Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Shawn Kohtz, Project Engineer Rick Hixson, City Engineer
SUBJECT: Golden Gate Condos Site Plan: Sewer and Water Pipeline and Access
Easement and Agreement
MEETING DATE: August 15, 2016
AGENDA ITEM TYPE: Consent Agenda
RECOMMENDATION: Authorize City Manager to sign
BACKGROUND: Attached are copies (original to Robin Crough), of the partially executed
Sewer and Water Pipeline and Access Easement and Agreement required
as a condition of the Golden Gate Condos Site Plan. Engineering staff has
reviewed the easement and found it to be acceptable.
FISCAL EFFECTS: N/A
ALTERNATIVES: As suggested by the City Commission.
Attachments: Sewer and Water Pipeline and Access Easement and Agreement.
Report compiled on: 8/1/16