement. If the Contractor does not proceed with correction of such nonconforming work as provided in subparagraph 12.2.1.1, the Owner may remove it and store the salvageable materials or equipment at the Contractor's expense. § 12.2.2 AFTER SUBSTANTIAL COMPLETION § 12.2.2.1 In addition to the Contractor's obligations under Section 3.5, if, within one year after the date of Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 9.9.1, or by terms of an applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or Architect, the Owner may correct it in accordance with Section 2.4. § 12.2.2.2 The one-year period for correction of Work shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual completion of that portion of the Work. § 12.2.2.3 The one-year period for correction of Work shall not be extended by corrective Work performed by the Contractor pursuant to this Section 12.2. § 12.2.3 The Contractor shall remove from the Site portions of the Work that are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the Owner. § 12.2.4 The Contractor shall bear the cost of correcting destroyed or damaged construction, whether completed or partially completed, of the Owner or separate contractors caused by the Contractor's correction or removal of Work that is not in accordance with the requirements of the Contract Documents. § 12.2.5 Nothing contained in this Section 12.2 shall be construed to establish a period of limitation with respect to other obligations the Contractor has under the Contract Documents. Establishment of the one-year period for correction of Work as described in Section 12.2.2 relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability with respect to the Contractor's obligations other than specifically to correct the Work. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 40 reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 12.3 ACCEPTANCE OF NONCONFORMING WORK If the Owner prefers to accept Work that is not in accordance with the requirements of the Contract Documents, the Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. The acceptance of nonconforming work by the Owner shall be by written Change Order, signed by the Owner's authorized representative. No person has authority to accept nonconforming work except pursuant to such written Change Order. (Paragraphs Deleted) ARTICLE 13 MISCELLANEOUS 1. PROVISIONS The Contract shall be governed by, and construed in accordance with, the laws of the State of Montana without regard to its conflict of laws provisions. § 13.2 SUCCESSORS AND ASSIGNS § 13.2.1 The Owner and Contractor respectively bind themselves, their partners, successors, assigns and legal representatives to covenants, agreements and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract as a whole without written consent of the other. If either party attempts to make such an assignment without such consent, that party shall nevertheless remain legally responsible for all obligations under the Contract. (Paragraph Deleted) § 13.3 WRITTEN NOTICE Written notices are to be provided to the representatives of the parties designated in this Contract. Written notices are deemed to have been duly served if delivered in person to the addressee for whom it was intended, or if delivered by electronic mail, fax, certified mail, or overnight courier. The date of any notice is deemed to be the earlier of the date of personal delivery, fax, or electronic mail; one day after delivery to the overnight courier; and three days after mailing by certified mail. § 13.4 RIGHTS AND REMEDIES § 13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies available thereunder shall be in addition to and not a limitation of duties, obligations, rights and remedies otherwise imposed or available by law. § 13.4.2 No action or failure to act by the Owner, Architect or Contractor shall constitute a waiver of a right or duty afforded them under the Contract, nor shall such action or failure to act constitute approval of or acquiescence in a breach there under, except as may be specifically agreed in writing. § 13.5 TESTS AND INSPECTIONS § 13.5.1 Tests, inspections and approvals of portions of the Work shall be made as required by the Contract Documents and by applicable laws, statutes, ordinances, codes, rules and regulations or lawful orders of public authorities. Unless otherwise provided, the Contractor shall make arrangements for such tests, inspections and approvals with an independent testing laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall bear all related costs of tests, inspections and approvals. The Contractor must schedule all tests, inspections or specific approvals required by law or the Contract Documents so as to avoid any delay in the Work. The Contractor shall give the Architect timely notice of when and where tests and inspections are to be made so that the Architect may be present for such procedures. § 13.5.2 If the Architect, Owner or public authorities having jurisdiction determine that portions of the Work require additional testing, inspection or approval not included under Section 13.5.1, the Architect will, upon written authorization from the Owner, instruct the Contractor to make arrangements for such additional testing, inspection or approval by an entity acceptable to the Owner, and the Contractor shall give timely notice to the Architect of when and where tests and inspections are to be made so that the Architect may be present for such procedures. Such costs, except as provided in Section 13.5.3, shall be at the Owner's expense. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 41 reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) § 13.5.3 If such procedures for testing, inspection or approval under Sections 13.5.1 and 13.5.2 reveal failure of the portions of the Work to comply with requirements established by the Contract Documents, all costs made necessary by such failure including those of repeated procedures and compensation for the Architect's services and expenses shall be at the Contractor's expense. The Contractor also agrees that the cost of testing services required for the convenience of the Contractor in his scheduling and performance of the Work, and the cost of testing services related to remedial operations performed to correct deficiencies in the Work shall be borne by the Contractor. § 13.5.4 Certificates of inspection, testing, or approval, as required by paragraphs 13.5.1 or 13.5.2, shall be secured by the Contractor using an independent agency, subject to the approval of the Architect and Owner. The independent agency shall complete field work, testing, and prepare the test reports, logs, and certificates promptly; and deliver the required number of copies directly to the Contractor for transmittal to the Architect. § 13.5.5 If the Architect is to observe tests, inspections or approvals required by the Contract Documents, the Architect will do so promptly and, where practicable, at the normal place of testing. § 13.5.6 Tests or inspections conducted pursuant to the Contract Documents shall be made promptly to avoid unreasonable delay in the Work. § 13.5.7 In addition to the tests required by this Section 13.5, the Owner may at any time arrange for other tests, inspections and specific approvals to be performed by others selected by the Owner, at the Owner's expense. The Contractor must cooperate with the Owner and provide access to the Work for such tests, inspections and approvals. § 13.6 INTEREST Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at such rate as the parties may agree upon in writing or, in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located. § 13.7 TIME LIMITS ON CLAIMS The Owner and Contractor shall commence all claims and causes of action, whether in contract, tort, breach of warranty,or otherwise, against the other arising out of or related to the Contract in accordance with the time period specified by applicable law. § 13.8 DOCUMENT RETENTION AND AUDIT PROVISIONS Contractor shall account for all materials, equipment and labor entering into the Work and must keep such full and detailed records as may necessary for proper financial management pursuant to the Contract Documents for a period of five (5) years after final payment. Furthermore, the Owner has the right to examine the Contractor's and its Subcontractors' and suppliers' records directly or indirectly pertaining or relating to the Work or the Contract and the Contractor must grant the Owner access to and an opportunity to copy such records at all reasonable times during the Contract period and for five (5) years after final payment. (Paragraphs Deleted) ARTICLE 14 "TERMINATION OR SUSPENSION OF THE 1. CONTRACT § 14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of sixty (60) consecutive days through no act or fault of the Contractor or a Subcontractor, Sub -subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contract with the Contractor, only for the following reasons: .1 Issuance of an order of a court or other public authority having jurisdiction that requires all Work to be stopped; .2 An act of government, such as a declaration of national emergency that requires all Work to be stopped; .3 Because the Architect has not issued a Certificate for Payment and has not notified the Contractor of the reason for withholding certification as provided in Section 9.4.1, or because the Owner has not made payment on a Certificate for Payment within the time stated in the Contract Documents; or .4 The Owner has failed to furnish to the Contractor promptly, upon the Contractor's request, reasonable evidence as required by Section 2.2.1. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 42 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This documentwas produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 14.1.2 The Contractor may terminate the Contract if, through no act or fault of the Contractor or a Subcontractor, Sub -subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contact with the Contractor, repeated suspensions, delays or interruptions of the entire Work by the Owner as described in Section 14.3 constitute more than 100 percent of the total number of days scheduled to achieve Substantial Completion as set forth in the Contract. § 14.1.3 If one of the reasons described in Section 14. 1.1 or 14.1.2 exists and sixty (60) days has elapsed, the Contractor may, upon fourteen (14) days' written notice to the Owner and Architect, terminate the Contract and recover from the Owner payment for Work executed and for loss with respect to materials, equipment, tools, construction equipment, and machinery (provided evidence reasonably acceptable to Owner for such loss is provided to Owner). Contractor shall make every effort to reduce the termination costs to the Owner and shall not be entitled to overhead, profit or damages of any kind or termination costs which are unrelated to the actual provision of the Work. The Contractor will be entitled to compensation only for the following items: payment for Work performed and accepted up to the date of termination; .2 the costs of preservation and protection of the Work if requested to do so by the Owner; .3 the cost of terminating the following contracts: (i) purchased materials but only if not returnable or the restocking or return charge, if any, if returnable at the Owner's written election; and (ii) equipment rental contracts if not terminable at no cost but not to exceed an amount equal to thirty (30) days rental. .4 documented transportation costs associated with removing Contractor -owned equipment. The Contractor will not be compensated for the cost of terminating subcontracts which must be terminable at no cost to the Owner for the costs listed in Section 14.1.3.1, 14.1.3.2, 14.1.3.3 and 14.1.3.4. If the Owner and the Contractor are unable to agree upon the amounts specified in this subsection, the Contractor must submit a Claim as provided in Article 15. The Claim must be limited to resolution of the amounts specified in Section 14.1.3.1, 14.1.3.2, 14.1.3.3, and 14.1.3.4. No other cost, damages or expenses may be claimed or paid to the Contractor or considered as part of the Claim, the same being hereby conclusively and irrevocably waived by the Contractor. Any such Claim must be delivered to the Owner within thirty (30) days of the termination of the Contract and must contain a written statement setting forth the specific reasons and supporting calculations and documentation as to the amounts the Contractor claims to be entitled to under this Subsection as a result of the termination of the Contract. § 14.2 TERMINATION BY THE OWNER FOR CAUSE 14.2.1 The Owner may terminate the Contract for cause if the Contractor: .1 Fails to supply adequate properly skilled workers or proper materials; .2 Fails to make payment to Subcontractors or Suppliers for materials or labor in accordance with the respective agreements between the Contractor and the Subcontractors or Suppliers; .3 Fails to comply with any laws, ordinances, or rules, regulations or orders of a public authority having jurisdiction; .4 Fails to perform the Work in accordance with the Contract Documents or otherwise materially breaches any provision of the Contract Documents; .5 Anticipatorily breaches or repudiates the Contract; or ,6 Fails to make satisfactory progress in the prosecution of the Work required by the Contract. § 14.2.2 The Owner may terminate the Contract, in whole or in part, whenever the Owner in good faith determines that sufficient grounds for termination exist as provided in Subsection 14.2.1. The Owner will provide the Contractor with a written ten (10) day notice to cure the default. If the default is not cured, the termination for default is effective on the date specified in the Owner's written notice. However, if the Owner determines that default contributes to the curtailment of an essential service or poses an immediate threat to life, health, or property, the Owner may terminate the Contract immediately upon issuing oral or written notice to the Contractor without any prior notice or opportunity to cure. In addition to any other remedies provided by law or the Contract, the Contractor must compensate the Owner for additional costs actually incurred by the Owner to obtain substitute performance. AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 43 reproduction or distribution of this AIA", Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) § 14.2.3 Upon receipt of written notice from the Owner of termination, the Contractor must: .1 Cease operations as directed by the Owner in the notice and, if required by the Owner and reasonably cooperate in an inspection of the Work with the Owner and the Architect to record the extent of completion thereof, to identify the Work remaining to be completed or corrected, and to determine what temporary facilities, tools, equipment and construction machinery are to remain at the Site pending completion of the Work; .2 Complete or correct the items directed by the Owner, and take actions necessary, or that the Owner may direct, for the protection and preservation of any stored materials and equipment and completed Work; .3 Remove its tools, equipment and construction machinery from the Site, and .4 Except as directed by the Owner, terminate all existing subcontracts and purchase orders and enter into no further subcontracts or purchase orders. § 14.2.4 Following written notice from the Owner of termination, the Owner may: .1 Take possession of the Site and of all materials for which Owner has paid and equipment thereon, and at the Owner's option, such temporary facilities, tools, construction equipment and machinery thereon rented by the Contractor that the Owner elects to utilize in completing the Work; .2 Accept assignment of subcontracts and purchase orders, and .3 Complete the Work by whatever reasonable method the Owner may deem expedient. § 14.2.5 Upon termination for cause, the Contractor must take those actions described in Section 14.2.3, and the Owner may take those actions described in Section 14.2.4, subject to the prior rights of the Contractor's Surety. § 14.2.6 When the Owner terminates the Contract for cause, the Contractor is not entitled to receive further payment until the Work is completed and the costs of completion have been established; provided, however, that the Owner shall withhold from payment only that amount the Owner reasonably estimates is necessary to complete the Work. § 14.2.7 If the unpaid balance of the Contract Sum less amounts which the Owner is entitled to offset from the unpaid Contract balance under Montana law, exceeds the costs of completing the Work, including compensation for the Owner's and the Architect's services made necessary thereby, such excess will be paid to the Contractor or Surety, as directed by the Surety. If such costs exceed the unpaid Contract balance, the Contractor must pay the difference to the Owner upon written demand. This obligation for payment survives termination of the Contract. § 14.2.8 In completing the Work following termination for cause, the Owner may or may not solicit competitive bids or award completion work to the lowest bidder, and may obtain such completion work and related services on the basis of sole source procurement and negotiated compensation if in accordance with applicable law. §14.2.9 If the Contractor files for protection, or a petition is filed against it, under the Bankruptcy laws, and Contractor wishes to affirm the Contract, Contractor shall immediately file with the Bankruptcy Court a motion to affirm the Contract and shall provide satisfactory evidence to Owner and to the Court of its ability to cure all present defaults and its ability to timely and successfully complete the Work. If Contractor does not make such an immediate filing, Contractor accepts that Owner shall petition the Bankruptcy Court to lift the Automatic Stay and permit Owner to terminate the Contract. § 14.3 SUSPENSION BY THE OWNER FOR CONVENIENCE § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be equitably adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1. No adjustment shall be made to the extent .1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or .2 that an equitable adjustment is made or denied under another provision of the Contract. § 14.4 TERMINATION BY THE OWNER FOR CONVENIENCE § 14.4.1 The Owner may, at any time, terminate the Contract or any portion thereof or of the Work for the Owner's convenience and without cause. AIA Document A201T"—2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright law and International Treaties. Unauthorized 44 reproduction or distribution of this AIA° Document, or any portion of it, may result insevere civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (389ADA17) § 14.4.2 Upon receipt of written notice from the Owner of termination, the Contractor must: .1 Cease operations as directed by the Owner in the notice and, if required by the Owner, participate in an inspection of the Work with the Owner and the Architect/Engineer to record the extent of completion thereof, to identify the Work remaining to be completed or corrected, and to determine what temporary facilities, tools, equipment and construction machinery are to remain at the Site pending completion of the Work; .2 Complete or correct the items directed by the Owner, and take actions necessary, or that the Owner may direct, for the protection and preservation of any stored materials and equipment and completed Work; .3 Remove its tools, equipment and construction machinery from the Site, and .4 Except as directed by the Owner, terminate all existing subcontracts and purchase orders related to the Work and enter into no further subcontracts or purchase orders therefor. § 14.4.3 Following written notice from the Owner of termination, the Owner may: .1 Take possession of the Site and of all materials and equipment thereon, and at the Owner's option, such temporary facilities, tools, construction equipment and machinery thereon rented by the Contractor that the Owner elects to utilize in completing the Work; .2 Accept assignment of subcontracts and purchase orders; and .3 Complete the Work by whatever reasonable method the Owner may deem expedient. § 14.4.4 In case of termination for the Owner's convenience, the Contractor will be entitled to compensation only for the following items: .1 Payment for acceptable Work performed up to the date of termination; .2 The costs of preservation and protection of the Work if requested to do so by the Owner; .3 The cost of terminating the following contracts including: 1. Purchased materials but only if not returnable and provided to the Owner, or the restocking or return charge, if any, if returnable at the Owner's written election; .4 Documented transportation costs associated with removing Contractor -owned equipment; and .5 Documented demobilization and close-out costs. The Contractor will not be compensated for the cost of terminating subcontracts, which must be terminable at no cost to the Owner if the Contract is terminated, except for those costs listed in Section 14.4.4.1 through 14.4.4.5. If the Owner and the Contractor are unable to agree upon the amounts specified in this subsection, the Contractor may submit a Claim as provided in Article 15. The Claim must be limited to resolution of the amounts specified in Subsections 14.4.4.1, 14.4.4.2, 14.4.4.3, 14.4.4.4 and 14.4.4.5 of this Subsection 14.4.4. No other cost, damages or expenses may be claimed or paid to the Contractor or considered as part of the Claim, the same being hereby conclusively and irrevocably waived by the Contractor. Any such Claim must be delivered to the Owner within thirty (30) days of the termination of the Contract and must contain a written statement setting forth the specific reasons and supporting calculations and documentation as to the amounts the Contractor claims to be entitled to under this Subsection as a result of the termination of the Contract. (Paragraph Deleted) § 14.4.5 The Contractor's obligations surviving final payment under the Contract, including without limitation those with respect to insurance, indemnification, and correction of Work that has been completed at the time of termination, remains effective notwithstanding termination for convenience of the Owner. (Pa/•agraph Deleted) ARTICLE 15 CLAIMS AND 1. ;DISPUTES § 15.1.1 DEFINITION A Claim is a written demand or assertion by one of the parties seeking, as a matter of right, payment of money, or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. The responsibility to substantiate Claims shall rest with the party making the Claim. AIA Document A201 TM —2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 45 reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (369ADA17) § 15.1.2 NOTICE OF CLAIMS Notice of circumstances that could give rise to a Claim must be given to the other party as soon as possible, to enable that party to take action as appropriate to lessen the impact of the potential Claim. The party recognizing a potential claim shall also explore all options and generate suggestions for how to avoid or overcome the impact of the circumstances. If damage cannot be avoided and unless provided otherwise by the Contract, Claims by either the Owner or Contractor must be initiated by written notice to the other party and to the Initial Decision Maker with a copy sent to the Architect, if the Architect is not serving as the Initial Decision Maker. Claims by either party must be initiated within ten days after occurrence of the event giving rise to such Claim or within ten days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. § 15.1.3 CONTINUING CONTRACT PERFORMANCE Pending final resolution of a Claim, except as otherwise agreed in writing or as provided in Section 9.7 and Article 14, the Parties shall proceed diligently with performance of the Contract in accordance with the Contract Documents. § 15.1.4 CLAIMS FOR ADDITIONAL COST If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4. § 15.1.5 CLAIMS FOR ADDITIONAL TIME § 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. §15.1.5.2 Contractor may request an extension of time to the Contract Schedule based on adverse weather conditions only if the following criteria are met: .1 The weather conditions are recorded on a daily basis at the Site. (Paragraph Deleted) .2 The weather conditions encountered exceed the previous 10 -year historical records for the general locality of the Project based on records of the Office of Environmental Data Service of the National Oceanic and Atmospheric Administration of the U.S. Department of Commerce nearest the site of the Project. .3 The weather conditions adversely impact the Contractor's performance of Work. 4 The adverse impact of the weather conditions cannot not be overcome by reasonable steps undertaken by Contractor, such as rescheduling Work or implementing measures to protect Work without additional expense to Contractor. .5 Contractor has notified Owner in writing whenever it reasonably anticipates future adverse weather conditions, or immediately upon encountering unanticipated adverse weather conditions. Contractor shall not only advise Owner of the anticipated impact of the adverse weather conditions, but shall also suggest to Owner steps which might be undertaken to avoid or lessen the impact of such conditions, so that Owner has sufficient information upon which to base a decision as to whether to employ such steps. 6 Owner shall promptly advise Contractor in writing if Owner wishes for Contractor to take any steps to avoid or lessen the impact of adverse weather conditions. If such steps require Contractor to incur additional costs, the Contract Sum shall be equitably adjusted as otherwise provided in this Contract. § 15.2 INITIAL DECISION § 15.2.1 Claims, excluding those arising under Sections 10.3 and 10.4, shall be referred to the Initial Decision Maker for initial decision. Except for those Claims excluded by this Section 15.2.1, an initial decision shall be required as a condition precedent to mediation of any Claim arising prior to the date final payment is due, unless 30 days have passed after the Claim has been referred to the Initial Decision Maker with no decision having been rendered. Unless AIA Document A201 TM —2007. Copyright© 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized AC reproduction or distribution of this AIA© Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) the Initial Decision Maker and all affected parties agree, the Initial Decision Maker will not decide disputes between the Contractor and persons or entities other than the Owner. § 15.2.2 The Initial Decision Maker will review Claims and within ten (10) days of the receipt of a Claim take one or more of the following actions: (1) request additional supporting data from the claimant or a response with supporting data from the other party, (2) reject the Claim in whole or in part, (3) approve the Claim, (4) suggest a compromise, or (5) advise the parties that the Initial Decision Maker is unable to resolve the Claim if the Initial Decision Maker lacks sufficient information to evaluate the merits of the Claim or if the Initial Decision Maker concludes that, in the Initial Decision Maker's sole discretion, it would be inappropriate for the Initial Decision Maker to resolve the Claim. § 15.2.3 In evaluating Claims, the Initial Decision Maker may, but shall not be obligated to, consult with or seek information from either party or from persons with special knowledge or expertise who may assist the Initial Decision Maker in rendering a decision. The Initial Decision Maker may request the Owner to authorize retention of such persons at the Owner's expense. § 15.2.4 If the Initial Decision Maker requests a party to provide a response to a Claim or to furnish additional supporting data, such party shall respond, within ten days after receipt of such request, and shall either (1) provide a response on the requested supporting data, (2) advise the Initial Decision Maker when the response or supporting data will be furnished or (3) advise the Initial Decision Maker that no supporting data will be furnished. Upon receipt of the response or supporting data, if any, the Initial Decision Maker will either reject or approve the Claim in whole or in part. § 15.2.5 The Initial Decision Maker will render an initial decision approving or rejecting the Claim, or indicating that the Initial Decision Maker is unable to resolve the Claim. This initial decision shall (1) be in writing; (2) state the reasons therefor; and (3) notify the parties and the Architect, if the Architect is not serving as the Initial Decision Maker, of any change in the Contract Sum or Contract Time or both. The initial decision shall be final and binding on the parties but subject to mediation and, if the parties fail to resolve their dispute through mediation, to further forms of dispute resolution available to the Parties in accordance with the Contract. § 15.2.6 Either party may file for mediation of a Claim at any time. (Paragraph Deleted) § 15.2.7 In the event of a Claim against the Contractor, the Owner may, but is not obligated to, notify the surety, if any, of the nature and amount of the Claim. If the Claim relates to a possibility of a Contractor's default, the Owner may, but is not obligated to, notify the surety and request the surety's assistance in resolving the controversy. (Paragraph Deleted) § 15.3 MEDIATION § 15.3.1 Claims, disputes, or other matters in controversy arising out of or related to the Contract except those waived as provided for in Sections 9.10.4, 9.10.5, and 15.1.6 shall be subject to mediation as a condition precedent to litigation in a court of competent jurisdiction. § 15.3.2 The parties shall endeavor to resolve their Claims by mediation administered by a neutral third party mediator in accordance with American Arbitration Association procedures in effect on the date the Claim is made. § 15.3.3 The parties shall share the mediator's fee and any filing fees equally. The parties will bear their own attorneys' fees, expert witnesses' fees, costs and expenses in the mediation. The mediation shall be held in the place where the Project is located, unless another location is mutually agreed upon. Agreements reached in mediation shall be enforceable as settlement agreements in any court having jurisdiction thereof. § 15.4 ARBITRATION § 15.4.1 Claims, disputes or other matters in controversy arising out of or related to this Agreement may, by mutual written agreement, be subject to arbitration. In the event the parties agree to utilize an arbitration process, it shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect as of the date of this Agreement. A request for arbitration shall be made in writing, delivered to the other party, and must contain all Claims then known to that party on which arbitration is permitted. In the event that AIA Document A201 TM — 2007. Copyright ©1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 47 reproduction or distribution of this AIA° Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the t maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3139ADA17) the other party is not willing to submit the matter to arbitration, the dispute shall be resolved through the judicial forum available to the parties. § 15.4.1.1 A request for arbitration shall be made no earlier than concurrently with the filing of a request for mediation, but in no event shall it be made after the date when the institution of legal or equitable proceedings based on the Claim would be barred by the applicable statute of limitations. For statute of limitations purposes, receipt of a written request for arbitration by the person or entity administering the arbitration shall constitute the institution of legal or equitable proceedings based on the Claim. § 15.4.1.2 Pending resolution of any controversy, claim or dispute arising out of this Agreement, the Contractor must proceed diligently with the performance of the Work under this Agreement. § 15.4.2 If the parties mutually agree to arbitration, the award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. § 15.4.3 The agreement to arbitrate and other agreements to arbitrate with an additional person or entity duly consented to by parties to the Agreement shall be specifically enforceable under applicable law in any court having jurisdiction thereof. § 15.4.4 CONSOLIDATION OR JOINDER § 15.4.4.1 Either party, at its sole discretion, may consolidate an arbitration conducted under this Agreement with any other arbitration to which it is a party provided that (1) the arbitration agreement governing the other arbitration permits consolidation, (2) the arbitrations to be consolidated substantially involve common questions of law or fact, and (3) the arbitrations employ materially similar procedural rules and methods for selecting arbitrator(s). § 15.4.4.2 Either party, at its sole discretion, may include by joinder persons or entities substantially involved in a common question of law or fact whose presence is required if complete relief is to be accorded in arbitration. § 15.4.4.3 The Owner and Contractor grant to any person or entity made a party to an arbitration conducted under this Section 15.4, whether by joinder or consolidation, the same rights of joinder and consolidation as the Owner and Contractor under this Agreement. 1. ARTICLE 16 EQUAL OPPORTUNITY AIA Document A201 TM — 2007. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The American Init. Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized 48 reproduction or distribution of this AIV Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:18:10 on 05/17/2016 under Order No. 0080255486 which expires on 05/17/2017, and is not for resale. User Notes: (3B9ADA17) ARTICLE 16 EQUAL OPPORTUNITY § 16.1 The Contractor shall have a policy to provide equal employment opportunity in accordance with all applicable state and federal anti -discrimination laws, regulations, and contracts. Contractor shall not refuse employment to a person, bar a person from employment, or discriminate against a person in compensation or in a term, condition, or privilege of employment because of race, color, religion, creed, political ideas, sex, age, marital status, national origin, actual or perceived sexual orientation, gender identity, physical or mental disability, except when the reasonable demands of the position require an age, physical or mental disability, marital status or sex distinction. The Contractor shall require these nondiscrimination terms of its Subcontractors. Init AIA Document A201— 2007 — Sports Park, Bozeman MT 49